Bluegrass Concrete Construction Co. v. Commonwealth

664 S.W.2d 936, 1983 Ky. App. LEXIS 322
CourtCourt of Appeals of Kentucky
DecidedAugust 19, 1983
StatusPublished
Cited by1 cases

This text of 664 S.W.2d 936 (Bluegrass Concrete Construction Co. v. Commonwealth) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bluegrass Concrete Construction Co. v. Commonwealth, 664 S.W.2d 936, 1983 Ky. App. LEXIS 322 (Ky. Ct. App. 1983).

Opinion

HOWARD, Judge.

This appeal is from a dismissal in Franklin Circuit Court of a contractor’s claim against the Department of Highways on the basis that the contractor failed to file a claim within the one-year statute of limitations provided in K.R.S. 45A.260.

On July 12, 1979, appellant Bluegrass Concrete Construction Company entered into a contract with appellee Department for construction of the Kentucky 467 Sparta-Glencoe road and approaches in Gallatin County. Appellant states that Bluegrass relied on its bid on plans for construction furnished by the appellee Department which included information that an L & N railroad track adjacent to the construction site had a 16V2 foot right-of-way from the center of the track. After the project started, appellant states that they discovered the right-of-way was in fact 33 feet and construction therefore included excavation on the L & N railroad right-of-way. Appellant alleges in the complaint and statement of facts in their brief that they incurred additional expenses in order to complete the project on time. They were required by L & N Railroad to install shoring and cribbing materials to shore up the railroad right-of-way and were additionally required by their insurer to purchase railroad protective liability insurance. Appellant Bluegrass wrote appellee on October 23, 1979, and October 26, while the work was in progress, concerning the problem, and again made claim for additional payment after completion of the work prior to final payment under the contract. The disputed sum was $8,211.48. The appellee apparently denied liability for additional costs but agreed to pay for the railroad liability insurance appellant had to purchase.

On June 17, 1980, the appellee issued a document titled Formal Acceptance Report of Completed Construction citing May 15, 1980, as the date on which all work on the project was completed. Appellant continued to write employees of the appellee concerning resolution of the claim of additional [937]*937compensation including letters on September 25, 1980, November 19,1980, and February 9,1981. On March 11,1981, R.L. Guidi, the district construction engineer for appel-lee, sent a letter to appellant which stated, “The Department of Transportation, Division of Construction Claims Committee has reviewed and hereby denies your claim .... As a final administrative action, you may appeal this decision directly to Mr. Dean Huff, Commissioner of Highways. In the event of further rejection at that level, your last option would be to seek recourse in a court of law.”

Thereafter, appellant sent a petition of appeal to Dean Huff. Appellant wrote Dean Huff on December 18, 1981, and June 15,1982, requesting information concerning disposition of the case. On June 30, 1982, Dean Huff, on behalf of appellee, denied appellant’s claim for additional compensation but agreed to pay reimbursement for purchase of the railroad liability protective insurance.

Appellant filed a complaint in Franklin Circuit Court on September 9,1982, against appellee Commonwealth of Kentucky, Bureau of Highways, Department of Transportation (now Transportation Cabinet, Department of Highways). The appellee Department filed a motion to dismiss on September 30, 1982, alleging that the court lacked jurisdiction of the subject matter of the case as the statute of limitations on filing the suit had run and further alleging insufficiency of process and insufficiency of service of process as the appellant Bluegrass had failed to serve the Attorney General or Assistant Attorney General under CR 4.04(6).

After hearing the motion to dismiss, on October 19, 1982, Franklin Circuit Court Judge Henry Meigs II entered an opinion and order dismissing the complaint on the basis that appellant Bluegrass failed to timely file the complaint and therefore the court lacked jurisdiction to hear the matter. It is from that order that appellant appeals. We affirm.

The appellant initially argues that the trial court erred by concluding that it lacked jurisdiction due to the failure of appellant to timely file the claim. K.R.S. 45A.245 through 260 sets out the procedures whereby any person, firm or corporation with a lawful contract with the Commonwealth may bring an action regarding the contractual relationship. The action shall be brought in Franklin Circuit Court and K.R.S. 45A.260 specifies:

Limitations on claims. Any such claim shall be commenced in Franklin Circuit Court within one (1) year from the date of completion specified in the contract.

There have been two cases decided by this Court that interpret this clause. The appellant relies on Codell Construction Co. v. Commonwealth, Ky.App., 566 S.W.2d 161 (1977), and the appellee relies on H.E. Cummins & Sons Construction Co. v. Turnpike Authority, Ky.App., 562 S.W.2d 651 (1977). In Codell, a contractor sought additional compensation for work performed for the Commonwealth. The appellant asked for the additional funds on February 28, 1969, and presented the claim to both the district engineer and the Commissioner of Highways. On February 17, 1972, almost three years later, the contractor was advised of what the Commonwealth was willing to pay. Codell then sued in Franklin Circuit Court on January 5, 1973. The Commonwealth moved to dismiss alleging that the claim was barred by a one-year statute of limitations in K.R.S. 44.310, the predecessor to K.R.S. 45A.260. The Court of Appeals held at page 165 that:

This claim was made in a timely fashion and the trial court was correct in not dismissing the matter because of the statute of limitations provision of KRS 44.-310. The cause of action did not arise until February 17, 1972, when the Commonwealth advised the Appellant of what it was willing to pay.

The appellant argues that his cause of action did not arise until June 30, 1982, when the Bureau of Highways notified ap[938]*938pellant of its intent to pay the insurance costs and deny payment of the additional work costs.

The appellee argues that the case of H.E. Cummins, supra, controls the result in this situation. The Cummins case was decided a week after the Codell decision and appears to have an opposite result. On page 653 of the decision in H.E. Cummins, the court holds:

We conclude that the Turnpike Authority is an agency of the Commonwealth and that any contract action against the Turnpike Authority must be brought pursuant to the provisions of the Contract Claims Act.
[[Image here]]
Without regard to the question of sovereign immunity, the legislature has the express power to enact legislation fixing venue and limitations for all actions including contract actions brought against an agency of the Commonwealth. Ky. Const., § 231. In its action against the Turnpike Authority, Cummins was bound by the limitations provided by KRS 44.-310.

K.R.S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jasper Contracting Co. v. Commonwealth
890 S.W.2d 296 (Court of Appeals of Kentucky, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
664 S.W.2d 936, 1983 Ky. App. LEXIS 322, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bluegrass-concrete-construction-co-v-commonwealth-kyctapp-1983.