This text of Blomquist v. County of Santa Clara CA6 (Blomquist v. County of Santa Clara CA6) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blomquist v. County of Santa Clara CA6, (Cal. Ct. App. 2022).

Opinion

Filed 4/11/22 Blomquist v. County of Santa Clara CA6 NOT TO BE PUBLISHED IN OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

SIXTH APPELLATE DISTRICT

JENNIFER BLOMQUIST et al., H045975 (Santa Clara County Plaintiffs and Appellants, Super. Ct. No. CV304201)

v.

COUNTY OF SANTA CLARA et al.,

Defendants and Respondents;

SAN JOSE WATER COMPANY et al.,

Real Parties in Interest and Respondents.

Jennifer and Michael Blomquist petitioned for writ of mandate against the County of Santa Clara, a member of the board of supervisors, and several county employees, naming the San Jose Water Company and the San Jose Water Group as real parties in interest. The dispute relates to the approval and construction of a water storage tank near appellants’ property, and the associated relocation of an access road. The trial court sustained demurrers to the operative third amended petition, finding that the petition was fatally uncertain. Appellants argue that the trial court erred in sustaining the demurrer and, alternatively, that the trial court erred by not granting leave to amend. We will affirm the judgment of dismissal because appellants failed to state facts sufficient to constitute a cause of action and have not demonstrated a reasonable possibility that further amendment would cure that defect. I. TRIAL COURT PROCEEDINGS According to the third amended petition (operative petition), appellants own two parcels of land on La Mirada Road in unincorporated Santa Clara County. Appellants live in a house on one of the parcels, and the other is undeveloped. Real parties in interest the San Jose Water Company and San Jose Water Group (collectively, San Jose Water) own property near appellants’ parcels. San Jose Water sought to replace a water tank on its property with a larger water tank, and proposed that a part of La Mirada Road on San Jose Water’s property would be “slightly realigned within two fee title owned [San Jose Water] parcels.” The operative petition describes a “recorded road dedicated for public access and underlying public service easements” on San Jose Water’s property referred to as La Mirada Road. The petition states La Mirada Road is a “road for public use,” but the county “has not officially accepted La Mirada into County Roads for maintenance.” In compliance with the California Environmental Quality Act (CEQA; Pub. Res. Code, § 21000 et seq.), a notice of determination for the tank replacement project was filed in March 2014 with the State Clearinghouse at the California Office of Planning and Research, indicating that a mitigated negative declaration was adopted and that the project would not have a significant effect on the environment. The California Department of Public Health was the lead agency for the project under CEQA. Building permits for the project were issued by the county in March 2014 and March 2015. Representing themselves, appellants filed the initial petition for writ of mandate in December 2016. They named as respondents Santa Clara County, Supervisor Mike Wasserman, and several county employees (collectively, respondents). The San Jose Water Company and “SJW Group” were named as real parties in interest. Appellants filed a first amended petition, apparently before any responsive pleading was filed. The trial court sustained demurrers to the first amended petition on grounds of uncertainty and failure to state a cause of action, and granted leave to amend. Appellants filed a second 2 amended petition, and the trial court again sustained demurrers to that pleading because the court found it “ambiguous, uncertain, and incomprehensible.” The court granted leave to amend, but admonished appellants to “remove all extraneous allegations and references to law that do not support a grant of writ of mandate for the facts in this case.” (Underscoring omitted.) The operative petition was filed in December 2017. Rather than remove extraneous allegations, appellants included more than 10 additional pages. The operative petition consists mostly of extended quotations from state and local laws, interspersed with conclusory factual allegations. The operative petition does not separate different legal theories into causes of action; indeed, no specific cause of action is identified. It alleges broadly that “[n]umerous laws were violated so [San Jose Water] could avoid SRA Fire Safe Regulations, circulation elements (General Plans), inter alia,” and that respondents “could not administratively exempt [San Jose Water] and did not perform ministerial duties” related to a use permit and design review. The operative petition acknowledges that San Jose Water “provided new physical access” to appellants’ property on the realigned La Mirada Road after completing the new water tank, but asserts that appellants “no longer have legal access to Home and Development as a result of [respondents’] allegedly unlawful approval of [capital improvement project] permits as well as [respondents’] failure to faithfully execute our laws once notified.” The operative petition includes a lengthy prayer, seeking among other things an order compelling respondents to “[n]otice [San Jose Water] of violations and hold related hearing.” It also seeks an order compelling respondents to enforce San Jose Water’s compliance with: “SRA Fire Safe Regulations,” “General Plans (Los Gatos or County as required by law/facts),” the Subdivision Map Act, CEQA, and “fence setbacks and trees within La Mirada.” Finally, it seeks to require the county to adopt a “resolution for La Mirada to become a County maintained road.”

3 The trial court sustained demurrers to the operative petition after a hearing. The trial court concluded the operative petition remained “uncertain, ambiguous, and incomprehensible.” The court denied leave to amend, noting that appellants “had two prior opportunities to clarify their pleading” and failed to do so. II. DISCUSSION A. THE DEMURRERS WERE PROPERLY SUSTAINED We review de novo a judgment of dismissal based on a sustained demurrer. (Organizacion Comunidad De Alviso v. City of San Jose (2021) 60 Cal.App.5th 783, 790.) We will reverse the dismissal if the allegations of the petition state a cause of action under any legal theory. (Ibid.) We assume the truth of all facts alleged in the petition (id. at pp. 790–791), but we do not consider conclusory factual or legal allegations. (B & P Development Corp. v. City of Saratoga (1986) 185 Cal.App.3d 949, 953.) “The plaintiff has the burden of showing that the facts pleaded are sufficient to establish every element of the cause of action and overcoming all of the legal grounds on which the trial court sustained the demurrer.” (Martin v. Bridgeport Community Assn., Inc. (2009) 173 Cal.App.4th 1024, 1031 (Martin).) The trial court here sustained the demurrers on the ground that the operative petition was uncertain. (Code Civ. Proc., § 430.10, subd. (f).) Though a demurrer for uncertainty is generally disfavored, dismissal on that ground is warranted if the pleading is “so incomprehensible that a defendant cannot reasonably respond.” (Lickiss v. Financial Industry Regulatory Authority (2012) 208 Cal.App.4th 1125, 1135 (Lickiss).) “We will affirm if there is any ground on which the demurrer can properly be sustained.” (Martin, at p. 1031.) 1. Applicable Statutes of Limitations Bar Most Claims

Appellants’ dispute stems from land use decisions that occurred in 2014 and 2015, namely a notice of determination that the tank replacement project complied with CEQA and the issuance of two building permits.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Goodman v. Kennedy
556 P.2d 737 (California Supreme Court, 1976)
Farmers Insurance Exchange v. Superior Court
826 P.2d 730 (California Supreme Court, 1992)
Aubry v. Tri-City Hospital District
831 P.2d 317 (California Supreme Court, 1992)
B & P DEVELOPMENT CORP. v. City of Saratoga
185 Cal. App. 3d 949 (California Court of Appeal, 1986)
Martin v. Bridgeport Community Assn., Inc.
173 Cal. App. 4th 1024 (California Court of Appeal, 2009)
Lickiss v. Financial Industry Regulatory Authority
208 Cal. App. 4th 1125 (California Court of Appeal, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Blomquist v. County of Santa Clara CA6, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blomquist-v-county-of-santa-clara-ca6-calctapp-2022.