Blanchette v. Superior Court of Imperial County

8 Cal. App. 5th 521, 213 Cal. Rptr. 3d 552, 2017 WL 541939, 2017 Cal. App. LEXIS 105
CourtCalifornia Court of Appeal
DecidedFebruary 10, 2017
DocketD070545
StatusPublished

This text of 8 Cal. App. 5th 521 (Blanchette v. Superior Court of Imperial County) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blanchette v. Superior Court of Imperial County, 8 Cal. App. 5th 521, 213 Cal. Rptr. 3d 552, 2017 WL 541939, 2017 Cal. App. LEXIS 105 (Cal. Ct. App. 2017).

Opinion

*524 Opinion

BENKE, Acting P. J.

—In this construction defect case we are called upon to interpret the notice and time requirements of the Right to Repair Act (the act), Civil Code 1 section 895 et seq. As we explain, the goal of the act is to resolve, if possible, construction defect claims without resort to litigation. In brief, the act requires that, before initiating litigation, construction defect claimants must give a builder notice of alleged defects and if a builder wishes, an opportunity to inspect and repair the noticed defects. The act requires that a claimant’s notice set forth the defects “in reasonable detail” sufficient to determine the nature and location of the alleged defects. (§ 910, subd. (a).) A builder receiving the notice has 14 days in which to acknowledge receipt of the claim and 14 additional days in which, if the builder wishes, to inspect the premises; within 30 days after completing an inspection, a builder may make an offer to repair the claimed defects. The act requires that its time limits and other requirements be strictly construed. (§ 930, subd. (a).)

Here, we grant petitioner William Blanchette’s petition for a writ of mandate and direct that the trial court vacate its order staying proceedings pending Blanchette’s compliance with the act. As we explain, Blanchette’s compliance with the act was relieved by virtue of real party GHA, Enterprises’s (GHA) 2 failure to timely acknowledge receipt of Blanchette’s notice of a claim. Contrary to GHA’s argument, the act’s goal of promptly resolving claims without resort to litigation cannot be achieved by permitting homebuilders to serve tardy responses to claims or to ignore them entirely.

FACTUAL AND PROCEDURAL BACKGROUND

Blanchette is the owner of one of 28 homes constructed by GHA. No later than February 2, 2016, Blanchette served GHA with notice of a claim, which set forth a number of alleged defects in all 28 homes; Blanchette’s notice used, almost verbatim, the language section 896 employs in setting forth building standards, the violation of which gives rise to actionable claims against homebuilders. 3 Attached to the notice of claims was a list of the *525 names and addresses of each of the owners of the 28 homes in the development.

*526 GHA responded to Blanchette’s notice of claims by letter dated February 23, 2016. GHA asserted the construction defects set forth in Blanchette’s *527 claim were not alleged with reasonable detail, as required by section 910, subdivision (a); nonetheless GHA offered to inspect the homes.

Blanchette responded to GHA on February 26, 2016. Blanchette asserted that GHA’s response was untimely and excused him and the other homeowners from any obligations under the act.

Thereafter, Blanchette filed a construction defect class action complaint against GHA in the trial court. GHA responded to the complaint by moving to stay the action until Blanchette satisfied the prelitigation requirements of the act. Blanchette opposed the motion on the grounds GHA had not timely responded to his notice of claims.

The trial court agreed with GHA that Blanchette’s notice of claim lacked detail sufficient to trigger GHA’s obligations under the act. Accordingly, the trial court stayed the action pending completion of the notice and inspection procedures required by the act and ordered that Blanchette serve a new notice of claims to “identify each individual claimant by address,” to “provide a defect list for each subject property, which sets forth [the] alleged defects,” to *528 “set forth the location, nature and severity of each alleged defect,” and to identify “the code section(s) [the claimants] contend each alleged defect violates.”

Blanchette filed a petition for a writ of mandate in which he challenged the trial court’s order. We issued an order to show cause.

DISCUSSION

I

Blanchette’s petition raises a novel issue under the act: when must defects in a notice of claim be raised by a builder? We also note that because the trial court enforced its interpretation of the act by way of a pretrial stay, Blanchette has no adequate remedy by way of appeal. The novel issue raised by Blanchette’s petition and the absence of an adequate remedy by way of appeal support writ review here. (See Omaha Indemnity Co. v. Superior Court (1989) 209 Cal.App.3d 1266, 1273-1274 [258 Cal.Rptr. 66].)

II

The act, its purposes, and provisions were in many important respects considered by the court in Darling v. Superior Court (2012) 211 Cal.App.4th 69 [149 Cal.Rptr.3d 331] (Darling). In Darling, the court rejected a homeowner’s contention the document production required of homebuilders under the act (§912) could be initiated in the absence of the notice of claims required by section 910. (Darling, at p. 84.) However, neither Darling nor any other case which has come to our attention has directly considered when defects in the notice of claim must be asserted by a builder.

As the court in Darling noted, the prelitigation requirements of the act are set forth in chapter 4 of the act, commencing with section 910. (Darling, supra, 211 Cal.App.4th at p. 82.) The purpose of chapter 4, “is to give a builder the opportunity to resolve a homeowner’s construction defect claim in an expeditious and nonadverserial manner. [Citation.]” (Darling, at p. 82; see also Stats. 2002, ch. 722, § 1(b) & (c), p. 4247 [chapter 4 intended to provided for “prompt and fair resolution of construction defect claims” and “procedures for early disposition of construction defects” claims.].)

“Chapter 4 begins with section 910. Section 910 requires a homeowner to serve notice of a construction defect claim to commence the prelitigation process, before bringing a lawsuit. The statute provides in relevant part: ‘Prior to filing an action against any party alleged to have contributed to a violation of the standards set forth in Chapter 2 (commencing with Section *529 896), the claimant shall initiate the following prelitigation procedures: [¶] (a) The claimant or his or her legal representative shall provide written notice via certified mail, overnight mail, or personal delivery to the builder, in the manner prescribed in this section, of the claimant’s claim that the construction of his or her residence violates any of the standards set forth in Chapter 2 (commencing with Section 896). That notice shall provide the claimant’s name, address, and preferred method of contact, and shall state that the claimant alleges a violation pursuant to this part against the builder, and shall describe the claim in reasonable detail sufficient to determine the nature and location, to the extent known, of the claimed violation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Darling v. Superior Court
211 Cal. App. 4th 69 (California Court of Appeal, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
8 Cal. App. 5th 521, 213 Cal. Rptr. 3d 552, 2017 WL 541939, 2017 Cal. App. LEXIS 105, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blanchette-v-superior-court-of-imperial-county-calctapp-2017.