Blue v. Harrelson

CourtCourt of Appeals of South Carolina
DecidedDecember 22, 2004
Docket2004-UP-656
StatusUnpublished

This text of Blue v. Harrelson (Blue v. Harrelson) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blue v. Harrelson, (S.C. Ct. App. 2004).

Opinion

THIS OPINION HAS NO PRECEDENTIAL VALUE.  IT SHOULD NOT BE CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING EXCEPT AS PROVIDED BY RULE 239(d)(2), SCACR.

THE STATE OF SOUTH CAROLINA
In The Court of Appeals

Victor L. Blue and Gail V. Blue,        Respondents,

v.

Larry Harrelson and Nancy Harrelson d/b/a Angle Construction Company,        Appellants.


Appeal From Florence County
B. Hicks Harwell, Jr., Circuit Court Judge


Unpublished Opinion No. 2004-UP-656
Submitted November 1, 2004 – Filed December 22, 2004


AFFIRMED


Kenneth E. Merriman, of Florence, for Appellants.

Daryl James Corbin, of Florence, for Respondents.

PER CURIAM:  In this action to recover damages arising from a construction contract, Larry Harrelson and Nancy Harrelson, d/b/a Angle Construction Company (the Harrelsons), appeal the trial judge’s entry of judgment in favor of Victor L. Blue and Gail Blue (the Blues).  We affirm. [1]

FACTS

The Blues entered into a construction contract with the Harrelsons on April 6, 1999.  The Harrelsons agreed to complete construction of the Blues’ home no later than 265 days from the date of the contract for a purchase price of $340,000.  In addition, the parties negotiated a late-fee provision of $120 per day after December 28, 1999, if the home was not complete.  The Harrelsons never completed the home.  During this time period, the Blues were also subjected to litigation with the Shaw Lumber Company and forced to refinance their home due to the Harrelsons’ failure to satisfy an account that was designated for the Blues’ construction project. 

On November 22, 2000, the Blues filed this action, alleging breach of contract with fraudulent intent, negligence, breach of fiduciary duty, and civil conversion.  Underlying these causes of action, the Blues primarily asserted the Harrelsons breached the contract by:  (1) failing to complete the construction within the designated 265-day time period; (2) failing to construct the home in a workmanlike manner; and (3) failing to pay the material suppliers and subcontractors involved in the project.  The Blues sought relief of $150,000 in actual damages and $150,000 in punitive damages.

Because the Harrelsons failed to answer or respond to the pleadings, the trial judge entered an order of default on February 14, 2001.  This order provided that “all allegations contained within the Plaintiffs’ pleadings are deemed true.”  The judge denied the Harrelsons’ motion to set aside the entry of default.  The judge then held a hearing solely on the amount of damages.

The judge found the Blues were entitled to an award of actual damages “for completion costs of construction in a proper manner, reputational harms and damages, and emotional distress.”  The judge also concluded the Blues were entitled to “additional damages under its breach of contract theory given the [Harrelsons’] violation of the late-fee provision for some of the period of time between December 28, 1999, and May 1, 2001.”  The judge entered judgment in the amount of $50,000 for “breach of contract, violation of the late-fee penalty provision, negligence, breach of fiduciary duties, and civil conversion.”  The judge denied the Blues’ request for punitive damages.

Subsequently, the Harrelsons filed a motion pursuant to Rule 59(e), SCRCP.  The judge denied the motion and affirmed his previous ruling, explaining:

In considering damages, the Court based its consideration on the causes of action contained in the Plaintiff’s complaint:  breach of contract, breach of fiduciary duty, negligence, conversion and emotional and reputational harm.  The Court’s consideration of damages was also based on the following:  delay in not complying with the construction completion date which was provided for in the contract, injury to the Plaintiff’s credit standing, including refinancing with increased interest on the loan, assorted tools, including but not limited to, saws, hammers and paint brushes that were charged to the Plaintiffs but were never given to them, and those items charged to the building site that were not found in the construction.

The Harrelsons appeal.

STANDARD OF REVIEW

This case presents an action at law. See Roberts v. Gaskins, 327 S.C. 478, 483, 486 S.E.2d 771, 773 (Ct. App. 1997) (stating an action for a breach of contract seeking money damages is an action at law); see also Corley v. Ott, 326 S.C. 89, 92 n.1, 485 S.E.2d 97, 99 n.1 (1997) (recognizing an action for breach of fiduciary duty is an action at law); Advance Int’l, Inc. v. North Carolina Nat’l Bank of South Carolina, 316 S.C. 266, 271, 449 S.E.2d 580, 583 (Ct. App. 1994), aff’d in part and vacated in part, 320 S.C. 532, 466 S.E.2d 367 (1996) (action alleging, inter alia, fraud and negligence and seeking damages is one at law); Blackwell v. Blackwell, 289 S.C. 470, 471, 346 S.E.2d 731, 732 (Ct. App. 1986)(“An action for damages for conversion is an action at law.”).  In an action at law, tried without a jury, our scope of review extends merely to the correction of errors of law.  Crary v. Djebelli, 329 S.C. 385, 388, 496 S.E.2d 21, 23 (1998).  Thus, the trial judge’s factual findings will not be disturbed on appeal unless a review of the record discloses that there is no evidence which reasonably supports the judge’s findings. Id.; Townes Assocs., Ltd. v. City of Greenville, 266 S.C. 81, 86, 221 S.E.2d 773, 775 (1976).

DISCUSSION

I.

The Harrelsons argue the trial judge erred in failing to dismiss the Blues’ causes of action for civil conversion, negligence, and breach of fiduciary duty.  As to each cause of action, the Harrelsons contend the Blues failed to prove damages.  In conjunction with their civil conversion argument, the Harrelsons claim there is no evidence to support the judge’s finding that the Blues were damaged by the Harrelsons charging tools and materials to an account with the Shaw Lumber Company, which was designated for the Blues’ construction project.

To the extent the Harrelsons challenge their liability, we find they are precluded from raising these issues due to the entry of default.  Because the Harrelsons were found in default, they are deemed to have admitted the truth of the Blues’ allegations and conceded liability.  See Roche v. Young Bros., Inc., of Florence, 332 S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Masters v. Rodgers Development Group, S. C., Inc.
321 S.E.2d 194 (Court of Appeals of South Carolina, 1984)
Corley v. Ott
485 S.E.2d 97 (Supreme Court of South Carolina, 1997)
Island Car Wash, Inc. v. Norris
358 S.E.2d 150 (Court of Appeals of South Carolina, 1987)
Howard v. Holiday Inns, Inc.
246 S.E.2d 880 (Supreme Court of South Carolina, 1978)
MUT. SAVINGS AND LOAN ASSOC. v. McKenzie
266 S.E.2d 423 (Supreme Court of South Carolina, 1980)
Roberts v. Gaskins
486 S.E.2d 771 (Court of Appeals of South Carolina, 1997)
Regions Bank v. Schmauch
582 S.E.2d 432 (Court of Appeals of South Carolina, 2003)
Townes Associates, Ltd. v. City of Greenville
221 S.E.2d 773 (Supreme Court of South Carolina, 1976)
Noisette v. Ismail
403 S.E.2d 122 (Supreme Court of South Carolina, 1991)
Moser v. Gosnell
513 S.E.2d 123 (Court of Appeals of South Carolina, 1999)
Blackwell v. Blackwell
346 S.E.2d 731 (Court of Appeals of South Carolina, 1986)
Thomasko v. Poole
561 S.E.2d 597 (Supreme Court of South Carolina, 2002)
Tate v. LeMaster
99 S.E.2d 39 (Supreme Court of South Carolina, 1957)
Roche v. Young Bros., Inc.
504 S.E.2d 311 (Supreme Court of South Carolina, 1998)
Crary v. Djebelli
496 S.E.2d 21 (Supreme Court of South Carolina, 1998)
Jackson v. Midlands Human Resources Center
374 S.E.2d 505 (Court of Appeals of South Carolina, 1988)
Hendricks v. Clemson University
578 S.E.2d 711 (Supreme Court of South Carolina, 2003)
In Re the Treatment & Care of Luckabaugh
568 S.E.2d 338 (Supreme Court of South Carolina, 2002)
Powell v. A. K. Brown Motor Co.
20 S.E.2d 636 (Supreme Court of South Carolina, 1942)
D & D Leasing Co. of South Carolina, Inc. v. Lipson
409 S.E.2d 794 (Court of Appeals of South Carolina, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
Blue v. Harrelson, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blue-v-harrelson-scctapp-2004.