Blackhawk Construction Co. v. Village of Homewood

175 N.E. 427, 343 Ill. 182
CourtIllinois Supreme Court
DecidedFebruary 18, 1931
DocketNo. 19679. Reversed and remanded.
StatusPublished
Cited by6 cases

This text of 175 N.E. 427 (Blackhawk Construction Co. v. Village of Homewood) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blackhawk Construction Co. v. Village of Homewood, 175 N.E. 427, 343 Ill. 182 (Ill. 1931).

Opinions

Under a special assessment proceeding filed in the county court of Cook county the board of local improvements of the village of Homewood on October 25, 1926, entered into *Page 184 a written contract with the Blackhawk Construction Company for a sewer system, consisting of a disposal plant, a 24-inch outlet about one mile long and lateral drains about thirty-four miles long, at a total cost of almost $500,000. The contractor claims that the work was completed about December 14, 1927, and that the board of local improvements failed to file in the county court a certificate of cost and completion. On June 15, 1928, the contractor filed in the county court its petition, alleging, in substance, that it had constructed the work in substantial compliance with the ordinance more than thirty days prior to the date of the filing of the petition, that the improvement was then in use by the village, and that the board of local improvements had failed to file its certificate as provided in section 84 of the Local Improvement act. The prayer was for a rule on the board to file the certificate or to show cause why it did not do so. The court ordered the board to file its certificate within ten days or show cause why the same should not be filed. The board filed a certificate in which it set up the making of the contract, the completion of the work, and alleged that the board unanimously voted not to accept the work, for the reason that it was not completed in substantial compliance with the ordinance and contract; that there was an excessive infiltration of ground water in the sewer over the entire system, and particularly in the last mile in the main outlet immediately above the disposal plant; that this excessive infiltration was due to defective workmanship, material and faulty construction of the joints between the sections of tile; that the contract and ordinance provided that the degree of tightness of the joints should be such that after the system was completed, and before any house connections were made, the ground water leakage under a saturated soil should not exceed 5000 gallons per mile of sewer per day; that during the construction of the sewer the contractor represented to the board that owing to the wetness of the soil it would be very difficult, if not impossible, *Page 185 to construct a tight joint by using a hot-poured bituminous joint, but that by using a prestite bituminous joint, which is called a "pre-cast joint," it could construct a tighter and more satisfactory joint, and that the contract provided that use of pre-cast bituminous joints would be considered a compliance with the ordinance; that thereupon the contractor proceeded to use the prestite bituminous joint, which, if properly installed, would have produced as satisfactory a joint as the hot-poured joint provided for in the ordinance. The certificate described certain tests made on January 25, 1928, and May 14, 1928, in the 24-inch outlet, and alleged that the large quantity of infiltrated ground water passing through the sewer reduced the capacity of the plant approximately fifty per cent. The certificate then gave a statement of cost of the improvement, the amount required to pay interest on bonds and vouchers, and concluded by asking the court to consider and determine whether the facts stated in the certificate were true and whether the contractor had built the improvement in substantial compliance with the ordinance. Evidence was heard upon both sides as to the manner in which the sewer had been constructed, the condition of the joints and the amount of ground water passing through the sewer. At the close of the evidence leave was granted certain attorneys to appear as additional counsel for the contractor and for George Repp, who held some of the bonds. Paul E. Klapsteg and Amanda Klapsteg, as property owners, obtained leave to file objections to the acceptance of the improvement, their objections being substantially the same as set forth in the answer of the board of local improvements. They were granted leave to file an affidavit in support of their motion to file objections. Appellants made a motion to strike this affidavit and these objections from the files, which motion was overruled. At the close of the evidence appellants submitted to the court a written order containing findings of fact and conclusions of law to the effect that the improvement had been completed *Page 186 in substantial compliance with the contract and ordinance. The court refused to enter this order. On April 5, 1929, an order was entered which found that the improvement had not been completed in substantial compliance with the ordinance; that the certificate of costs and completion, in which the board of local improvements certified that the contract had not been completed in compliance with the ordinance, was true and the board was ordered to proceed to complete the improvement in substantial accordance with the ordinance. From that order an appeal has been prosecuted to this court.

A motion has been made in this court to strike the bill of exceptions from the files and dismiss the appeal on the ground that section 84 of the Local Improvement act provides that the order of the court shall be conclusive upon all of the parties and no appeal therefrom or writ of error thereto shall be allowed to modify or reverse the same. It is insisted by appellants, under this motion, that the provisions of section 84 apply only to an appeal to reverse an order based upon a misconception by the trial court as to the facts; that the right of appeal is not denied under section 84 where errors of law are made, where there is a controversy relative to a proper construction of the section, or where questions of law arise which require the determination of the trial judge sitting as a court; that an appeal lies under section 123 of the County Court act (Cahill's Stat. 1929, p. 856,) where questions of law, the construction of statutes, the competency of evidence and the construction of contracts are involved, and that this appeal is under section 123 even though the questions may have arisen while the court was proceeding under section 84 of the Local Improvement act.

Section 83 of the Local Improvement act authorizes the board of local improvements to make contracts, receive all bonds, do all acts pertaining to the execution of the work and fix the time for the commencement and the completion *Page 187 of the work. It provides that all work must be done under the direction and to the satisfaction of the board, And all contracts must contain a provision to that effect. Section 84 provides that within thirty days after the final completion and acceptance of the work the board of local improvements shall cause the costs thereof to be certified in writing to the court, together with an amount estimated necessary to pay the accruing interest on bonds. Provision is made for a rebate, if one is necessary. If the assessment is divided into installments the board in said certificate must state whether or not the improvement conforms substantially to the requirements of the ordinance and must make application to the court to determine whether the facts stated in the certificate are true. The court shall fix a time and place for a hearing by giving notice as therein provided, and at the time and place for such hearing the court shall proceed to hear the application and any objections which may be filed, and the certificate of the board shall be prima facie evidence that the matters therein stated are true.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

People Ex Rel. Dolan v. Dusher
104 N.E.2d 775 (Illinois Supreme Court, 1952)
The Maccabees v. City of North Chicago
125 F.2d 330 (Seventh Circuit, 1942)
Village of Elmwood Park v. W. A. Black Co.
185 N.E. 230 (Illinois Supreme Court, 1933)
Gjellefald Construction Co. v. City of South Beloit
183 N.E. 211 (Illinois Supreme Court, 1932)
Wilmette State Bank v. City of DesPlaines
181 N.E. 696 (Illinois Supreme Court, 1932)
City of Alton v. Hellrung
179 N.E. 127 (Illinois Supreme Court, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
175 N.E. 427, 343 Ill. 182, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blackhawk-construction-co-v-village-of-homewood-ill-1931.