Bluefield Armature Company, a Corporation v. R. G. Pope Construction Company, a Corporation

548 F.2d 484, 1976 U.S. App. LEXIS 6439
CourtCourt of Appeals for the Fourth Circuit
DecidedNovember 2, 1976
Docket75-1908
StatusPublished
Cited by2 cases

This text of 548 F.2d 484 (Bluefield Armature Company, a Corporation v. R. G. Pope Construction Company, a Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bluefield Armature Company, a Corporation v. R. G. Pope Construction Company, a Corporation, 548 F.2d 484, 1976 U.S. App. LEXIS 6439 (4th Cir. 1976).

Opinion

PER CURIAM:

This diversity case arose out of repairs on a 500 horsepower electric motor performed by Bluefield Armature Company (Bluefield) for R. G. Pope Construction Company (Pope), the owner of the motor.

The trial was to the court without a jury. The only questions are whether the judge’s findings of fact were clearly erroneous as they found the motor was properly repaired, and whether the trial court erred in holding that, after it had found that the repairs done to the motor were performed in a skillful and workmanlike manner, the burden was then on Pope, if it were to escape liability on the account and prevail in a counterclaim for consequential damages, to prove that the repairs had been performed with defective workmanship. We affirm.

The motor in question had been installed some time previous to the times relevant here. It burned out July 12, 1973, and, upon being repaired and having run a few days, more trouble was encountered on July 25,1973. This sequence was repeated twice in August, until, after more trouble near the end of September, the motor was not repaired again. Some months later, Blue-field brought suit on the account to collect the repair charges. Pope denied liability for the charges and filed its counterclaim.

The trial court stated into the record its findings of fact and conclusions of law, which are copied here:

“THE COURT:
Therefore, at this time I am going ahead and state to you orally what I find the facts to be and conclusions of law. Now since I have not written these down I want you gentlemen to pay particular attention to what the Court has to say because after I finish I’ll then attempt to answer any additional facts which you gentlemen might feel that I have not covered.
“This is basically an action on contract for the repairing and rebuilding of an electric motor. The Answer filed by the Defendant and the Counterclaim filed by the Defendant raises the question as to why the motor was burned up on several occasions and the Answer also questions the propriety of the invoices that were presented by the Plaintiff for the work performed.
“Now there’s no question but what the Plaintiff implied a warranty and perhaps by an expressed warranty, I believe the invoice says, ‘Prompt Service’, ‘All Work Guaranteed’. But anyway, there’s no question but what they’ve implied warranty that the work which the Plaintiff undertook to perform would be performed in a skillful and workmanlike manner. The Defendant says that the Plaintiff failed to properly repair and rewind the motor. The Plaintiff says that the work was performed in a skillful and workmanlike manner.
“I don’t think there is a great amount of conflict in the evidence. There is some variation as to the opinions expressed by the experts, but the evidence as to what actually happened is not too much in conflict. Now I find that the Plaintiff had no *486 control over the source of power, had nothing to do with the startup mechanism or the equipment for starting up the motor, had no control over the protective or safety devices insofar as this machine was concerned and was not responsible for the hookup of the motor to the source of power.
“I find persuasive the testimony of both Mr. Mattox and Mr. Shrewsbury that the motor was properly rewound and that all tests required to be run were run at the plant on the repaired motor and each time the tests showed that the motor to be in proper working order, or when it left* the plant. I find as particularly persuasive Plaintiff’s Exhibits numbered 9 and 10. Number 9 is a letter from Mr. Shrewsbury to Mr. Pope dated December the 7th, 1973, at which time he indicated what the amount of the bill was, he indicated a willingness to accept payment of $11,740.64 at that time; he said it left a balance of $23,436.91; that he would be willing to carry this amount for a period of 90 days, but that he would have to have interest at the rate of 1V2% per month for the 90-day period.
“I find as particularly significant the fact that Mr. Pope for a long period of time did not answer this letter, did not deny anything set forth in the letter, and, the letter itself was confirming a telephone conversation that had taken place between Mr. Shrewsbury and Mr. Pope.
“And then Plaintiff’s Exhibit Number 10, the letter dated November the 27th, 1973, from Mr. Pope to Appalachian Power Company indicating at that time he did not question but what the work on each occasion had been performed in a satisfactory workmanlike manner. At that time he blamed Appalachian Power Company for the trouble. Now I think that he thought at that time Appalachian was at fault.
“I think that from the discovery depositions that have been taken and the evidence that he has heard and investigation, that he is truthful in now saying he thinks that Appalachian was not at fault.
“I think that the Plaintiff carried the burden of proof by its testimony that the work each time was performed at the request of the Defendant, that the work was performed in a skillful and workmanlike manner, that each time the work was tested before the machine was sent back. I’m frank to say I do not know what caused the machine, or the motor, to burn up on these four or five different occasions, but I believe the burden of proof then was shifted to the Defendant to show in what way that the work was not performed in a workmanlike manner.
“Therefore, with these findings of fact, I conclude that the Plaintiff, as a matter of law, is entitled to recover in this action and that it has proven its damages in the amount of $23,436.99. I think under the law of the Commonwealth of Virginia that the Plaintiff would also be entitled to recover interest on that amount from December the 7th, 1973, until paid. And I cannot allow interest at 1V2% per month. I think the Plaintiff would be entitled to recover interest at the rate of 8% from December the 7th, 1973.
“Now, if the Court is wrong as to the burden of proof and if Mr. Roberts is right that this is a res ipsa situation and that the burden shifted over to the Plaintiff to show the exact cause of the burn-up of the engine, then the Plaintiff would not be entitled to recover and I certainly invite Mr. Roberts to take an appeal to the Fourth Circuit if he feels the Court is wrong as to the burden of Proof.
“The Court is of the opinion that the work was performed in a skillful and workmanlike manner; that there has been no showing that the motor burned up because of defective workmanship on — because of any of the work performed by the Plaintiff. Therefore, it is the conclusion of this Court that the Plaintiff is entitled to recover in the amount that I have stated and judgment will be entered for the Plaintiff in that amount.
“It goes without saying, since the Plaintiff is entitled to recover, that the Court feels that the Counterclaim is without merit and a judgment will be entered in favor of *487 the Plaintiff on the Counterclaim of the Defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Estelle W. Sligh v. John Doe
596 F.2d 1169 (Fourth Circuit, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
548 F.2d 484, 1976 U.S. App. LEXIS 6439, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bluefield-armature-company-a-corporation-v-r-g-pope-construction-ca4-1976.