Blastmaster Holdings USA, LLC v. Land Coast Insulation

CourtCourt of Appeals of North Carolina
DecidedDecember 3, 2024
Docket24-347
StatusPublished

This text of Blastmaster Holdings USA, LLC v. Land Coast Insulation (Blastmaster Holdings USA, LLC v. Land Coast Insulation) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blastmaster Holdings USA, LLC v. Land Coast Insulation, (N.C. Ct. App. 2024).

Opinion

IN THE COURT OF APPEALS OF NORTH CAROLINA

No. COA24-347

Filed 3 December 2024

Wake County, No. 21 CVS 14599

BLASTMASTER HOLDINGS USA, LLC d/b/a BLASTONE INTERNATIONAL, Plaintiff,

v.

LAND COAST INSULATION, INC.; MATRIX SERVICE, INC.; PIEDMONT NATURAL GAS COMPANY, INC. a/k/a PIEDMONT NATURAL GAS CO. INC.; and FIDELITY AND DEPOSIT COMPANY OF MARYLAND, Defendants.

Appeal by Defendants from Order entered 4 January 2024 by Judge G. Bryan

Collins, Jr. in Wake County Superior Court. Heard in the Court of Appeals 24

September 2024.

Lewis Brisbois Bisgaard & Smith LLP, by Eric G. Sauls, Jonathan M. Preziosi, pro hac vice, and Brian C. Deeney, pro hac vice, for Defendant-Appellants.

Smith Debnam Narron Drake Saintsing & Myers, LLP, by Byron L. Saintsing & Joseph A. Davies, for Plaintiff-Appellee.

HAMPSON, Judge.

Factual and Procedural Background

Matrix Service, Inc. (Matrix), Piedmont Natural Gas Company, Inc. (PNG),

and Fidelity and Deposit Company of Maryland (Fidelity) (collectively, Defendants)

appeal from an Order granting Summary Judgment in favor of Plaintiff-Appellee

Blastmaster Holdings USA (Blastmaster) and denying Defendants’ Motion for Partial BLASTMASTER HOLDINGS USA, LLC V. LAND COAST INSULATION, INC.

Opinion of the Court

Summary Judgment. The Record before us tends to reflect the following:

On or about 30 April 2019, Matrix entered into a contract with PNG (the

Primary Contract) to perform certain engineering, procurement, and construction

services for PNG’s Robeson County LNG Peak-Shaving Facility (the Project). On 3

July 2019, Matrix filed a Notice of Contract with the Robeson County Clerk of Court.

However, Matrix has never provided any evidence a Notice of Contract was posted at

the Project site at any time. Matrix entered into a Subcontract Construction

Agreement with Land Coast Insulation, Inc. (Land Coast) on 21 January 2021 for

Land Coast to provide labor and materials for the Project.

Land Coast then entered into a Credit Application with Blastmaster, pursuant

to which Blastmaster provided Land Coast with sandblasting abrasive and

equipment, rental of sandblasting equipment, and related materials and/or labor for

use on the Project. Pursuant to the Credit Agreement, between 22 February and 23

August 2021, Land Coast ordered a total of $323,050.47 in sandblasting services and

rental equipment from Blastmaster for use on the Project. During the course of Land

Coast’s work on the Project, it submitted periodic invoices to Matrix for the labor and

materials it had furnished in a given period. With each invoice, Land Coast also

provided a Subcontractor’s Partial Lien Waiver and Release. The partial lien waivers

stated:

[Land Coast], in consideration of payment in the amount of $ [invoice amount] and contingent only upon the receipt of payment, waives and releases any right which it now has [or] may

-2- BLASTMASTER HOLDINGS USA, LLC V. LAND COAST INSULATION, INC.

have in the future to claim a mechanics’ lien or any other lien rights, and waives and releases all other claims or actions of any kind (whether billed or unbilled) against (a) the real property on which the Project is located; (b) the improvements and other property located thereon; and (c) Contractor and Owner and their partners, parents, members, subsidiaries and affiliates, at all tiers[.]

Under the partial lien waivers, Land Coast certified it had paid all of its

subcontractors, suppliers, and employees for the labor and materials connected to the

Project. Land Coast submitted the relevant invoices and partial lien waivers on 24

February 2021, 23 March 2021, 25 May 2021, 28 May 2021, 9 July 2021, and 2 August

2021. Matrix terminated Land Coast from the Project for cause on 23 August 2021.

On 14 September 2021, Blastmaster filed and served a Claim of Lien on Real

Property and a Notice of Claim of Lien Upon Funds to Matrix and PNG, asserting a

lien on real property in the amount of $323,050.47, plus interest and costs. Matrix

then executed a Release of Lien Bond with Fidelity. At the time Blastmaster filed its

Claim of Lien, Matrix’s work on the Project was ongoing. As of 16 September 2021,

two days after Blastmaster filed and served a Claim of Lien and Notice of Claim of

Lien Upon Funds, Matrix had three outstanding invoices with PNG: one for

$2,500,000.00; another for $164,476.81; and a third for $5,511,084.88—totaling

$8,175,561.69.

On 28 October 2021, Blastmaster filed a Complaint in Wake County District

Court against Land Coast, Matrix, and PNG, alleging breach of contract, claim of lien

on real property, wrongful payment by PNG to Matrix, and wrongful payment by

-3- BLASTMASTER HOLDINGS USA, LLC V. LAND COAST INSULATION, INC.

Matrix to Land Coast. On 3 December 2021, Blastmaster filed an Amended

Complaint adding Fidelity as a defendant and making an additional allegation of

claim on corporate surety bond to discharge a statutory lien. Matrix and PNG filed

their Answers on 4 January 2022, and Fidelity filed its Answer on 7 January 2022.

In its Answer, Matrix filed a counterclaim against Blastmaster. Blastmaster filed a

Motion to Dismiss Matrix’s counterclaim on 25 January 2022. Matrix and PNG filed

their Answers to the Amended Complaint on 26 January 2022. On 15 February 2022,

Blastmaster filed a Renewed Motion to Dismiss Matrix’s counterclaim.

This matter was transferred to Wake County Superior Court by consent order

on 9 March 2022. On 12 May 2022, the trial court denied Blastmaster’s Renewed

Motion to Dismiss Matrix’s Counterclaim. Blastmaster filed a Motion for Summary

Judgment on 20 March 2023. After a continuance, Defendants filed a Motion for

Partial Summary Judgment against Blastmaster on 10 October 2023. The summary

judgment Motions came on for hearing on 16 November 2023. On 4 January 2024,

the trial court entered an Order granting Blastmaster’s Motion for Summary

Judgment and denying Defendants’ Motion for Partial Summary Judgment. The

Order awarded Blastmaster a subrogation lien in the principal amount of

$323,050.47 with 18% interest per annum from 14 April 2021 until the date of the

Order, and an interest rate of 8% per year beginning after entry of the Order until

paid in full. Defendants timely filed Notice of Appeal on 11 January 2024.

Issue

-4- BLASTMASTER HOLDINGS USA, LLC V. LAND COAST INSULATION, INC.

The dispositive issue on appeal is whether the trial court erred by granting

Summary Judgment for Blastmaster based on: (I) its application of N.C. Gen. Stat. §

44A-23(c); or (II) the existence of genuine issues of material fact.1

Analysis

I. Construction Lien Statute

“Our standard of review of an appeal from summary judgment is de novo; such

judgment is appropriate only when the record shows that there is no genuine issue

as to any material fact and that any party is entitled to a judgment as a matter of

law.” In re Will of Jones, 362 N.C. 569, 573, 669 S.E.2d 572, 576 (2008) (citation and

quotation marks omitted); see also Rawls & Assocs. v. Hurst, 144 N.C. App. 286, 289,

550 S.E.2d 219, 222 (2001) (“A summary judgment motion should be granted when,

based upon the pleadings and supporting materials, the trial court determines that

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rawls & Associates v. Hurst
550 S.E.2d 219 (Court of Appeals of North Carolina, 2001)
Craig Ex Rel. Craig v. New Hanover County Board of Education
678 S.E.2d 351 (Supreme Court of North Carolina, 2009)
Electric Supply Co. of Durham, Inc. v. Swain Electrical Co.
403 S.E.2d 291 (Supreme Court of North Carolina, 1991)
Vulcan Materials Co. v. Fowler Contracting Corp.
433 S.E.2d 462 (Court of Appeals of North Carolina, 1993)
In Re the Will of Jones
669 S.E.2d 572 (Supreme Court of North Carolina, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
Blastmaster Holdings USA, LLC v. Land Coast Insulation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blastmaster-holdings-usa-llc-v-land-coast-insulation-ncctapp-2024.