Blond v. United States Fidelity & Guaranty Co.

80 S.W.2d 675, 336 Mo. 684, 99 A.L.R. 36, 1935 Mo. LEXIS 616
CourtSupreme Court of Missouri
DecidedMarch 9, 1935
StatusPublished
Cited by4 cases

This text of 80 S.W.2d 675 (Blond v. United States Fidelity & Guaranty Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blond v. United States Fidelity & Guaranty Co., 80 S.W.2d 675, 336 Mo. 684, 99 A.L.R. 36, 1935 Mo. LEXIS 616 (Mo. 1935).

Opinions

This is an appeal from a judgment against appellant on its surety bond and in favor of respondents in the sum of $10,000.

B.L. Hoffman, principal in the bond, was made a defendant, but did not appeal from the judgment entered. Respondents were the owners of a city lot at the northwest corner of Sixteenth and Wyandotte streets, Kansas City, Missouri. By a written contract, dated July 15, 1925, this property was leased to Hoffman for a term of ninety-nine years. The lot was unimproved. Hoffman agreed to pay a rental for the first five years of $1500 per year, payable in four equal quarterly installments on the 15th of July, October, January and April. The balance of the term the rental was to be $1800 per year, also payable in quarterly installments. In addition to the rental Hoffman agreed to pay all taxes to be assessed against the property. It was further agreed that Hoffman, at his own expense, *Page 687 would erect a building on the lot at a cost of not less than $30,000, construction of this building to be commenced within eighteen months after the date of the lease. By a modification of the agreement this period of time was extended to five years. Hoffman was required to, and did, furnish a surety bond in the sum of $10,000, for the faithful performance of the obligations contained in the lease.

On January 15, 1927, Hoffman was in default because he had not commenced the erection of the building as agreed. At that time the terms of the lease were modified in certain respects, including the time in which the building was to be completed. The bond of $10,000, which had been given, was released by the modification agreement and a new bond provided for, which was given. It is this latter bond upon which this suit was based.

The quarterly installments of rent due October, 1928, and January, 1929, were not paid. Neither did Hoffman pay the taxes for the year 1928. On March 7, 1929, respondents notified Hoffman and appellant surety company of the default in the payment of the rent and taxes and that if the default continued for sixty days from the date of the notice the lease would be forfeited. On May 11, 1929, Hoffman and appellant surety company were notified that respondents had exercised their right to forfeit the lease because the default in the payment of the rental and taxes had continued for more than sixty days. Respondents thereupon took possession of the property and placed signs thereon reading, "For Sale Or Lease."

Since liability, under the terms of the bond, was the main and only issue in the case we will embody herein the provisions of the lease and bond pertinent to that issue. The forfeiture clause of the lease reads in part as follows:

"This lease is made upon the express condition that if lessee fail to keep and perform any of the covenants or agreements contained in this indenture, then this lease shall become void at the option of lessors, provided, the lessors shall first give to lessee at lease sixty days' written notice of intention to forfeit this lease, and shall set forth therein, the specific breach of lease and of lessors' intention to reenter the premises and declare this lease forfeited, if such breach be continued. Such notice shall be served in the manner hereinafter provided and after the expiration of said sixty days' notice, this lease shall be void, provided the lessee is then in default respecting the complained of covenant or agreement, and the lessor shall then be entitled to the possession of the demised premises. . . ."

Section 3, modification agreement reads:

"The lessee as a part of the consideration of this agreement covenants and agrees to commence, at his own expense and within five (5) years from the date of this lease, the erection and construction on said premises of a building or buildings, according to plans and specifications, to be first approved by said lessors, for the purposes *Page 688 hereinafter stated, to cost not less than thirty thousand dollars ($30,000.00) and to fully complete and fully pay for said building or buildings within one year after commencement of construction, and lessee further agrees that upon commencement of the construction of said building or buildings he will faithfully continue such construction until the full completion thereof within the period provided for in this paragraph. Provided, however, that if such construction be delayed by act of God, strikes, riots or acts of public enemies, said period in which construction shall be completed shall be extended for a like period of time as the period of such delay, but in no event shall such extension of time be for a period greater than one year."

Section 6 of this agreement reads as follows:

"That Section Thirteen (13) of the original lease is hereby stricken out in its entirety, and all rights thereunder waived by the parties hereto, and in lieu of said Section Thirteen (13), the following is agreed to and adopted by the parties hereto as a part of said lease:

"`Contemporaneously with the signing of this instrument and before the same shall be binding upon the parties hereto, lessee shall execute and deliver to lessors a good and sufficient surety company bond in the sum of Ten Thousand Dollars ($10,000) which shall be executed by a surety company authorized to do business in the State of Missouri, subject to the approval of lessors or their agents, conditioned upon and for the prompt and faithful payment of all rent and moneys hereunder, and for the faithful performance of all convenants, stipulations and agreements herein expressed upon the part of the lessee, by the said lessee to be kept and performed, including the complete erection and full payment for the building or buildings to cost not less than Thirty Thousand Dollars ($30,000.00) to be constructed within five years from date of lease, and at least ten days before the commencement of construction operations (and for this purpose wherever the words `construction operations' are used, `construction operations' shall be deemed to commence when lessee begins the removal of any improvements on said premises, or the grading or excavation of same) lessee shall execute and deliver to lessors a good and sufficient surety company bond in an amount to the estimated cost of the proposed improvements, as lessors may ascertain such cost by the plans and specifications submitted by lessee and said bond subject to approval of lessors or their agents, conditioned upon the faithful performance of all of the terms, stipulations and conditions herein expressed on the part of the lessee to be kept and performed, and also including the prompt and complete payment of all bills and indebtedness for services, labor and material, arising from and in and about the construction and erection of such improvements, and the same shall remain in full force and effect until the completion of the proposed improvements *Page 689 and until the same has been completely and entirely paid for by lessee. For the purpose of this section, it is agreed and inasmuch as it would be difficult or/and impossible to determine the exact amount of damages in the event lessee defaults in his covenants to erect the agreed improvements, according to the terms and conditions of this lease, within said period of five years from date of lease, it is now agreed between said lessors and lessee that damages for said breach shall be in the sum of Ten Thousand Dollars ($10,000), and said sum is and has been agreed upon as liquidated damages and shall not be held or considered as a penalty.'"

The condition of the bond of appellant provides as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ten-Six Olive, Inc. v. Curby
208 F.2d 117 (Eighth Circuit, 1953)
Abrams v. St. Louis County Library District Board
258 S.W.2d 672 (Supreme Court of Missouri, 1953)
Merrimac Mining Co. v. Gross
12 N.W.2d 506 (Supreme Court of Minnesota, 1943)
Blond v. Hoffman
121 S.W.2d 137 (Supreme Court of Missouri, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
80 S.W.2d 675, 336 Mo. 684, 99 A.L.R. 36, 1935 Mo. LEXIS 616, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blond-v-united-states-fidelity-guaranty-co-mo-1935.