IN THE COURT OF APPEALS OF NORTH CAROLINA
No. COA24-347
Filed 3 December 2024
Wake County, No. 21 CVS 14599
BLASTMASTER HOLDINGS USA, LLC d/b/a BLASTONE INTERNATIONAL, Plaintiff,
v.
LAND COAST INSULATION, INC.; MATRIX SERVICE, INC.; PIEDMONT NATURAL GAS COMPANY, INC. a/k/a PIEDMONT NATURAL GAS CO. INC.; and FIDELITY AND DEPOSIT COMPANY OF MARYLAND, Defendants.
Appeal by Defendants from Order entered 4 January 2024 by Judge G. Bryan
Collins, Jr. in Wake County Superior Court. Heard in the Court of Appeals 24
September 2024.
Lewis Brisbois Bisgaard & Smith LLP, by Eric G. Sauls, Jonathan M. Preziosi, pro hac vice, and Brian C. Deeney, pro hac vice, for Defendant-Appellants.
Smith Debnam Narron Drake Saintsing & Myers, LLP, by Byron L. Saintsing & Joseph A. Davies, for Plaintiff-Appellee.
HAMPSON, Judge.
Factual and Procedural Background
Matrix Service, Inc. (Matrix), Piedmont Natural Gas Company, Inc. (PNG),
and Fidelity and Deposit Company of Maryland (Fidelity) (collectively, Defendants)
appeal from an Order granting Summary Judgment in favor of Plaintiff-Appellee
Blastmaster Holdings USA (Blastmaster) and denying Defendants’ Motion for Partial BLASTMASTER HOLDINGS USA, LLC V. LAND COAST INSULATION, INC.
Opinion of the Court
Summary Judgment. The Record before us tends to reflect the following:
On or about 30 April 2019, Matrix entered into a contract with PNG (the
Primary Contract) to perform certain engineering, procurement, and construction
services for PNG’s Robeson County LNG Peak-Shaving Facility (the Project). On 3
July 2019, Matrix filed a Notice of Contract with the Robeson County Clerk of Court.
However, Matrix has never provided any evidence a Notice of Contract was posted at
the Project site at any time. Matrix entered into a Subcontract Construction
Agreement with Land Coast Insulation, Inc. (Land Coast) on 21 January 2021 for
Land Coast to provide labor and materials for the Project.
Land Coast then entered into a Credit Application with Blastmaster, pursuant
to which Blastmaster provided Land Coast with sandblasting abrasive and
equipment, rental of sandblasting equipment, and related materials and/or labor for
use on the Project. Pursuant to the Credit Agreement, between 22 February and 23
August 2021, Land Coast ordered a total of $323,050.47 in sandblasting services and
rental equipment from Blastmaster for use on the Project. During the course of Land
Coast’s work on the Project, it submitted periodic invoices to Matrix for the labor and
materials it had furnished in a given period. With each invoice, Land Coast also
provided a Subcontractor’s Partial Lien Waiver and Release. The partial lien waivers
stated:
[Land Coast], in consideration of payment in the amount of $ [invoice amount] and contingent only upon the receipt of payment, waives and releases any right which it now has [or] may
-2- BLASTMASTER HOLDINGS USA, LLC V. LAND COAST INSULATION, INC.
have in the future to claim a mechanics’ lien or any other lien rights, and waives and releases all other claims or actions of any kind (whether billed or unbilled) against (a) the real property on which the Project is located; (b) the improvements and other property located thereon; and (c) Contractor and Owner and their partners, parents, members, subsidiaries and affiliates, at all tiers[.]
Under the partial lien waivers, Land Coast certified it had paid all of its
subcontractors, suppliers, and employees for the labor and materials connected to the
Project. Land Coast submitted the relevant invoices and partial lien waivers on 24
February 2021, 23 March 2021, 25 May 2021, 28 May 2021, 9 July 2021, and 2 August
2021. Matrix terminated Land Coast from the Project for cause on 23 August 2021.
On 14 September 2021, Blastmaster filed and served a Claim of Lien on Real
Property and a Notice of Claim of Lien Upon Funds to Matrix and PNG, asserting a
lien on real property in the amount of $323,050.47, plus interest and costs. Matrix
then executed a Release of Lien Bond with Fidelity. At the time Blastmaster filed its
Claim of Lien, Matrix’s work on the Project was ongoing. As of 16 September 2021,
two days after Blastmaster filed and served a Claim of Lien and Notice of Claim of
Lien Upon Funds, Matrix had three outstanding invoices with PNG: one for
$2,500,000.00; another for $164,476.81; and a third for $5,511,084.88—totaling
$8,175,561.69.
On 28 October 2021, Blastmaster filed a Complaint in Wake County District
Court against Land Coast, Matrix, and PNG, alleging breach of contract, claim of lien
on real property, wrongful payment by PNG to Matrix, and wrongful payment by
-3- BLASTMASTER HOLDINGS USA, LLC V. LAND COAST INSULATION, INC.
Matrix to Land Coast. On 3 December 2021, Blastmaster filed an Amended
Complaint adding Fidelity as a defendant and making an additional allegation of
claim on corporate surety bond to discharge a statutory lien. Matrix and PNG filed
their Answers on 4 January 2022, and Fidelity filed its Answer on 7 January 2022.
In its Answer, Matrix filed a counterclaim against Blastmaster. Blastmaster filed a
Motion to Dismiss Matrix’s counterclaim on 25 January 2022. Matrix and PNG filed
their Answers to the Amended Complaint on 26 January 2022. On 15 February 2022,
Blastmaster filed a Renewed Motion to Dismiss Matrix’s counterclaim.
This matter was transferred to Wake County Superior Court by consent order
on 9 March 2022. On 12 May 2022, the trial court denied Blastmaster’s Renewed
Motion to Dismiss Matrix’s Counterclaim. Blastmaster filed a Motion for Summary
Judgment on 20 March 2023. After a continuance, Defendants filed a Motion for
Partial Summary Judgment against Blastmaster on 10 October 2023. The summary
judgment Motions came on for hearing on 16 November 2023. On 4 January 2024,
the trial court entered an Order granting Blastmaster’s Motion for Summary
Judgment and denying Defendants’ Motion for Partial Summary Judgment. The
Order awarded Blastmaster a subrogation lien in the principal amount of
$323,050.47 with 18% interest per annum from 14 April 2021 until the date of the
Order, and an interest rate of 8% per year beginning after entry of the Order until
paid in full. Defendants timely filed Notice of Appeal on 11 January 2024.
Issue
-4- BLASTMASTER HOLDINGS USA, LLC V. LAND COAST INSULATION, INC.
The dispositive issue on appeal is whether the trial court erred by granting
Summary Judgment for Blastmaster based on: (I) its application of N.C. Gen. Stat. §
44A-23(c); or (II) the existence of genuine issues of material fact.1
Analysis
I. Construction Lien Statute
“Our standard of review of an appeal from summary judgment is de novo; such
judgment is appropriate only when the record shows that there is no genuine issue
as to any material fact and that any party is entitled to a judgment as a matter of
law.” In re Will of Jones, 362 N.C. 569, 573, 669 S.E.2d 572, 576 (2008) (citation and
quotation marks omitted); see also Rawls & Assocs. v. Hurst, 144 N.C. App. 286, 289,
550 S.E.2d 219, 222 (2001) (“A summary judgment motion should be granted when,
based upon the pleadings and supporting materials, the trial court determines that
Free access — add to your briefcase to read the full text and ask questions with AI
IN THE COURT OF APPEALS OF NORTH CAROLINA
No. COA24-347
Filed 3 December 2024
Wake County, No. 21 CVS 14599
BLASTMASTER HOLDINGS USA, LLC d/b/a BLASTONE INTERNATIONAL, Plaintiff,
v.
LAND COAST INSULATION, INC.; MATRIX SERVICE, INC.; PIEDMONT NATURAL GAS COMPANY, INC. a/k/a PIEDMONT NATURAL GAS CO. INC.; and FIDELITY AND DEPOSIT COMPANY OF MARYLAND, Defendants.
Appeal by Defendants from Order entered 4 January 2024 by Judge G. Bryan
Collins, Jr. in Wake County Superior Court. Heard in the Court of Appeals 24
September 2024.
Lewis Brisbois Bisgaard & Smith LLP, by Eric G. Sauls, Jonathan M. Preziosi, pro hac vice, and Brian C. Deeney, pro hac vice, for Defendant-Appellants.
Smith Debnam Narron Drake Saintsing & Myers, LLP, by Byron L. Saintsing & Joseph A. Davies, for Plaintiff-Appellee.
HAMPSON, Judge.
Factual and Procedural Background
Matrix Service, Inc. (Matrix), Piedmont Natural Gas Company, Inc. (PNG),
and Fidelity and Deposit Company of Maryland (Fidelity) (collectively, Defendants)
appeal from an Order granting Summary Judgment in favor of Plaintiff-Appellee
Blastmaster Holdings USA (Blastmaster) and denying Defendants’ Motion for Partial BLASTMASTER HOLDINGS USA, LLC V. LAND COAST INSULATION, INC.
Opinion of the Court
Summary Judgment. The Record before us tends to reflect the following:
On or about 30 April 2019, Matrix entered into a contract with PNG (the
Primary Contract) to perform certain engineering, procurement, and construction
services for PNG’s Robeson County LNG Peak-Shaving Facility (the Project). On 3
July 2019, Matrix filed a Notice of Contract with the Robeson County Clerk of Court.
However, Matrix has never provided any evidence a Notice of Contract was posted at
the Project site at any time. Matrix entered into a Subcontract Construction
Agreement with Land Coast Insulation, Inc. (Land Coast) on 21 January 2021 for
Land Coast to provide labor and materials for the Project.
Land Coast then entered into a Credit Application with Blastmaster, pursuant
to which Blastmaster provided Land Coast with sandblasting abrasive and
equipment, rental of sandblasting equipment, and related materials and/or labor for
use on the Project. Pursuant to the Credit Agreement, between 22 February and 23
August 2021, Land Coast ordered a total of $323,050.47 in sandblasting services and
rental equipment from Blastmaster for use on the Project. During the course of Land
Coast’s work on the Project, it submitted periodic invoices to Matrix for the labor and
materials it had furnished in a given period. With each invoice, Land Coast also
provided a Subcontractor’s Partial Lien Waiver and Release. The partial lien waivers
stated:
[Land Coast], in consideration of payment in the amount of $ [invoice amount] and contingent only upon the receipt of payment, waives and releases any right which it now has [or] may
-2- BLASTMASTER HOLDINGS USA, LLC V. LAND COAST INSULATION, INC.
have in the future to claim a mechanics’ lien or any other lien rights, and waives and releases all other claims or actions of any kind (whether billed or unbilled) against (a) the real property on which the Project is located; (b) the improvements and other property located thereon; and (c) Contractor and Owner and their partners, parents, members, subsidiaries and affiliates, at all tiers[.]
Under the partial lien waivers, Land Coast certified it had paid all of its
subcontractors, suppliers, and employees for the labor and materials connected to the
Project. Land Coast submitted the relevant invoices and partial lien waivers on 24
February 2021, 23 March 2021, 25 May 2021, 28 May 2021, 9 July 2021, and 2 August
2021. Matrix terminated Land Coast from the Project for cause on 23 August 2021.
On 14 September 2021, Blastmaster filed and served a Claim of Lien on Real
Property and a Notice of Claim of Lien Upon Funds to Matrix and PNG, asserting a
lien on real property in the amount of $323,050.47, plus interest and costs. Matrix
then executed a Release of Lien Bond with Fidelity. At the time Blastmaster filed its
Claim of Lien, Matrix’s work on the Project was ongoing. As of 16 September 2021,
two days after Blastmaster filed and served a Claim of Lien and Notice of Claim of
Lien Upon Funds, Matrix had three outstanding invoices with PNG: one for
$2,500,000.00; another for $164,476.81; and a third for $5,511,084.88—totaling
$8,175,561.69.
On 28 October 2021, Blastmaster filed a Complaint in Wake County District
Court against Land Coast, Matrix, and PNG, alleging breach of contract, claim of lien
on real property, wrongful payment by PNG to Matrix, and wrongful payment by
-3- BLASTMASTER HOLDINGS USA, LLC V. LAND COAST INSULATION, INC.
Matrix to Land Coast. On 3 December 2021, Blastmaster filed an Amended
Complaint adding Fidelity as a defendant and making an additional allegation of
claim on corporate surety bond to discharge a statutory lien. Matrix and PNG filed
their Answers on 4 January 2022, and Fidelity filed its Answer on 7 January 2022.
In its Answer, Matrix filed a counterclaim against Blastmaster. Blastmaster filed a
Motion to Dismiss Matrix’s counterclaim on 25 January 2022. Matrix and PNG filed
their Answers to the Amended Complaint on 26 January 2022. On 15 February 2022,
Blastmaster filed a Renewed Motion to Dismiss Matrix’s counterclaim.
This matter was transferred to Wake County Superior Court by consent order
on 9 March 2022. On 12 May 2022, the trial court denied Blastmaster’s Renewed
Motion to Dismiss Matrix’s Counterclaim. Blastmaster filed a Motion for Summary
Judgment on 20 March 2023. After a continuance, Defendants filed a Motion for
Partial Summary Judgment against Blastmaster on 10 October 2023. The summary
judgment Motions came on for hearing on 16 November 2023. On 4 January 2024,
the trial court entered an Order granting Blastmaster’s Motion for Summary
Judgment and denying Defendants’ Motion for Partial Summary Judgment. The
Order awarded Blastmaster a subrogation lien in the principal amount of
$323,050.47 with 18% interest per annum from 14 April 2021 until the date of the
Order, and an interest rate of 8% per year beginning after entry of the Order until
paid in full. Defendants timely filed Notice of Appeal on 11 January 2024.
Issue
-4- BLASTMASTER HOLDINGS USA, LLC V. LAND COAST INSULATION, INC.
The dispositive issue on appeal is whether the trial court erred by granting
Summary Judgment for Blastmaster based on: (I) its application of N.C. Gen. Stat. §
44A-23(c); or (II) the existence of genuine issues of material fact.1
Analysis
I. Construction Lien Statute
“Our standard of review of an appeal from summary judgment is de novo; such
judgment is appropriate only when the record shows that there is no genuine issue
as to any material fact and that any party is entitled to a judgment as a matter of
law.” In re Will of Jones, 362 N.C. 569, 573, 669 S.E.2d 572, 576 (2008) (citation and
quotation marks omitted); see also Rawls & Assocs. v. Hurst, 144 N.C. App. 286, 289,
550 S.E.2d 219, 222 (2001) (“A summary judgment motion should be granted when,
based upon the pleadings and supporting materials, the trial court determines that
only questions of law, not fact, are to be decided.” (citation omitted)). “Under a de
novo review, the court considers the matter anew and freely substitutes its own
judgment for that of the lower tribunal.” Craig ex rel. Craig v. New Hanover Cnty.
Bd. of Educ., 363 N.C. 334, 337, 678 S.E.2d 351, 354 (2009) (citation and quotation
marks omitted).
This Court has recently addressed subrogation lien rights of second- and third-
1 Defendants additionally contend the trial court erred by denying their Motion for Partial
Summary Judgment seeking dismissal of Blastmaster’s claim for a subrogation lien on real property. Because we conclude the trial court did not err by granting Blastmaster’s Motion for Summary Judgment, we do not reach this issue.
-5- BLASTMASTER HOLDINGS USA, LLC V. LAND COAST INSULATION, INC.
tier subcontractors arising from the same underlying Project in Atlantech
Distribution, Inc. v. Land Coast Insulation, Inc., et al, _ N.C. App. _, 905 S.E.2d 224
(2024). There, the Court considered the caselaw around subrogation lien rights and
its interaction with the statutes governing subcontractors’ lien rights and property
owners’ liability when a general contractor or subcontractor fails to pay its
subcontractor. We recognized the General Assembly’s enactment of N.C. Gen. Stat.
§ 44A-23 as creating statutory mechanisms by which a property owner may protect
itself from a risk of double payment to contractors and subcontractors, including the
use of lien waivers. Indeed, in that case, the same Defendants raised identical
arguments as they do here. This Court rejected those arguments, concluding “partial
lien waivers do not extinguish a subcontractor’s subrogation rights; however, a
partial lien waiver may limit the amount of a subcontractor’s claim to the amount
remaining on the primary contract following the latest partial lien waiver if that
amount is less than the amount owed to the subcontractor.” Id. at 229 (citing Vulcan
Materials Co. v. Fowler Contracting Corp., 111 N.C. App. 919, 922, 433 S.E.2d 462,
464 (1993) and Elec. Supply Co. of Durham, Inc. v. Swain Elec. Co., Inc., 328 N.C.
651, 661, 403 S.E.2d 291, 297 (1991)).
Thus, consistent with our recent precedent, we conclude Blastmaster retained
its subrogation lien rights to the extent its claim as of the latest partial lien waiver
issued was less than the amount remaining on the Primary Contract. Here,
Blastmaster filed and served a Claim of Lien and a Notice of Claim of Lien Upon
-6- BLASTMASTER HOLDINGS USA, LLC V. LAND COAST INSULATION, INC.
Funds to Matrix and PNG on 14 September 2021 for $323,050.47. Land Coast
submitted its last partial lien waiver before its termination on or about 30 July 2021.
Although Matrix submitted another partial lien waiver to PNG on 16 September
2021, Blastmaster had already filed and served its Claim of Lien; thus, we consider
only the last partial lien waiver preceding Blastmaster’s Claim of Lien. It is
undisputed that following Land Coast’s last partial lien waiver, Matrix had three
outstanding invoices totaling $8,175,561.69. Thus, because the amount of
Blastmaster’s claim was less than the amount outstanding on the Primary Contract
when Blastmaster perfected its Subrogation Lien, Blastmaster was entitled to lien
rights for the entirety of its claim.
Additionally, Defendants note a different statute—N.C. Gen. Stat. § 22B-5—
differentiates partial lien waivers from final lien waivers.2 They then assert: “Being
thoroughly familiar with the construction industry’s reliance upon both interim lien
waivers and final lien waivers . . . , the Legislature would have used the phrase ‘final
lien waiver’ in N.C. Gen. Stat. § 44A-23(c) if that were the only type of waiver that
could affect a lower tier subcontractor’s right to assert a subrogated lien against real
property.” We disagree.
Section 22B-5 provides in full:
2 Despite this argument being only briefly raised by Defendants to this Court in Atlantech—
and then only in a Reply Brief—it, nevertheless, features heavily in their pending Petition for Discretionary Review to the North Carolina Supreme Court. Defendants now raise substantially the same argument here as in their pending Petition for Discretionary Review.
-7- BLASTMASTER HOLDINGS USA, LLC V. LAND COAST INSULATION, INC.
(a) Provisions in lien waivers, releases, construction agreements as defined in G.S. 22B-1(f)(1), or design professional agreements as defined in G.S. 22B-1(f)(5) purporting to require a promisor to submit a waiver or release of liens or claims as a condition of receiving interim or progress payments due from a promisee under a construction agreement or design professional agreement are void and unenforceable unless limited to the specific interim or progress payment actually received by the promisor in exchange for the lien waiver.
(b) This section does not apply to the following:
(1) Lien waivers or releases for final payments.
(2) Agreements to settle and compromise disputed claims after the claim has been identified by the claimant in writing regardless of whether the promisor has initiated a civil action or arbitration proceeding.
N.C. Gen. Stat. § 22B-5 (2023). Under this provision, lien claimants may only waive
claims for which they have been paid to date and cannot waive future lien claims for
which they have not been paid. See “§ 1:31. Public Policy Limitations on Common
Construction Contract Provisions—Limits on Lien Waivers,” N.C. CONSTR. L. (Aug.
2024). This is to say partial lien waivers are unenforceable unless they are limited
specifically to the payment actually received. This is consistent with this Court’s
interpretation of N.C. Gen. Stat. § 44A-23: a partial lien waiver reduces the amount
of a party’s liability by the amount of the payment. Thus, when a subcontractor issues
a partial lien waiver in exchange for a payment, the property owner’s liability is
reduced by the amount of that payment. However, a second- or third-tier
subcontractor retains its lien claim and can enforce that claim to the extent there is
-8- BLASTMASTER HOLDINGS USA, LLC V. LAND COAST INSULATION, INC.
an outstanding balance on the primary contract.
Further, although it is true this provision differentiates between partial and
final lien waivers, a careful reading of the statute bolsters our interpretation of the
statute at issue here. Subsection (b) of § 22B-5 states the above section does not apply
to “[l]ien waivers or releases for final payments.” N.C. Gen. Stat. § 22B-5(b) (2023)
(emphasis added). Merriam-Webster defines “or” as “(1) used as a function word to
indicate an alternative, the equivalent or substitutive character of two words or
phrases, or approximation or uncertainty.” Or, THE MERRIAM-WEBSTER DICTIONARY
(11th ed. 2022). Under this definition, we read the term “lien waiver” as “the
equivalent or substitutive character” of the term that follows: “releases for final
payments.” Similarly, Black’s Law Dictionary addresses the use of “or” in statutory
construction: “in a legal instrument, and joins a conjunctive list to combine items,
while or joins a disjunctive list to create alternatives.” Conjunctive/Disjunctive
Canon, BLACK’S LAW DICTIONARY (12th ed. 2024). Thus, N.C. Gen. Stat. § 22B-5 does
not apply to final lien waivers; rather, a final lien waiver can eliminate all liability.
This bolsters the above interpretation because a partial lien waiver only releases a
property owner from the amount of liability tied to each partial lien waiver. While
the General Assembly added language clarifying some lien waivers as partial in §
22B-5, when it referred simply to “lien waivers” it meant releases for final payment—
final lien waivers.
Additionally, we note N.C. Gen. Stat. § 22B-5 was enacted in 2022—nine years
-9- BLASTMASTER HOLDINGS USA, LLC V. LAND COAST INSULATION, INC.
after N.C. Gen. Stat. § 44A-23(c) was enacted. Thus, although Section 22B-5
differentiates between partial and final lien waivers, it does not necessarily follow
that the General Assembly had the same understanding or perception of different
types of lien waivers in 2013. Indeed, the General Assembly declined to recognize
partial lien waivers in 2012 when it rejected proposed amendments to N.C. Gen. Stat.
§ 44A-12, which included required forms for partial lien waivers and final lien
waivers, as well as language specifying the differing effect of partial versus final lien
waivers on the effective date of lien claims. Compare H.B. 1052, 2011 Gen. Assemb.,
2012 Reg. Sess. (N.C. 2012) (proposed version 22 May 2012) and H.B. 1052, 2011 Gen.
Assemb., 2012 Reg. Sess. (N.C. 2012) (adopted version 12 July 2012). We are,
therefore, not persuaded Section 22B-5 requires a contrary reading of the term “lien
waivers” in § 44A-23; rather, we conclude it bolsters this Court’s prior interpretation.
Thus, based on the pleadings and materials in the Record, we conclude Blastmaster
was entitled to judgment as a matter of law for the full amount of its lien.
II. Issues of Material Fact
Defendants also contend the trial court erred in granting summary judgment
for Blastmaster because there were genuine issues of material fact. Defendants
specifically argue there was no evidence proving Blastmaster’s equipment was
directly utilized on the Project after Land Coast abandoned the Project; thus, there is
a genuine issue of material fact as to whether all the equipment for which
Blastmaster asserted its lien was directly used to improve the Project “for all the time
- 10 - BLASTMASTER HOLDINGS USA, LLC V. LAND COAST INSULATION, INC.
periods covered by its invoices and lien claims.” Therefore, Defendants assert,
Blastmaster may not be entitled to the amount it sought for the use of its equipment
after Land Coast left the Project. We disagree.
As above, “[o]ur standard of review of an appeal from summary judgment is de
novo; such judgment is appropriate only when the record shows that there is no
genuine issue as to any material fact and that any party is entitled to a judgment as
a matter of law.” In re Will of Jones, 362 N.C. at 573, 669 S.E.2d at 576 (citation and
quotation marks omitted); see also Rawls, 144 N.C. App. at 289, 550 S.E.2d at 222
(“A summary judgment motion should be granted when, based upon the pleadings
and supporting materials, the trial court determines that only questions of law, not
fact, are to be decided.” (citation omitted)).
Blastmaster sought relief under Chapter 44A, Article 2 of our General
Statutes. This Article provides for lien rights to a second-tier subcontractor, which it
defines as “[a] person who contracts with a first tier subcontractor to improve real
property.” N.C. Gen. Stat. § 44A-7(8) (2023). The term “improve” under this Section
means “[t]o build, effect, alter, repair, or demolish any improvement upon, connected
with, or on or beneath the surface of any real property, . . . and rental of equipment
directly utilized on the real property in making the improvement.” N.C. Gen. Stat. §
44A-7(3) (2023). Thus, to make a claim for a lien on real property, Blastmaster must
prove its equipment was “directly utilized” on the Project.
According to Defendants, Land Coast abandoned its work under the Painting
- 11 - BLASTMASTER HOLDINGS USA, LLC V. LAND COAST INSULATION, INC.
Subcontract on 23 July 2021, and it did not return to the Project prior to its
termination on 23 August 2021. Blastmaster submitted nine invoices totaling
$61,293.80 for use of its equipment after Land Coast abandoned the Project.
Defendants contend there was no evidence in the Record showing Blastmaster’s
rental equipment was directly utilized on the Project after Land Coast’s abandonment
of the Project on 23 July 2021; thus, in Defendants’ view, there was a genuine issue
of material fact as to whether all of the equipment for which Blastmaster asserted its
lien was directly utilized to improve the Project through the dates for which it billed
Land Coast.
Defendants point to no caselaw or statute to support their assertion that the
requirement equipment be “directly utilized” to improve real property means such
equipment must be continuously utilized. It is undisputed that Blastmaster
furnished the rental equipment at issue for the Project, the equipment remained
onsite at the Project at all times covered by Blastmaster’s invoices, and that the
equipment was, in fact, directly utilized on the Project. Further, Defendants
acknowledge none of the invoices Blastmaster submitted cover a time period after
Land Coast was terminated from the Project. Defendants’ only contention, then, is
that Blastmaster needed to prove the equipment was actively used on the Project
after Land Coast’s abandonment of the Project. However, such a requirement is not
supported by our caselaw or the plain language of the statute. Indeed, we agree with
Plaintiff that such a requirement would be untenable in a case such as this, involving
- 12 - BLASTMASTER HOLDINGS USA, LLC V. LAND COAST INSULATION, INC.
rental equipment which is made available on a particular site and therefore cannot
be rented by the supplier to a different customer. In the absence of statutory or
caselaw support, we decline to read into § 44A-7(8) a requirement that a supplier
establish rental equipment was used throughout the entirety of a time period at issue.
Based on the Record and materials before us, Plaintiff established its rental
equipment was used on the Project and was onsite at the Project until Land Coast
was terminated from the Project. Further, Plaintiff’s invoices cover only the period
of time prior to Land Coast’s termination from the Project. Thus, we conclude
Plaintiff established its rental equipment was directly utilized on the Project for
purposes of satisfying the definitions of “second-tier subcontractor” and “improve”
under N.C. Gen. Stat. § 44A-7(3) and (8). Therefore, there was no genuine issue of
material fact before the trial court. Consequently, Plaintiff was entitled to summary
judgment.
Conclusion
Accordingly, for the foregoing reasons, we affirm the trial court’s Order
granting summary judgment for Plaintiff.
AFFIRMED.
Judges STROUD and ZACHARY concur.
- 13 -