Blount v. . Guthrie

5 S.E. 890, 99 N.C. 93
CourtSupreme Court of North Carolina
DecidedFebruary 5, 1888
StatusPublished
Cited by1 cases

This text of 5 S.E. 890 (Blount v. . Guthrie) is published on Counsel Stack Legal Research, covering Supreme Court of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blount v. . Guthrie, 5 S.E. 890, 99 N.C. 93 (N.C. 1888).

Opinion

On 5 August, 1886, the defendant entered into a written contract with one Joseph Ransley, by which Ransley was to build for him a dwelling-house in the town of Durham. The written contract and specifications are set out in full in the record, and are minutely drawn and of considerable length, but for the purpose of this controversy it is only necessary to state that Ransley was to complete the dwelling "to (94) the full and entire satisfaction of the architect" — one Pugin, employed by defendant — by 1 November, 1886, for which the defendant was to pay to him the sum of $3,484, as follows:

"When the foundations are complete and ready for framing, $225; when the entire building is under roof, $700; when the entire building is plastered, $200; when the entire wood work is completed, $1,000; and the final payment when all work of every kind is completed and upon a written acceptance of such by the architect."

The work was to be done "in accordance with drawings prepared by the architect, under his supervision and to his satisfaction and acceptance." Among other things, the specifications provided for gas and water pipes.

The plaintiff testified in substance that he was engaged in plumbing, and did work on defendant's house for hot and cold water and gas, and furnished the material, under a contract made with Ransley.

The work was begun during the second week in November, and finished some time in December, 1886. There was an estimate submitted by witness and accepted by contractor for $226; in this estimate there was a water tank which was taken off at defendant's suggestion, value $25.

Witness was directed by Pugin to make the connection for an additional gas pipe in dressing room. Pugin looked over and saw all material and gave the order. Defendant paid for the extra gas pipes. "Pugin pointed out every position where pipes, etc., were to be placed; defendant was there once or twice during the work; he did not tell me he had discharged Ransley, and I did not know it till my conversation with Guthrie in last of December, when work was done; Guthrie directed the pipe from tank to boiler to be stopped; these directions were all observed by me; the $200 has not been paid; made demand before I brought this suit; my work was included in the contract with Ransley; don't know whether Ransley had made the contract (95) when I furnished my estimate; I had put in all the gas pipe before I ever spoke to defendant about it; it was not defendant who first ordered me to put in the extra piece of gas pipe — it was Pugin; for that piece of pipe I have been paid by defendant; before the contract was *Page 100 accepted, contract to be approved by Pugin; he said he had not yet seen Mr. Guthrie, but he thought he would accept my estimate; Pugin asked me in July to make my estimate and hand it to Ransley; I did so; most of the work was done after Ransley quit; Hill was Ransley's foreman; Guthrie said he had taken the contract away from Ransley — that he had failed to comply; told Guthrie he would look to him for the money; Guthrie said Ransley had been gone for several weeks."

T. B. Hill testified: "Ransley was discharged by Mr. Guthrie's direction for drunkenness; I then took charge; Guthrie hired me to take charge of the house and superintend it; Blount at that time had not finished his work, and had not finished it at the time I completed the work; while the work was going on Mr. Guthrie was there; Pugin gave orders for changes, etc., in defendant's name; Pugin had charge of the work, to see that it was carried out according to plans and specifications; Guthrie said he had never authorized Pugin as his agent, but had authorized me; he said whatever work was done after Ransley left he was responsible for, for he had assumed the work; I think plaintiff was nearly through before Ransley was discharged."

Plaintiff recalled: "The pipe that Guthrie stopped was the first water pipe put in — all water pipe was put in after 13 November; $37.08 done before 13 November; Guthrie was there and saw me at work, and did not notify me."

Defendant testified: "I was to furnish the lot and the old house that stood upon it, and Ransley was to build me a house for $3,484, to be finished by 1 November, according to plans and specifications by (96) Pugin; plumbing, etc., in contract; Pugin was my architect to superintend — not authorized to make contracts; in October I came to Durham; found gas pipes had all been put in; was in the house; called Blount in and asked him if he considered the gas piping done; he answered, `yes'; never paid Blount for anything but that amount for the price for a drop light; never made myself responsible for any other item; I directed water tank to be left off; had no other conversation with Blount till last of December; he had then completed all his work except putting on the cocks and connecting the pipes with the bath tub; I took charge 17 November; I inspected the premises — went over the whole place; no work was done by plaintiff between 13 and 17 November; discharged Ransley 17 November; time had passed for completing the house, and it was about half done; at the time I discharged Ransley I had paid him $1,897.95 — this prior to 17 November, 1887, at the time the plaintiff's lien was filed, to wit: 25 January, 1887, I had paid on account of the work, $3,867.80, including what I paid Hill for Ransley on 17 November; I paid him more than the work was worth; when I took charge entire building was under roof but not plastered; several *Page 101 rooms had not been; the entire wood work was not half done — it was probably one-fourth done. At date of discharge defendant would, under his contract, have owed Ransley $925; never have had any written acceptance of house by architect; Hill receipted as Ransley's foreman; I saw Blount working there before Ransley's discharge, but made no inquiry as to whether he had been paid; when payments made I had not written certificates from Pugin that there were no liens; did not give Ransley three days' notice of intention to take charge of the contract; the man I talked to about drop light spoke as sub-contractor under Ransley; never had anything to do with Blount's estimate; I never saw it or heard of it till lien was filed; Blount never notified me of any claim he had before I discharged Ransley; I have never (97) made any settlement with Ransley; did not go into details as to what the value of the work was up to date of discharging Ransley; I sent the checks for Ransley to Pugin in order that he might hold them if the work had not been done, or pay them over if it had been done."

Pugin testified: "I never made any contract with Blount; Blount's work nearly all completed when Ransley discharged; I think, when Ransley discharged, frame complete; roof partially on; small amount of plastering on; according to contract-price work was about half done; I handed Blount's estimate to Mr. Guthrie 26 January, 1887; I had never seen it till Hill gave it to me; this after Ransley was discharged, before Blount's suit; sent the estimate to Guthrie 26 January, 1887; Ransley had not complied with the contract; the work had been neglected, consequence failure to finish the house; I asked Blount to make an estimate, probably; I never accepted the house; never notified defendant that there were no liens upon it; accepted Blount's work in writing."

With the record there is a copy of the "estimate of gas and water pipes for house of W. A. Guthrie," dated 12 July, 1886, and signed by Lewis Blount, and also copies of checks of the defendant payable to the order of Joseph Ransley and endorsed by the said Ransley and B. A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

International Glass Co. v. Krouse
282 F. 206 (Third Circuit, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
5 S.E. 890, 99 N.C. 93, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blount-v-guthrie-nc-1888.