Blue Flame Gas Co SP & CU - Decision on Motion

CourtVermont Superior Court
DecidedDecember 6, 2021
Docket20-ENV-00011
StatusPublished

This text of Blue Flame Gas Co SP & CU - Decision on Motion (Blue Flame Gas Co SP & CU - Decision on Motion) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blue Flame Gas Co SP & CU - Decision on Motion, (Vt. Ct. App. 2021).

Opinion

VERMONT SUPERIOR COURT Environmental Division 32 Cherry St, 2nd Floor, Suite 303, Burlington, VT 05401 802-951-1740 www.vermontjudiciary.org

│ Blue Flame Gas Co. Inc. Site Plan │ & Conditional Use Application │ Docket No. 20-ENV-00011 │

Decision on Motion Applicant-appellant Blue Flame Gas Co. Inc (“Blue Flame”) appeals from a Town of Landgrove Zoning Board of Adjustment (ZBA) decision denying its application for conditional use and site plan approval for a proposed propane storage and distribution facility. Presently before the Court is Blue Flame’s motion to amend its Statement of Questions. Interested party Michael Toole filed an objection, as did the Town of Landgrove following the Court’s request for supplemental briefing.

Background We recite the following facts and procedural history purely to provide context for the present motion. Blue Flame seeks the necessary municipal approvals to install a 30,000-gallon propane tank and to construct an accompanying building, variously referred to as a business and/or retail office, on a parcel of land in the town of Landgrove. At the time of Blue Flame’s submission of its initial application to the Town’s zoning administrator in March 2020, the property was owned by other persons, but Blue Flame subsequently purchased the property. Blue Flame labelled its initial application as one for a permitted use, however the zoning administrator informed them that the above-ground fuel tank they proposed was “Bulk Fuel Storage,” a defined term in the Bylaws, and, as such, an industrial use. As industrial uses required conditional use approval in the Commercial District, the zoning administrator advised Blue Flame that the application required conditional use and site plan approval by the ZBA and requested additional information to complete the application. Blue Flame provided the additional information and the ZBA held a hearing noticed as conditional use and site plan review on June 18, 2020. At that meeting, several neighbors presented objections to the proposed project. The ZBA recessed the hearing given the high level of interest and what it identified as deficiencies in the information provided. Ahead of the reconvened hearing, Blue Flame submitted a revised application and narrative. Notably, it proposed to bury the propane tank, which it claimed would alleviate one major source of the neighbors’ concerns. It did not, at the time, argue that this revision changed the application to one for a permitted use or that conditional use approval was otherwise unnecessary. The ZBA held the reconvened hearing on July 23, 2020, where the revised project was discussed and input from many of the same interested parties received. The hearing was adjourned and the ZBA subsequently denied the application in a written decision dated September 2, 2020. In its legal conclusions, the ZBA determined that the application required conditional use approval, both because bulk fuel storage was an industrial use and because the project proposed a “multi-use building,” which automatically subjected the application to conditional use review. It concluded the project did not meet the general conditional use standards, specifically because of its impact on the character of the adjacent area and on traffic. The ZBA denied the application on these grounds, but noted that if it were to proceed to the specific conditional use standards, “it would impose conditions to address, among other concerns, Performance Standards under Bylaws §§ 320, 321, or 322; Landscaping under Bylaws § 330; or Commercial District Development under Bylaws §§ 420—425.” The ZBA also disapproved of the site plan, finding it did not maximize the safety of vehicular circulation or adequately screen buildings and service areas. Blue Flame subsequently filed this appeal in October 2020. In its original Statement of Questions, filed October 22, 2020, it posed two questions and nine sub-questions. Essentially, the initial Statement of Questions asked whether the project should be granted conditional use and site plan approval and challenged the specific reasons the ZBA had given for denying those approvals. The parties subsequently began the discovery process, which was extended by court order. Blue Flame filed the present motion on August 25, 2021, two weeks after the Court issued its most recent amended discovery scheduling order. By the terms of that order, written discovery had long since closed, and the parties had one month before any deposition of Blue Flame expert witnesses needed to occur. At the time, only one week remained before the parties other than Blue Flame needed to disclose all their expert witnesses. See “Second Amended Discovery/Alternate Dispute Resolution Stipulation and Order,” Aug. 10, 2021. The proposed amended Statement of Questions contains 12 questions and no sub-questions. The new questions can be broken into three categories. Questions 1-6 all essentially ask whether the proposed development should be reviewed as a permitted use. They raise issues not presented in the original statement of questions. Questions 7 and 9 concern the appropriate standard by which to

-2- judge adverse impacts. Question 7 expounds on question 1(a) in the original Statement of Questions, while Question 9 is brand new. Finally, 8, 10, 11, and 12 amend the remaining questions in the original Statement of Questions (1(b)-2(c)). They essentially change these from questions about the particular conditional use criteria, performance standards, and site plan criteria under which the ZBA denied the project to questions of whether the project meets all the applicable conditional use and site plan approval standards.

Legal Standard Like a complaint in a civil case, appellants to the Environmental Division may amend their Statement of Questions once as a matter of right within 21 days of the initial filing thereof. V.R.C.P. 15(a);1 In re Killington Mountain House, LLC NOV, Nos. 138-12-18 and 30-2-19 Vtec, slip op. at 9 (Vt. Super. Ct. Envtl. Div. Nov. 17, 2020) (Durkin, J.). Thereafter, we “generally take a liberal view in granting a motion to amend a Statement of Questions.” Laberge Shooting Range, No. 96-8-16 Vtec, slip op. at 1 (Vt. Super. Ct. Envtl. Div. Jan. 4, 2017) (Walsh, J.) (internal quotation marks omitted) (citing Colby v. Umbrella, Inc., 2008 VT 20, ¶ 4, 184 Vt. 1). We consider “whether there has been undue delay or bad faith by the moving party, whether the amendment will prejudice other parties, and whether the amendment is futile.” Id. at 3. There is no fixed length of time that constitutes undue delay, but we are more receptive when less time has passed and above all when there are good reasons for the delay, such as discovery of new information. In re Burns 12 Weston Street NOV, No. 75-7-18 Vtec, slip op. at 2-3 (Vt. Super. Ct. Envtl. Div. Aug. 8, 2019) (Durkin, J.) (merits decision appealed on other grounds). As to prejudice, we look at whether the delay had or is likely to have any negative effect on the non-moving party’s ability to litigate their position. Cf. In re Northeast Materials Group, LLC., No. 35-3-13 Vtec, slip op. at 3 (Vt. Super. Ct. Envtl. Div. July 2, 2013) (Walsh, J.). And proposed questions are futile if they state a claim upon which relief could not be granted or which lies outside our court’s limited subject matter jurisdiction. Werner Conditional Use, No. 44-4-16 Vtec, slip op. at 7 (Vt. Super. Ct. Envtl. Div. Aug. 31, 2016) (Durkin, J.) (citing Prive v. Vt. Asbestos Grp., 2010 VT 2, ¶ 13, 187 Vt. 280) (“[T]he Court may deny motions to amend if the amendment would be ‘futile,’ i.e., if the added claims would not survive a motion to dismiss.”); In re Zlotoff Foundation Inc. NOV (2), No. 69-6-19 Vtec, slip op. at 3 (Vt. Super. Ct. Envtl. Div. Sept. 24, 2020) (Durkin, J.) (denying leave to add questions raising issues outside the scope of our Court’s jurisdiction).

Analysis 1 Note, V.R.C.P.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Prive v. Vermont Asbestos Group
2010 VT 2 (Supreme Court of Vermont, 2010)
In Re Sisters & Bros. Investment Group, LLP
2009 VT 58 (Supreme Court of Vermont, 2009)
Colby v. Umbrella, Inc.
2008 VT 20 (Supreme Court of Vermont, 2008)
Chioffi v. Winooski Zoning Board
556 A.2d 103 (Supreme Court of Vermont, 1989)
In Re Walker
588 A.2d 1058 (Supreme Court of Vermont, 1991)
In Re Appeal of Miller
742 A.2d 1219 (Supreme Court of Vermont, 1999)
In Re Maple Tree Place
594 A.2d 404 (Supreme Court of Vermont, 1991)
Village of Woodstock v. Bahramian
631 A.2d 1129 (Supreme Court of Vermont, 1993)
Simendinger v. City of Barre
770 A.2d 888 (Supreme Court of Vermont, 2001)
In Re John A. Russell Corp.
2003 VT 93 (Supreme Court of Vermont, 2003)
In re Glen M.
575 A.2d 193 (Supreme Court of Vermont, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
Blue Flame Gas Co SP & CU - Decision on Motion, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blue-flame-gas-co-sp-cu-decision-on-motion-vtsuperct-2021.