Blackmon Mooring of Austin, LLC v. St. Edward's University, Inc.

CourtTexas Court of Appeals, 3rd District (Austin)
DecidedMay 29, 2026
Docket03-24-00334-CV
StatusPublished

This text of Blackmon Mooring of Austin, LLC v. St. Edward's University, Inc. (Blackmon Mooring of Austin, LLC v. St. Edward's University, Inc.) is published on Counsel Stack Legal Research, covering Texas Court of Appeals, 3rd District (Austin) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blackmon Mooring of Austin, LLC v. St. Edward's University, Inc., (Tex. Ct. App. 2026).

Opinion

TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN

NO. 03-24-00334-CV

Blackmon Mooring of Austin, LLC, Appellant

v.

St. Edward’s University, Inc., Appellee

FROM THE 200TH DISTRICT COURT OF TRAVIS COUNTY NO. D-1-GN-18-001472, THE HONORABLE JAN SOIFER, JUDGE PRESIDING

MEMORANDUM OPINION

This is an appeal from a summary judgment dismissing a claim for breach of

contract. After a burst pipe flooded one of its on-campus student dormitories, St. Edward’s

University, Inc. (SEU) retained Blackmon Mooring of Austin, LLC to mitigate the damage and

rebuild portions of the dorm. The parties entered into a Reconstruction Contract, which provided

that SEU would pay Blackmon Mooring on a cost-plus basis with no guaranteed maximum price.

The Scope of Work attached to the Reconstruction Contract established an “estimated budgetary

price” for the work, which Blackmon Mooring could “exceed” with “notice” to SEU and its

casualty insurer, Federal Insurance Company.

As the work progressed, Blackmon Mooring notified SEU and Federal that it

would be exceeding the estimated budget, though it did not say by how much. Neither SEU nor

Federal objected. Both emphasized the importance of Blackmon Mooring completing the work as soon as possible. Blackmon Mooring completed the work as instructed, but when it sought

final payment in an amount far exceeding the estimated budget, SEU refused to pay the total

amount invoiced.

Blackmon Mooring sued SEU for breach of contract to recover the unpaid

balance, and SEU moved for summary judgment. Relying largely on the parties’ negotiations

and contemporaneous communications, SEU argued that the “estimated budgetary price” was a

“not-to-exceed” number that set a ceiling on SEU’s contractual obligation absent a written

Modification to the Reconstruction Contract. Because the parties never amended the

Reconstruction Contract to increase the amount of the estimated budget, and because Blackmon

Mooring had already been paid an amount exceeding the estimated budget, SEU argued that the

summary-judgment evidence established that SEU had fully satisfied its contractual obligations

and that there was no breach of contract as a matter of law. The trial court agreed, granted

SEU’s motion, and dismissed Blackmon Mooring’s claim for breach of contract.

We hold that the Reconstruction Contract unambiguously requires that SEU pay

Blackmon Mooring on a cost-plus basis with no guaranteed maximum price; that the estimated

budget is an estimate that can be exceeded with notice (as opposed to a written Modification);

and that, in holding otherwise, the trial court improperly relied on inadmissible parol evidence

that varies, adds to, and contradicts the plain meaning of the contract’s unambiguous text.

Accordingly, we reverse the trial court’s summary judgment and remand for further proceedings

consistent with our opinion.

2 BACKGROUND

In November 2018, a large chilled-water pipe burst at the Pavilions dorm on

SEU’s campus, flooding the building and rendering it uninhabitable. SEU notified Federal of the

covered flood event and retained Blackmon Mooring to mitigate the flood damage and rebuild

the dorm. This appeal concerns Blackmon Mooring’s latter reconstruction work, which it

performed under a Reconstruction Contract.

Blackmon Mooring and SEU sign the Reconstruction Contract

The parties and Federal engaged in extensive negotiations before signing the

Reconstruction Contract on February 1, 2019. The fully integrated instrument consists of two

principal “Contract Documents”: (1) the base Contract and (2) an attached Scope of Work.

Under Article 1 of the Contract, Blackmon Mooring agreed to “execute the Work

described in the Contract Documents,” including the Scope of Work. The Scope of Work, in

turn, listed fifteen broad categories of “structural” work that Blackmon Mooring would complete

to restore the Pavilions dorm to a “pre-water damaged condition.”

Under Article 3 of the Contract, SEU agreed to pay Blackmon Mooring the

“Contract Sum” for Blackmon Mooring’s “performance of the Contract.” The “Contract Sum”

was defined in Section 3.1, which allowed the parties to select one of three options:

(1) “Stipulated Sum,” which would set a fixed, total price for the Work and thereby place the risk of cost overruns on Blackmon Mooring;

(2) “Combined Time & Material basis and Cost of the Work plus the Contractor’s Fee, in accordance with Contractor’s Scope of Work, attached as Exhibit A,” a cost-plus-fee arrangement that would establish a formula for calculating the price without setting a cap and thereby place the risk of cost overruns on SEU; or

(3) “Cost of the Work plus the Contractor’s Fee with a Guaranteed Maximum Price,” a cost-plus-fee arrangement that would establish a formula for calculating the

3 price while setting a cap and thereby shift the risk of cost overruns exceeding the cap to Blackmon Mooring.

The parties selected the second option for the Contract Sum, according to which

Blackmon Mooring would be paid on a cost-plus basis with no guaranteed maximum price. The

parties thus rejected a stipulated sum or guaranteed maximum price for the Contract Sum. 1

Consistent with Article 3, the Scope of Work, attached to the Reconstruction

Contract as Exhibit A, in a section titled “Pricing,” provided that Blackmon Mooring would be

paid on a cost-plus basis: “This reconstruction service will be performed on a combined Time

& Material basis and Cost of the Work Plus Contractor’s Fees basis, as outlined below.” Like

other cost-plus contracts, the Scope of Work provided rate schedules for labor, equipment, and

materials. The Scope of Work also included an “estimated budgetary price” of just over

$4 million and provided that all parties would be “notified ASAP” if at any point that “budgetary

number” was “going to be exceeded”:

The estimated budgetary price for the work and services as outlined in this scope will be $4,043,303[]. If at any time the budgetary number is going to be exceeded, all parties will be notified ASAP.

Under Article 6 of the Contract, the parties agreed that the Reconstruction

Contract was a fully integrated agreement that could only be amended by Modification:

1 The other sections of Article 3 further reflected that the parties rejected a “Stipulated Sum” or “Guaranteed Maximum Price” for the Contract Sum. For Section 3.2, the section for establishing the basis for a “Stipulated Sum,” and for Section 3.4, the section for establishing the “Contractor’s Fee with a Guaranteed Maximum Price,” the parties marked “N/A” and left the remainder of the sections blank. For Section 3.3, the section for establishing the Contractor’s Fee under the second payment option, the parties agreed to a fee of 20% of the Cost of the Work.

4 The Contract Documents form the Contract for construction. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations or agreements, either written or oral. The Contract may be amended or modified only by a Modification.

“Modification” was defined as “a written amendment to the Contract signed by both parties.”

Blackmon Mooring notifies SEU and Federal that it will exceed the estimated budget

After the parties signed the Reconstruction Contract, Blackmon Mooring began

rebuilding the dorm. In February, Blackmon Mooring invoiced SEU for $1,010,825.75. Then,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State National Bank v. Academia, Inc.
802 S.W.2d 282 (Court of Appeals of Texas, 1991)
Hubacek v. Ennis State Bank
317 S.W.2d 30 (Texas Supreme Court, 1958)
Cobb v. Thomas
565 S.W.2d 281 (Court of Appeals of Texas, 1978)
Guillermo Garza D/B/A Wilhome Builders & Construction v. Jesse Cantu
431 S.W.3d 96 (Court of Appeals of Texas, 2013)
Syring-Workman, Inc. v. Colbert
532 S.W.2d 708 (Court of Appeals of Texas, 1976)
Gay v. Stratton
559 S.W.2d 131 (Court of Appeals of Texas, 1977)
Uri, Inc. v. Kleberg Cnty.
543 S.W.3d 755 (Texas Supreme Court, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Blackmon Mooring of Austin, LLC v. St. Edward's University, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/blackmon-mooring-of-austin-llc-v-st-edwards-university-inc-txctapp3-2026.