Blue Rock Structures, Inc.

CourtArmed Services Board of Contract Appeals
DecidedOctober 21, 2021
DocketASBCA No. 62127
StatusPublished

This text of Blue Rock Structures, Inc. (Blue Rock Structures, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blue Rock Structures, Inc., (asbca 2021).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Blue Rock Structures, Inc. ) ASBCA No. 62127 ) Under Contract No. N40085-16-D-6300 )

APPEARANCES FOR THE APPELLANT: Mr. Brent Hartness President Mr. Chris Lawson Vice President of Construction

APPEARANCES FOR THE GOVERNMENT: Craig D. Jensen, Esq. Navy Chief Trial Attorney Daniel J. Monahan, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE EYESTER ON THE GOVERNMENT’S MOTION FOR SUMMARY JUDGMENT

Blue Rock Structures, Inc. (Blue Rock or appellant) appeals a contracting officer’s final decision (COFD) denying its claim of $73,027.34 for additional steel and 21 days of additional time as a result of a differing site condition for the installation of translucent roof panels on Hanger 250 at Marine Corps Air Station, Cherry Point, North Carolina. The Department of the Navy (Navy or government) filed a motion for summary judgment arguing that the appellant has failed to demonstrate any material facts in dispute to demonstrate that a differing site condition was the sole cause of the need for additional steel and time for installation of the panels. Appellant opposes the motion, arguing that the existing steel in the hangar varied in straightness from the design and was insufficient for fastening the panels. Because we find that a material fact is in dispute, the motion is denied.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

1. On December 18, 2015, the Navy awarded General Multiple Award Construction Contract (MACC) No. N40085-16-D-6300 to Blue Rock (R4, tab 2 at 10, 12). 1 The purpose of the MACC was to provide a range of general construction services that included new construction, demolition, repair, and alteration of buildings, systems and infrastructure (R4, tab 2 at 25).

1 Citations to the Rule 4 file are to the government’s Bates-stamped numbers. Citations to the briefs are to the PDF page numbers. 2. All delivery or task orders issued pursuant to the MACC were subject to the MACC’s terms and conditions (R4, tab 2 at 44). As pertinent here, the MACC incorporated by reference Federal Acquisition Regulation (FAR) 52.233-1, DISPUTES (May 2014); FAR 52.236-2, DIFFERING SITE CONDITIONS (APR 1984); and FAR 52.243-4, CHANGES (JUN 2007) (R4, tab 2 at 30). FAR 52.236-2, DIFFERING SITE CONDITIONS (APR 1984), states, in pertinent part:

(a) The Contractor shall promptly, and before the conditions are disturbed, give a written notice to the Contracting Officer of-

(1) Subsurface or latent physical conditions at the site which differ materially from those indicated in this contract; or (2) Unknown physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the contract.

(b) The Contracting Officer shall investigate the site conditions promptly after receiving the notice. If the conditions do materially so differ and cause an increase or decrease in the Contractor’s cost of, or the time required for, performing any part of the work under this contract, whether or not changed as a result of the conditions, an equitable adjustment shall be made under this clause and the contract modified in writing accordingly.

3. On October 28, 2015, the Navy issued a solicitation for repairs and improvements to Hangar 250 to selected MACC holders, including Blue Rock (R4, tab 1 at 1-2). The solicitation included specifications and drawings for the project as attachments (R4, tab 1 at 3).

4. On November 30, 2016, the Navy issued fixed-priced Task Order No. 0005 to Blue Rock for $13,683,510 for repairs and improvements to Hangar 250 in accordance with the issued solicitation, as amended (R4, tab 10 at 1260-62, 1268, tab 11). The agency ultimately issued 13 modifications, which increased the task order award amount to $15,533,529.08 and established a completion date of December 13, 2019 (R4, tab 31 at 1480).

2 5. As part of the renovation, Blue Rock was to provide a translucent fiberglass skylight system in the hangar (R4, tab 3 at 75, 608-14). The specifications, prepared by the agency’s Designer of Record, DJG, Inc. (DJG), stated:

Field verify all submitted opening sizes, dimensions and tolerances . . . . The installer shall examine [the] area of installation to verify readiness of site conditions and to notify the Contractor about any defects requiring correction. Verify when structural support is ready to receive all specified work and to convene a pre-installation conference, if approved by the Contracting Officer, including the Contractor, skylight installer and all parties directly affecting and affected by the specified work. Do not commence work until conditions are satisfactory.

In addition, the specifications provided that Blue Rock shall “[e]rect [the] translucent skylight system in accordance with the approved shop drawings supplied by the manufacturer.” (R4, tab 3 at 614)

6. The specifications also incorporated by reference several drawings, including S-301 (Shop Roof) and S-402 (Sections & Details) (R4, tab 3 at 65).

7. Blue Rock subcontracted work to Carolina Architectural Products, Inc. (Carolina). Carolina used Kalwall Corporation (Kalwall) as its supplier for the translucent panels. (Gov’t mot., ex. 1 at 28-30)

8. Around March 2017, shop drawings prepared by Kalwall and reviewed by Carolina were submitted to DJG. DJG signed off on the shop drawing, stating “no exception taken,” on April 28, 2017 (R4, tab 14).

9. On July 20, 2018, Carolina sent a letter to Blue Rock and advised the following:

[This is p]er our previous discussions related to the additional support that is required under the Kalwall system. During the field verification process, it was determined that the alignment of the existing steel is off, varying from ½” to 1”, enough that additional support is necessary to ensure that there is adequate structure under the Kalwall system to support it and to which to attach.

The “waviness” of the existing steel will make it very difficult to install the Kalwall system and be certain that the

3 system is adequately supported. The existing support system is a 8” x 2” steel channel on edge, with the 2” wide flange being the support surface for the Kalwall system. A variance of this degree will be detrimental to the installation of the Kalwall system, weather tightness and the system warranties. It will be necessary to determine an effective method of increasing the bearing surface for the Kalwall system. A minimum bearing surface of 3½” will be necessary to allow for the inconsistencies in the existing structure.

(R4, tab 22 at 1328)

10. On July 23, 2018, Blue Rock submitted a request for information (RFI) to the agency stating:

During our site survey in order to make the shop drawings for the Translucent Panels for the submittal. . . we found that the existing Structural Supports vary from ½[”] to 1[”] in the span. The contractor is indicating that he needs to add additional support to make his system work correctly. Since the new Roof System is prefab at the factory field modifications cannot be done in the field. See attached for more information and sketch.

I have requested a proposal from a third party structural steel fabricator to provide and install this. I believe that this is a changed condition to the contract.

(R4, tab 22 at 1327)

11. On July 24, 2018, the agency responded to the RFI and stated it was “unclear why waviness would effect the fastening of the panels.” The agency further stated that per the shop drawings, “the panels are set perpendicular to the purlins” and therefore, a ½” or 1” difference would not matter.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
Blue Rock Structures, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/blue-rock-structures-inc-asbca-2021.