{¶ 1} Appellants, Sherry Sherrill Blount and Allen Blount, appeal from the judgment of the Franklin County Court of Common Pleas granting summary judgment to appellees, Schindler Elevator Corporation ("Schindler"), Spectacor Management Group ("Spectacor"), Eric Ashmore, Jim Matthews, Marc Dickson and Tim McCorkle. For the following reasons, we affirm.

{¶ 2} On April 15, 1997, appellant, Sherry Sherrill Blount, was working as a pizza stand manager for Aramark Services at the Columbus Convention Center ("Convention Center"). When appellant's shift ended at 10:30 p.m., she and a co-worker, Sheila Moorer, boarded an escalator located on the north side of the Convention Center. The women were approximately halfway down the escalator when it allegedly stopped abruptly. Due to the abrupt stop, appellant fell forward. Ms. Moorer, who was standing behind appellant, fell onto appellant. After both appellant and Ms. Moorer collected themselves, they walked down the unmoving escalator stairs and reported the incident to their supervisor and a Convention Center security guard.

{¶ 3} For the six months prior to appellant's fall, appellee Schindler had been under contract with the Convention Center to inspect and maintain the escalator. At the time of the accident, appellee Spectacor was the managing agent of the Convention Center and was responsible for the day-to-day operations of the facility.

{¶ 4} On April 15, 1999, appellants filed suit asserting negligence claims against Schindler and Spectacor for injuries appellant allegedly sustained due to her fall on the escalator. This suit was voluntarily dismissed by appellants without prejudice on February 2, 2000.

{¶ 5} On January 24, 2001, appellants refiled their suit against Spectacor, and Jim Matthews and Marc Dickson, two of Spectacor's employees (collectively the "Spectacor appellees"), as well as against Schindler, and Eric Ashmore and Tim McCorkle, two of Schindler's employees (collectively the "Schindler appellees"). In their complaint, appellants alleged that the Schindler appellees were negligent in their inspection and maintenance of the escalator, and that the Spectacor appellees were negligent in their supervision of the repair and maintenance of the escalator.

{¶ 6} When appellants filed the present action, they instructed the clerk of courts to serve each appellee with a copy of the summons and complaint via certified mail. However, not all of the appellees received personal service. The copy of the summons and complaint sent by certified mail to Schindler was returned to the clerk of courts marked "NOT DELIVERABLE AS ADDRESSED UNABLE TO FORWARD." The copy of the summons and complaint sent to Eric Ashmore was also returned, marked "MOVED, LEFT NO ADDRESS." After this initial attempt at service failed, appellants did not again attempt to serve either Schindler or Ashmore.

{¶ 7} Appellants directed the clerk of courts to serve a copy of the summons and complaint on Tim McCorkle, the third Schindler appellee, at the Schindler branch office where McCorkle was employed at the time of the accident. Although the clerk of courts received a return receipt for this summons and complaint, the receipt was signed by "Betty Haddox." McCorkle had not worked at Schindler for seven months.

{¶ 8} On March 1, 2001, the Schindler appellees jointly filed an answer to appellants' complaint. In their answer, the Schindler appellees asserted the affirmative defenses of insufficiency of service of process and lack of personal jurisdiction.

{¶ 9} On October 24, 2001, the Schindler appellees filed a summary judgment motion, arguing that no genuine issues of material fact existed and that they were entitled to judgment as a matter of law. Thereafter, appellants filed a memorandum contra, arguing that specified affidavits, exhibits and citations to deposition testimony established that there were genuine issues of material fact. The trial court never ruled upon the Schindler appellees' October 24, 2001 summary judgment motion.

{¶ 10} Subsequently, the Spectacor appellees filed a motion for summary judgment, arguing that the undisputed facts established that they did not breach any duty owed to appellants.

{¶ 11} On February 2, 2002, the Schindler appellees filed a motion for leave to file a second motion for summary judgment. The trial court granted this motion. In their second motion for summary judgment, the Schindler appellees argued that appellants' claims were barred by the statute of limitations, given that appellants failed to recommence their action against the Schindler appellees within the one-year grace period allowed by R.C. 2305.19, the savings statute.

{¶ 12} Appellants failed to file memoranda contra in response to either of these summary judgment motions, although appellants did file a motion to strike the affidavits and exhibits attached to the Spectacor appellees' motion.

{¶ 13} On May 23, 2002, the trial court issued a decision granting the Spectacor and the Schindler appellees' motions for summary judgment. The trial court also granted in part and denied in part appellants' motion to strike. Appellants appeal from this judgment.

{¶ 14} On appeal, appellants assign the following errors:

{¶ 15} "[1.] The trial court erred in granting summary judgment for the Schindler Defendants' Motion for Summary Judgment because Appellees made a voluntary appearance and voluntarily waived their affirmative defenses.

{¶ 16} "[2.] The trial court erred in dismissing Appellees Schindler, Ashmore, and McCorkle for failing to commence the re-filed action as required by R.C. § 2305 and Civ.R. 3(A) as Appellees had been served with process and thus the action had been commenced.

{¶ 17} "[3.] The trial court erred in granting Appellees' Spectacor Management Group, Jim Matthews, and Marc Dickson, Motion for Summary Judgment as there were general issues of material fact."

{¶ 18} We will address appellants' second assignment of error first. By appellants' second assignment of error, they argue that they properly commenced their action against the Schindler appellees within the time frame permitted by R.C. 2305.19.

{¶ 19} Generally, negligence actions such as appellants' must be brought within two years of when the cause of action accrued. R.C. 2305.10 ("[a]n action for bodily injury or injuring personal property shall be brought within two years after the cause thereof arose"). However, pursuant to R.C. 2305.19, "[i]n an action commenced, or attempted to be commenced, * * * if the plaintiff fails otherwise than upon the merits, and the time limited for the commencement of such action at the date of * * * failure has expired, the plaintiff * * * may commence a new action within one year after such date." Thus, if a plaintiff recommences his action within one year after a voluntary dismissal, he may avoid the operation of the statute of limitations.

{¶ 20} In the case at bar, appellants originally filed an action against the Schindler appellees seeking recovery for appellants' injuries on April 15, 1999 — the day before the two-year statute of limitations would have expired.

Free access — add to your briefcase to read the full text and ask questions with AI

Blount v. Schindler Elevator, Unpublished Decision (4-24-2003), (Ohio Ct. App. 2003).

Blount v. Schindler Elevator, Unpublished Decision (4-24-2003) (Blount v. Schindler Elevator, Unpublished Decision (4-24-2003)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Bell v. Midwestern Educational Services, Inc.
624 N.E.2d 196 (Ohio Court of Appeals, 1993)
Mergenthal v. Star Banc Corp.
701 N.E.2d 383 (Ohio Court of Appeals, 1997)
Helton v. Scioto County Board of Commissioners
703 N.E.2d 841 (Ohio Court of Appeals, 1997)
Akron-Canton Regional Airport Authority v. Swinehart
406 N.E.2d 811 (Ohio Supreme Court, 1980)
Maryhew v. Yova
464 N.E.2d 538 (Ohio Supreme Court, 1984)
First Bank of Marietta v. Cline
466 N.E.2d 567 (Ohio Supreme Court, 1984)
Jeffers v. Olexo
539 N.E.2d 614 (Ohio Supreme Court, 1989)
Dresher v. Burt
662 N.E.2d 264 (Ohio Supreme Court, 1996)
State ex rel. Grady v. State Employment Relations Board
677 N.E.2d 343 (Ohio Supreme Court, 1997)