Blaine-Hays Construction Co. v. Union Planters National Bank (In re Edgewater Motel, Inc.)

121 B.R. 962, 1988 Bankr. LEXIS 2663
CourtUnited States Bankruptcy Court, E.D. Tennessee
DecidedMarch 23, 1988
DocketBankruptcy No. 3-86-00599; Adv. No. 3-87-0081
StatusPublished
Cited by3 cases

This text of 121 B.R. 962 (Blaine-Hays Construction Co. v. Union Planters National Bank (In re Edgewater Motel, Inc.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, E.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blaine-Hays Construction Co. v. Union Planters National Bank (In re Edgewater Motel, Inc.), 121 B.R. 962, 1988 Bankr. LEXIS 2663 (Tenn. 1988).

Opinion

MEMORANDUM

JOHN C. COOK, Bankruptcy Judge.

This case involves an action by a contractor against the bankrupt owner of a construction project and its principal lender. Contending that it was not paid its last draw request on the construction project, the contractor seeks compensatory and punitive damages, an equitable lien, and equitable subordination against the principal lender based upon a number of legal theories. The parties previously consented to the entry of a final judgment by this court pursuant to 28 U.S.C. § 157(a)(2). Jurisdiction lies under 28 U.S.C. §§ 1334 and 157. Having conducted a two-day trial on the issues raised in this lawsuit, the court now enters its findings of fact and conclusions of law pursuant to Bankruptcy Rule 7052. References to plaintiff’s exhibits will be designated “Px.” and the exhibit number. [964]*964References to defendant’s exhibits will be designated “Dx” and the exhibit number.

Findings of Fact

1. Blaine-Hays Construction Company (“Blaine-Hays”) is a Tennessee corporation engaged in the general contracting business with its principal place of business in Knoxville, Tennessee.

2. Union Planters National Bank (“UPNB”) is a national banking association with its principal office in Memphis, Tennessee.

3. Edgewater Motel, Inc. (“Edgewater”) is a Tennessee corporation which owns the project involved in this suit. Edgewater filed a petition for relief under chapter 11 of the Bankruptcy Code on March 25, 1986.

4. In 1983 the debtor, Edgewater and its principal shareholder and officer, Mr. R.B. Hailey, began plans for the construction of the Edgewater Motel in Gatlinburg, Tennessee (the “project”). Mr. Hailey began negotiating with Dorman Blaine of Blaine-Hays in the hope that Blaine-Hays would become the general contractor for the project. Mr. Hailey also commenced efforts to obtain a construction loan from UPNB and permanent financing from Security Federal Savings and Loan Association. Mr. Hailey obtained a written commitment from Security Federal dated September 30, 1983 (Px 1A).

5. On December 27, 1983, Mr. Fountain Barksdale of UPNB prepared a credit proposal for submission to UPNB’s Senior Loan Committee (Px IB). Mr. Barksdale was the UPNB officer who was initially responsible for the construction loan to Edgewater.

6. During the negotiation period in the latter part of 1983, Dorman Blaine met with Mr. Hailey, Mr. Barksdale, and Miles McMahan, an employee of Mr. Hailey’s, and discussed the project. Mr. Blaine was not willing to rely upon Mr. Hailey to provide the funds needed for construction. He was told by Mr. Hailey and later by Mr. Barksdale that the construction loan would come from UPNB.

7. Union Planters Mortgage Company, a division of UPNB, provided Mr. Hailey with a commitment letter dated January 17, 1984 (Px 1C) setting forth the terms upon which it would make a construction loan to Edgewater. The loan was to be in a principal amount of $7 million and was to be secured by a first deed of trust on the project premises. The commitment letter required the borrower to pay certain “costs” in connection with the loan and acquisition and construction of the property from funds other than the loan proceeds. Among these costs were $1.5 million for “Leased Equipment.” The commitment letter also required copies of executed leases with Walter Heller & Company covering “all furniture, fixtures, equipment, elevators, fireplaces and heating and air conditioning units” to be reviewed and approved by UPNB prior to closing of the construction loan.

8. A “preliminary budget” was attached as Exhibit B to the commitment letter. That budget was as follows:

Total Cost Amount Paid Balance to be Paid
Land acquisition 883,740 225,000 658,740
Building Construction loan Interest 5,585,000 600,000 600,000* 4,985,000 600,000
Permanent loan/ brokerage fees 298,000 172,100 125,900
Construction loan fees 114,500 114,500
Legal and recording fees 20,000 20,000
Survey, soil testing, etc. 18.000 15.000 3.000
[965]*965Total Cost Amount Paid Balance to be Paid
Architectural & engineering fees 350,000 50,000 300,000
Contingency 350,000 175,000
Pre-opening expenses . 300,000 300,000
Furniture, fixtures and equipment 900,000 900,000*
TOTAL 9,419,240 2,137,100 7,282,140

9. The amounts in the right hand column of the budget were to be paid from the construction loan proceeds, plus 12 monthly cash contributions by the owner of $23,500 each. The amounts in the second column supposedly were already paid or were to be paid by the owner from other sources.

10. According to the commitment letter and budget, $4,985,000, the construction loan proceeds and the owner’s equity contributions, would be used to pay Blaine-Hays for the cost of building the project. The remaining $600,000 needed to pay the contractor to install elevators, fireplaces, heating and air conditioning units would come from a lease financing arrangement with parties other than UPNB.

11. By this time Blaine-Hays through Dorman Blaine had tentatively agreed to become general contractor for the project. The terms of the construction contract required Blaine-Hays to obtain performance bonds to ensure Blaine-Hays’ performance under the contract. Although Dorman Blaine had been told by both Mr. Hailey and Mr. Barksdale that UPNB would make the construction loan, Mr. Blaine wanted firm assurance from the bank that construction funds would be available for the construction.

12. Sometime prior to entering into the construction contract, Mr. Blaine telephoned Mr. Barksdale who assured him that UPNB’s construction loan would cover the contractual price of the construction contract, namely, $5,585,950. Mr. Barks-dale also agreed to confirm in writing this representation.

13. After receiving Mr. Barksdale’s assurance, Blaine-Hays informed its bonding company that UPNB had verified that its construction loan would cover the construction contract and that a letter confirming the oral representations would be forthcoming.

14. Blaine-Hays and the owner thereafter signed a construction contract for a lump sum amount of $5,585,950 (the “construction contract”) (Px 2B). Although the construction contract does not show the date it was signed, it recites that it was made as of February 20, 1984.

15. The construction loan made to Edgewater by UPNB was closed on March 1, 1984.

16. Shortly before the closing of the construction loan between Edgewater and UPNB, Dorman Blaine instructed Miles McMahan not to turn over the construction contract to UPNB before receiving a commitment letter from the bank confirming the earlier representations by Mr. Barks-dale on the financing. Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kryder v. Estate
296 F. Supp. 3d 892 (M.D. Tennessee, 2017)
The Farmers Bank v. Clint B. Holland
Court of Appeals of Tennessee, 2012

Cite This Page — Counsel Stack

Bluebook (online)
121 B.R. 962, 1988 Bankr. LEXIS 2663, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blaine-hays-construction-co-v-union-planters-national-bank-in-re-tneb-1988.