THIS OPINION HAS NO PRECEDENTIAL VALUE. IT SHOULD
NOT BE CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING EXCEPT AS PROVIDED
BY RULE 239(d)(2), SCACR.
THE STATE OF SOUTH CAROLINA
In The Court of Appeals
Victor L. Blue and Gail V. Blue,
Respondents,
v.
Larry Harrelson and Nancy Harrelson d/b/a Angle Construction Company,
Appellants.
Appeal From Florence County
B. Hicks Harwell, Jr., Circuit Court
Judge
Unpublished Opinion No. 2004-UP-656
Submitted November 1, 2004 Filed December
22, 2004
AFFIRMED
Kenneth E. Merriman, of Florence, for Appellants.
Daryl James Corbin, of Florence, for Respondents.
PER CURIAM: In this action to recover damages
arising from a construction contract, Larry Harrelson and Nancy Harrelson, d/b/a
Angle Construction Company (the Harrelsons), appeal the trial judges entry
of judgment in favor of Victor L. Blue and Gail Blue (the Blues). We affirm.
[1]
FACTS
The Blues entered into a construction
contract with the Harrelsons on April 6, 1999. The Harrelsons agreed to complete
construction of the Blues home no later than 265 days from the date of the
contract for a purchase price of $340,000. In addition, the parties negotiated
a late-fee provision of $120 per day after December 28, 1999, if the home was
not complete. The Harrelsons never completed the home. During this time period,
the Blues were also subjected to litigation with the Shaw Lumber Company and
forced to refinance their home due to the Harrelsons failure to satisfy an
account that was designated for the Blues construction project.
On November 22, 2000, the Blues filed this action, alleging breach of contract
with fraudulent intent, negligence, breach of fiduciary duty, and civil conversion.
Underlying these causes of action, the Blues primarily asserted the Harrelsons
breached the contract by: (1) failing to complete the construction within the
designated 265-day time period; (2) failing to construct the home in a workmanlike
manner; and (3) failing to pay the material suppliers and subcontractors involved
in the project. The Blues sought relief of $150,000 in actual damages and $150,000
in punitive damages.
Because the Harrelsons failed to answer or respond to the pleadings, the trial
judge entered an order of default on February 14, 2001. This order provided
that all allegations contained within the Plaintiffs pleadings are deemed
true. The judge denied the Harrelsons motion to set aside the entry of default.
The judge then held a hearing solely on the amount of damages.
The judge found the
Blues were entitled to an award of actual damages for completion costs of construction
in a proper manner, reputational harms and damages, and emotional distress.
The judge also concluded the Blues were entitled to additional damages under
its breach of contract theory given the [Harrelsons] violation of the late-fee
provision for some of the period of time between December 28, 1999, and May
1, 2001. The judge entered judgment in the amount of $50,000 for breach of
contract, violation of the late-fee penalty provision, negligence, breach of
fiduciary duties, and civil conversion. The judge denied the Blues
request for punitive damages.
Subsequently, the Harrelsons filed
a motion pursuant to Rule 59(e), SCRCP. The judge denied the motion
and affirmed his previous ruling, explaining:
In considering damages, the Court based its consideration
on the causes of action contained in the Plaintiffs complaint: breach of contract,
breach of fiduciary duty, negligence, conversion and emotional and reputational
harm. The Courts consideration of damages was also based on the following:
delay in not complying with the construction completion date which was provided
for in the contract, injury to the Plaintiffs credit standing, including refinancing
with increased interest on the loan, assorted tools, including but not limited
to, saws, hammers and paint brushes that were charged to the Plaintiffs but
were never given to them, and those items charged to the building site that
were not found in the construction.
The Harrelsons appeal.
STANDARD OF REVIEW
This case presents
an action at law. See Roberts v. Gaskins, 327 S.C. 478, 483, 486
S.E.2d 771, 773 (Ct. App. 1997) (stating an action for a breach of contract
seeking money damages is an action at law); see also Corley v. Ott,
326 S.C. 89, 92 n.1, 485 S.E.2d 97, 99 n.1 (1997) (recognizing an action for
breach of fiduciary duty is an action at law); Advance Intl, Inc. v. North
Carolina Natl Bank of South Carolina, 316 S.C. 266, 271, 449 S.E.2d 580,
583 (Ct. App. 1994), affd in part and vacated in part, 320 S.C. 532,
466 S.E.2d 367 (1996) (action alleging, inter alia, fraud and negligence and
seeking damages is one at law); Blackwell v. Blackwell, 289 S.C. 470,
471, 346 S.E.2d 731, 732 (Ct. App. 1986)(An action for damages for conversion
is an action at law.). In an action at law, tried without a jury, our scope
of review extends merely to the correction of errors of law. Crary v. Djebelli,
329 S.C. 385, 388, 496 S.E.2d 21, 23 (1998). Thus, the trial judges factual
findings will not be disturbed on appeal unless a review of the record discloses
that there is no evidence which reasonably supports the judges findings. Id.;
Townes Assocs., Ltd. v. City of Greenville, 266 S.C. 81, 86, 221 S.E.2d
773, 775 (1976).
DISCUSSION
I.
The Harrelsons argue the trial judge erred
in failing to dismiss the Blues causes of action for civil conversion, negligence,
and breach of fiduciary duty. As to each cause of action, the Harrelsons contend
the Blues failed to prove damages. In conjunction with their civil conversion
argument, the Harrelsons claim there is no evidence to support the judges finding
that the Blues were damaged by the Harrelsons charging tools and materials to
an account with the Shaw Lumber Company, which was designated for the Blues
construction project.
To the extent the Harrelsons challenge
their liability, we find they are precluded from raising these issues due to
the entry of default. Because the Harrelsons were found in default,
they are deemed to have admitted the truth of the Blues allegations and conceded
liability. See Roche v. Young Bros., Inc., of Florence, 332 S.C.
75, 81, 504 S.E.2d 311, 314 (1998) (It is well settled that by suffering a
default, the defaulting party is deemed to have admitted the truth of the plaintiffs
allegations and to have conceded liability.); Howard v. Holiday Inns, Inc.,
271 S.C. 238, 242, 246 S.E.2d 880, 882 (1978) (By defaulting, a defendant forfeits
his right to answer or otherwise plead to the complaint. In essence, the defaulting
defendant has conceded liability. However, a defaulting defendant does not
concede the amount of liability.) (citation omitted).
Despite the entry of default, the Harrelsons may
raise, as they have done, issues regarding the sufficiency of the Blues pleadings
and their entitlement to damages under each cause of action. See Masters
v. Rodgers Dev. Group, S.C., 283 S.C. 251, 254, 321 S.E.2d 194, 196 (Ct.
App. 1984) (holding defendant found in default was not precluded from challenging
the sufficiency of the plaintiffs complaint as a basis for judgment); see
also Mut. Sav. & Loan Assn v. McKenzie, 274 S.C. 630, 632, 266
S.E.2d 423, 424 (1980) (A party seeking a default judgment is entitled to only
such relief as is framed by his pleading . . . It follows that if a complaint
fails to state a cause of action, the rendering of a default judgment thereon
is without authority of law and therefore reversible error.). As will be discussed,
we find the Blues properly pled the alleged causes of action and there is evidence
to support the trial judges award of damages under each theory.
A.
Conversion has been defined as
the unauthorized assumption and exercise of the right of ownership over goods
or personal chattels belonging to another, to the alteration of the condition
or the exclusion of the owners rights. Powell v. A.K. Brown Motor Co.,
200 S.C. 75, 78, 20 S.E.2d 636, 637 (1942). Furthermore, [c]onversion may
arise by some illegal use or misuse, or by illegal detention of anothers personal
property. Regions Bank v. Schmauch, 354 S.C. 648, 667, 582 S.E.2d 432,
442 (Ct. App. 2003).
A review of the Blues complaint
reveals that they sufficiently pled a cause of action for civil conversion.
Specifically, the Blues alleged they entrusted funds to the Harrelsons which
were supposed to have been used solely for satisfaction of labor and materials
costs involving construction of their home. They further asserted the Harrelsons
intentionally took the Blues money and used it for their own personal benefit
to the Blues detriment. Finally, the Blues alleged the Harrelsons converted
approximately $50,000 of the Blues money and have failed to return it to them.
Not only did the Blues properly plead
a cause of action for civil conversion, there is also evidence in the record
to support their entitlement to damages under this cause of action. Mr. Blue
testified concerning their damages, which were outlined in a summary that was
admitted into evidence. He testified the Harrelsons misused construction
funds to purchase tools and materials that were not used in the construction
of the home. Thomas Robertson, a construction inspector, reviewed the invoices
from the Shaw Lumber Company and confirmed that items were designated for the
Blues construction projection but were not in fact used for the home. Robertson
concluded that missing construction materials and tools worth $4,632.96 were
inappropriately charged to the Blues account. Mrs. Harrelson admitted the
tools, valued at $1,513.22, were never given to the Blues. She also testified
that she understood that by charging these items to the Shaw Lumber account
and specifying that they were to be used for the Blues construction, the Blues
would be subject to litigation if the invoices were not paid. She acknowledged
the Blues were sued by Shaw Lumber Company and required to satisfy the debt.
Mr. Blue testified they paid Shaw Lumber Company $55,000 in order to release
the lien.
B.
To state a cause of action for negligence, the
plaintiff must allege facts that demonstrate: (1) a duty of care owed by the
defendant to the plaintiff; (2) a breach of that duty by negligent act or omission;
(3) resulting damages to the plaintiff; and (4) the damages proximately resulted
from the breach of that duty. Thomasko v. Poole, 349 S.C. 7, 11, 561
S.E.2d 597, 599 (2002). In their complaint, the Blues alleged the Harrelsons
owed the Blues a duty to construct the house in a workmanlike manner and failed
to do so. As part of this cause of action, the Blues incorporated other provisions
of their complaint. In paragraphs six and seven of the complaint, the Blues
outlined the construction deficiencies and alleged the failure of the Harrelsons
to correct the deficiencies despite being ordered to do so by the South Carolina
Residential Builders Commission. Furthermore, the Blues claimed that [d]ue
to the Harrelsons negligence, the Blues have incurred and will continue to
suffer from severe financial, emotional, and repuational harms and damages.
Therefore, we find the Blues sufficiently stated a cause of action for negligence.
There is also evidence supporting the Blues entitlement
to damages pursuant to their cause of action for negligence. During the presentation
of their case, the Blues offered the testimony of Robertson and John Kendall,
an investigator/inspector with the South Carolina Residential Home Builders
Commission (the Commission). Kendall testified concerning the deficiencies
in the Harrelsons workmanship. Based on his inspection, Kendall compiled two
reports, which listed items that needed to be corrected to the Blues home because
the work that was performed violated construction standards and building codes.
The Commission also issued an order, pursuant to its review of the Blues complaint,
in which it prohibited the renewal of Mr. Harrelsons building license until
the deficient work was corrected. Robertson also testified regarding
construction items that were either incomplete or not satisfactorily completed.
As a result of these alleged deficiencies, Robertson testified about the costs
incurred by the Blues to correct the construction problems, which included warped
hardwood floors and roof flashing problems. Furthermore, in explaining
the damage summary exhibit, Mr. Blue testified about the damages that he and
his wife incurred due to the defective construction.
C.
In terms of the Blues cause of action for breach
of fiduciary duty, it is well-settled equitable rule that anyone acting in
a fiduciary relationship shall not be permitted to make use of that relationship
to benefit his own personal interests. Island Car Wash, Inc. v. Norris,
III, 292 S.C. 595, 599, 358 S.E.2d 150, 152 (Ct. App. 1987); see
Hendricks v. Clemson Univ., 353 S.C. 449, 458, 578 S.E.2d 711, 715 (2003)
(Historically, this Court has reserved imposition of fiduciary duties to legal
or business settings, often in which one person entrusts money to another.).
In support of this cause of action, the Blues properly alleged that they entrusted
the Harrelsons with their construction funds; and the parties had a special
fiduciary relationship during the construction project. Accordingly, the Harrelsons
had a fiduciary relationship with the Blues and were required to use the construction
funds solely to satisfy costs involving the Blues project. The Blues further
asserted that the Harrelsons owed the Blues duties of honesty, loyalty, and
fair-dealing, and that they breached their fiduciary duty by taking their
construction funds and using the money for purposes other than paying the Blues
construction costs. The complaint further stated, [a]s a proximate result
and consequence of the Harrelsons breach of fiduciary duties, the Blues have
incurred and will continue to suffer from substantial additional construction
and repair costs, financing and interest expenses, litigation costs, and emotional
and reputational harms and damages.
As to damages, there is evidence in the record
to support the trial judges conclusion that the Blues were entitled to recover
under their cause of action for breach of fiduciary duty. As previously discussed,
the Blues, through their own testimony and that of Robertson, established that
the Harrelsons inappropriately charged materials and tools at the Shaw Lumber
Company and designated them for the Blues construction project. Mrs. Harrelson
admitted that the tools were never given to the Blues. Although the Harrelsons
were aware of the financial repercussions to the Blues, they did not satisfy
the outstanding invoices. Due to the Harrelsons actions, the Blues had to
pay Shaw Lumber $55,000 to obtain a release of their home and avoid foreclosure.
II.
The Harrelsons assert the trial court
erred in assessing damages based on the penalty provision of the construction
contract. They contend the provision is unenforceable because it is not based
on a consideration of actual damages and it is excessive.
The Harrelsons are correct that where
a contract provision is not based upon contemplated actual damages, but is intended
to provide punishment for breach of contract, it is a penalty. See Moser
v. Gosnell, 334 S.C. 425, 431-32, 513 S.E.2d 123, 126 (Ct. App. 1999) (The
test for determining whether a stipulation constitutes a penalty is whether
the sum stipulated is so large that it is plainly disproportionate to any probable
damage resulting from breach of the contract. (quoting Tate v. LeMaster,
231 S.C. 429, 442, 99 S.E.2d 39, 46 (1957))). However, because the Harrelsons
failed to answer or respond to the Blues complaint, they have waived any challenge
to this provision. See D & D Leasing Co. of South Carolina, Inc.
v. Lipson, 305 S.C. 540, 542, 409 S.E.2d 794, 796 (Ct. App. 1991) (Unenforceability
based on a penalty theory is an affirmative defense that must have been pled.).
III.
The Harrelsons argue the trial
judges orders were insufficient under Rule 52(A), SCRCP, to determine the basis
for the award of actual damages in the amount of $50,000.
Rule 52(a) of the South Carolina Rules of Civil Procedure
provides, [i]n all actions tried upon the facts without a jury or with an advisory
jury, the court shall find the facts specially and state separately its conclusions
of law thereon. Our supreme court has held that:
this requirement to be directory and that noncompliance
would not form the basis for invalidating a judgment. Rather, where a trial
court substantially complies with Rule 52(a) and adequately states the basis
for the result it reaches, the appellate court should not vacate the trial courts
judgment for lack of an explicit or specific factual finding.
Noisette v. Ismail, 304 S.C. 56, 58, 403 S.E.2d
122, 123-24 (1991)(citations omitted).
Because we find the trial judges
order entering judgment and the order denying a new trial substantially complied
with the requirements of Rule 52(a), we decline to invalidate the judgment in
favor of the Blues. In the initial order, the judge made eight specific findings
of fact and then found the Blues were entitled to actual damages under each
cause of action. In the order denying the Harrelsons motion for a new trial,
the judge affirmed his previous ruling and explained the basis for his award
of damages. See In re: Treatment and Care of Luckabaugh, 351
S.C. 122, 133, 568 S.E.2d 338, 343 (2002) (We do not require a lower court
to set out findings on all the myriad factual questions arising in a particular
case. But the findings must be sufficient to allow this Court, sitting in its
appellate capacity, to ensure the law is faithfully executed below.) (citation
omitted). Although the judge did not delineate the amount of damages for each
cause of action, we find this omission does not mandate an invalidation of the
judgment in favor of the Blues. As will be discussed, there is evidence to
support the amount of damages awarded to the Blues.
IV.
Finally, the Harrelsons argue the trial judge erred
in awarding the Blues $50,000 in damages.
The plaintiff has the burden of proving damages
for a breach of contract action. Jackson v. Midlands Human Resources Ctr.,
296 S.C. 526, 528, 374 S.E.2d 505, 506 (Ct. App. 1988). Specifically, this
Court has stated:
In a default case, the plaintiff must prove by competent
evidence the amount of his damages, and such proof must be by a preponderance
of the evidence. Although the defendant is in default as to liability, the
award of damages must be in keeping not only with the allegations of the complaint
and the prayer for relief, but also with the proof that has been submitted.
Id. at 529, 374 S.E.2d at 506 (citation omitted).
Initially, we note the Harrelsons assert the Blues
are only entitled to $4,297.98 in damages, which represents the amount needed
to complete the construction in excess of the original contract price of $340,000. [2] This assertion, however, confines
the Blues damages solely to their breach of contract action. Because the Blues
sought to recover under several other causes of action, as their attorney reiterated
during the hearing, their damages would not be limited to this amount.
Turning to the testimony and evidence presented
by the Blues, Mr. Blue testified they suffered $173,990.57 in actual damages.
These damages were itemized on a summary sheet that was entered into evidence
during Mr. Blues testimony. [3]
The contract required the Harrelsons to comply
with all building laws and applicable building codes of Dillon County and of
the State of South Carolina. However, Kendall, who investigated the Blues
complaint against the Harrelsons for the Commission, concluded that construction
of the home violated the standard building practices, codes, regulations, and
standards. Robertson, who the Blues hired as an expert to inspect the construction,
testified there were problems with several contract items, which included the
front porch, painting, fixtures, warped hardwood floors, and roof flashing.
As to the cost of correcting and completing these items, Mr. Blue testified
they paid $13,138.98. He further stated the cost of completing construction
on the Blues home was estimated at $9,650 for work on the porches, shower units,
window screens, light wiring, as well as other items.
In addition, Mr. Blue testified concerning the
Harrelsons use of the construction account at Shaw Lumber Company to purchase
tools and materials not used in the Blues home. Robertson, who had forty-two
years of experience in construction and held South Carolina General Contractors
and Residential Home Builders licenses, examined the Shaw Lumber invoices and
determined $4,632.96 in missing construction materials and tools was charged
to an account at Shaw Lumber, which was designated for the Blues construction
project. Because the Harrelsons did not pay the Shaw Lumber invoices as agreed
upon by the parties in the contract, Shaw Lumber sued the Blues for the balance
of the account. The Blues had to pay Shaw Lumber $55,000 to obtain a release
from this debt. Mrs. Harrelson acknowledged this debt and the financial repercussions
could have been avoided had the Harrelsons satisfied the charges as stipulated
by the contract between the parties.
Due to the Shaw Lumber Company debt and resulting
litigation, the Blues testified their credit rating was adversely affected.
Additionally, the Blues original mortgage holder, NBSC, began foreclosure.
The Blues were then forced to obtain financing at a higher interest rate from
another financial institution. They paid an application fee of $300 and closing
costs of $3,912.40 to First Citizens Bank where the Blues eventually obtained
financing for a second mortgage. Aside from the above-outlined tangible damages,
Mr. Blue also testified they suffered emotional damages in the amount of $50,000.
Mrs. Blue, a mental health counselor, testified regarding the specifics of the
emotional damages. She claimed that as result of the financial problems she
was anxious and had migraine headaches for which she took medication. She further
testified her husband became irritable, experienced headaches, and had trouble
sleeping.
Finally, the construction contract provided for
a late-fee of $120 per day if the Harrelsons failed to complete the Blues home
in the allotted 265-day time period. Because the project was not completed
as agreed upon by the parties, Mr. Blue testified the Harrelsons accrued a late
fee of $58,680.00 for the 489 days between December 28, 1999 and May 1, 2001,
the day the Blues obtained financing to complete the project. Based on the
foregoing, we find there is evidence in the record to support the trial judges
award of actual damages to the Blues in the amount of $50,000.
CONCLUSION
We find the Blues properly pled each cause
of action raised in their complaint and presented evidence in support of their
entitlement to damages. We hold the trial judges order awarding damages to
the Blues was sufficient and there is evidence to support his award of damages
in the amount of $50,000. Accordingly, the decision of the trial judge is
AFFIRMED.
HUFF, KITTREDGE, and BEATTY, JJ., concur.
[1] Because oral argument would not aid the court in resolving the issues
on appeal, we decide this case without oral argument pursuant to Rule 215,
SCACR.
[2] The Harrelsons base this amount on the following
calculation:
Paid by the Blues directly to the Harrelsons
$ 266,500.00
Paid by the Blues to Shaw Lumber Company
55,000.00
Construction cost paid directly by the Blues
13,138.98
Construction cost to complete the contract
9,650.00
$
344,297.98
[3] The following is an abbreviated version of the
Blues damage summary:
Construction Costs Paid by the Blues
$ 13,138.98
Construction Completion Costs
9,650.00
Items Missing Charged By Harrelsons to
Blues
4,632.96
Mortgage Refinancing
Costs
22,893.63
Liens, Attorneys Fees, and Litigation
Expenses 64,995.00
Contract Damages (Late Penalty: $120/day
x 489) 58,680.00
Emotional/Reputational Damages
50,000.00
$ 173,990.57