Blackhawk Neff v. Kusevich

Superior Court of Pennsylvania·Decided February 29, 2016·No. 1721 WDA 2014·Unpublished

Opinion

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

BLACKHAWK NEFF, INC., IN THE SUPERIOR COURT OF PENNSYLVANIA

Appellant

v.

KUSEVICH CONTRACTING, INC., Appellee No. 1721 WDA 2014

Appeal from the Order Entered September 22, 2014 In the Court of Common Pleas of Allegheny County Civil Division at No(s): G.D. 12-011044

BEFORE: BOWES, OLSON, AND STABILE, JJ. MEMORANDUM BY BOWES, J.: FILED FEBRUARY 29, 2016 Blackhawk Neff, Inc. (“Blackhawk”) appeals from the September 22, 2014 order enforcing a settlement agreement reached by it with Kusevich Contracting Inc. (“Kusevich”). We affirm.

On June 27, 2012, Blackhawk instituted this action against Kusevich, both of which were prime contractors on a construction project for the Pine- Richland School District (“Pine-Richland”). Blackhawk averred in this lawsuit that it incurred damages due to delay on the project attributable to Kusevich. Specifically, one of Kusevich’s sub-contractors, W&K Steel, LLC, was unable to perform its contractual obligations, which were then assumed by a different entity. Blackhawk averred that W&K Steel, LLC’s default caused Blackhawk to start its aspect of the project late and that it incurred increased costs associated with its need to accelerate its schedule to meet

its deadline. Blackhawk pled breach of contract and quantum meruit causes of action.

The events pertinent to the inquiry of whether there is an enforceable settlement agreement with respect to this action began on September 19, 2014. On that day, the parties were prepared to proceed to a jury trial with a jury empaneled. Just prior to the start of trial, Blackhawk agreed to accept $30,000 to settle this action. That amount was to be paid by Pine- Richland, which had retained approximately $119,000 that it owed to Kusevich due to this lawsuit. On September 19, 2014, Edward Hirshberg, Esquire, counsel for Pine-Richland, was present in the courtroom. Maurice Nernberg, Esquire, represented Kusevich, and Paul Robinson, Esquire, was Blackhawk’s attorney.

The transcript of the proceedings indicates that the court initiated the conversation by stating, “We have an agreement here between the two attorneys.” Pre-Trial Proceeding, 9/19/14 and 9/22/14, at 3. The agreement involved Pine-Richland because, as noted, it had withheld payment of $119,000 that it owed to Kusevich due to the pendency of the within action by Blackhawk. Mr. Nernberg, Kusevich’s lawyer, was asked to place that accord on the record. He reported:

Total settlement is $30,000.

We will agree that we will write a letter to Pine-Richland.

They will release $30,000. Pine-Richland is withholding one hundred nineteen thousand some odd dollars.

That upon release, they may release $30,000 to Blackhawk Neff. Blackhawk Neff will write them that they are satisfied to release all funds. If they want to make it conditional on their getting $30,000, that's fine.

Id.

At that point, Mr. Robinson, Blackhawk’s attorney, interjected and stated, “We are settling the case for $30,000 that Kusevich Contracting is paying. Because Pine-Richland, the School District, is holding the money, we want it to come directly from Pine-Richland.” Id. at 4. Mr. Robinson continued, “If Pine-Richland for some reason -- and I have already talked with Pine-Richland's attorney who is in the back of the room -- would refuse to pay us, the $30,000, then Kusevich Contracting still must pay the $30,000 because this settlement is with Kusevich Contracting.” Id. Mr. Robinson also outlined that Pine-Richland could have until the end of the following week to decide whether to participate in the settlement. Id. at 6.

Mr. Nernberg then objected to this recitation of the terms of the settlement. He reported that the agreement was that Pine-Richland was to pay Blackhawk the $30,000 directly from the funds that Pine-Richland had withheld from Kusevich and that Kusevich had not agreed to pay the money if Pine-Richland would not agree to release the $30,000 to Blackhawk. Mr. Nernberg stated, “We will write Pine-Richland. We are satisfied to release all funds. Out of the release they can get $30,000. That's all we're doing.” Id. at 6. Paul Kusevich, who was appearing at trial on behalf of Kusevich, explained that Pine-Richland would have a strong incentive to pay the

$30,000 to Blackhawk. He said, “The only reason Pine-Richland held $119,000 is because of the Blackhawk Neff claim. No other reason. Pine- Richland owes that money to Kusevich. It's an outstanding payable to them that's left over from the contract balance. It's in both people's best interest to get that done.” Id. at 15. Mr. Kusevich continued that he and Robert Neff, who was owner of Blackhawk and present in the courtroom, were comfortable with the arrangement and wanted to ensure that “when Pine- Richland gets the document, that they understand completely that we jointly both feel the same way that all the moneys should be released. It’s over.” Id. at 16.

Mr. Robinson then acceded to the settlement being structured in that manner. “Maybe that's the way to do it. Make it a contingent settlement. If Pine-Richland doesn't pay the $30,000, then there's no settlement. I would agree with that a hundred percent. I would agree. Give Pine-Richland the opportunity to say yes. Because if they say yes, there's no issue here.” Id. at 7. Mr. Robinson later confirmed that if Pine-Richland refused to pay the $30,000, “we then can have our trial. There's no settlement. I'm fine with that as well.” Id. at 14-15.

Since the jury had been selected, the parties did not want the trial continued and the jury to be released. Thus, the court asked Pine-Richland’s attorney when he would have a response. Mr. Hirshberg responded, “I can't speak to that today, Your Honor. I can certainly ask the question.”

Id. at 8. Mr. Robinson then observed that, since it was a Friday, Pine- Richland could consider the matter over the weekend, and the jurors could be informed to return on Monday in case there was no settlement by that time.

On the afternoon of September 19, 2014, Kusevich and Blackhawk sent a joint letter, executed by Mr. Nernberg and Mr. Robinson, to Pine- Richland. The letter stated, “Kusevich authorizes Pine-Richland School District to release all funds being held pertaining to the Pine-Richland additions and alterations as follows: $30,000 in the amount held will be released to Blackhawk Neff. Blackhawk Neff has no further claims against Kusevich Contracting or Pine-Richland School District.” Id. at 23-24. The letter was hand-delivered to the solicitor of Pine-Richland that day.

At 7:45 a.m. on Monday September 22, 2014, Pine-Richland’s solicitor sent an email to Kusevich and Blackhawk indicating that the board had agreed to release the funds as outlined in the September 19, 2014 letter. That e-mail stated as follows.

Subject: Blackhawk v Kusevich CONFIDENTIAL: FOR SETTLEMENT PURPOSES ONLY.

Messrs Robinson and Nernberg: I apprised the appropriate representatives of the School District of the settlement terms which were brought over to my office Friday afternoon. Despite the very short notice, the District was able to reach a consensus as follows:

The District is willing to make the thirty thousand dollar payment to Blackhawk Neff from the funds (slightly in excess of $119,000) being withheld from Kusevich by the District as a result of the filing of the claim by Blackhawk Neff.

The District can make that payment within 21 days. However, the District would like Kusevich to confirm that, in the District making that payment, Kusevich is waiving and releasing that portion of its claim to the funds, up to the settlement amount of $30,000. In other words, Kusevich agrees that its remaining claim for monies to be released by the District is slightly less than $90,000, or the original Blackhawk Neff claim amount, minus the $30 000 payment to Blackhawk Neff. "Once the parties confirm this agreement, I will contact the District and get the payment process started. Please confirm."

Free access — add to your briefcase to read the full text and ask questions with AI

Blackhawk Neff v. Kusevich, (Pa. Ct. App. 2016).

Blackhawk Neff v. Kusevich (Blackhawk Neff v. Kusevich) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Commonwealth v. Walker
878 A.2d 887 (Superior Court of Pennsylvania, 2005)
Trowbridge v. McCaigue
992 A.2d 199 (Superior Court of Pennsylvania, 2010)
Mastroni-Mucker v. Allstate Insurance
976 A.2d 510 (Superior Court of Pennsylvania, 2009)
Thunberg v. Strause
682 A.2d 295 (Supreme Court of Pennsylvania, 1996)
Gargano v. Terminix International Co.
784 A.2d 188 (Superior Court of Pennsylvania, 2001)
Step Plan Services, Inc. v. Koresko
12 A.3d 401 (Superior Court of Pennsylvania, 2010)
Felix v. Giuseppe Kitchens & Baths, Inc.
848 A.2d 943 (Superior Court of Pennsylvania, 2004)
Adams v. Adams
848 A.2d 991 (Superior Court of Pennsylvania, 2004)
Lundy v. Manchel
865 A.2d 850 (Superior Court of Pennsylvania, 2004)
Commonwealth v. Kennedy
868 A.2d 582 (Superior Court of Pennsylvania, 2005)
Commonwealth v. Preston
904 A.2d 1 (Superior Court of Pennsylvania, 2006)