Black & Veatch International Co. v. Foster Wheeler Energy Corp.

211 F.R.D. 641, 2002 U.S. Dist. LEXIS 23870, 2002 WL 31777796
CourtDistrict Court, D. Kansas
DecidedDecember 3, 2002
DocketNo. 00-2402-JAR
StatusPublished
Cited by10 cases

This text of 211 F.R.D. 641 (Black & Veatch International Co. v. Foster Wheeler Energy Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Black & Veatch International Co. v. Foster Wheeler Energy Corp., 211 F.R.D. 641, 2002 U.S. Dist. LEXIS 23870, 2002 WL 31777796 (D. Kan. 2002).

Opinion

ORDER ON MOTION FOR SANCTIONS

ROBINSON, District Judge.

This action arises out of the construction of the Hanfeng Power Plant, Units 1 and 2 (Project) in the Peoples Republic of China. Plaintiff Black & Veatch International Company (Black & Veatch) contracted with Defendant Foster Wheeler Energy Corporation (Foster Wheeler) to design, supply and fabricate structural steel for the Project, in exchange for payment of $20,990,657. This matter comes before the Court pursuant to Foster Wheeler’s Motion for Sanctions Against Plaintiff and for an Award of Costs and Attorneys’ Fees to Defendant (Doc. 204). The motion requests the imposition of sanctions, including costs and fees, due to Black & Veatch’s bad faith failure to comply with Judge Waxse’s May 2, 2002 Memorandum and Order (Court Order), and due to Black & Veatch’s bad faith failure to comply with the discovery obligations imposed by the Federal Rules of Civil Procedure. The motion seeks sanctions in the form of: dismissing with prejudice all of Black & Veatch’s claims in excess of the contract price (over $1.4 million); 1 judgment for Foster Wheeler on its counterclaim ($488,854); and reasonable costs and fees incurred by Foster Wheeler.

The Court Order sets forth the facts leading up to this dispute. The Court will not repeat those facts and will only address the dispute from that point forward.2 At the heart of the dispute are design calculations utilized by Black & Veatch at the time it made purchases (mill orders) of structural steel for a power plant in China.3 Judge [643]*643Waxse found that these interim design calculations were within the scope of Foster Wheeler’s discovery request, and the fact that they did not exist in their original form and must be recreated did not take such calculations outside the scope of the request. Judge Waxse also found that Foster WTieeler’s need for the materials requested outweighed any projected’ burden on Black & Veatch, and ordered that:

(1) Plaintiff shall produce CDs containing the actual creation/modifieation dates of each of the Input Files;
(2) Plaintiff shall produce the information necessary for Defendant experts to run the Input Files on the VAX and/or UNIX in order to recreate specific design calculations existing at the time of Plaintiffs mill order;
(3) Plaintiff shall cooperate with Defendant in Defendant’s efforts to accomplish the task set forth in subsection (2) above; and
(4) The deadline before which Defendant shall designate its structural steel experts is hereby reset to August 1, 2002.
(1) Both parties shall keep accurate records regarding the time and costs associated with the tasks set forth in (1), (2), and (3) above and, if after such tasks are accomplished, the parties are unable to come to an agreement regarding allocation of such costs in terms of time and money, the parties shall file the appropriate motion; and
(2) Plaintiff and Defendant shall each pay their own costs and expenses, including attorney and expert witness fees, incurred with respect to briefing the Motion.

The Court Order makes clear that Black & Veatch is required to actively participate, jointly with Foster Wheeler, in carrying out the necessary steps to recreate the design calculations in question. The Court Order also makes clear that Black & Veatch’s cooperation must be given in a timely manner in order to permit both recreation of the design calculations and analysis of the same by Foster WTieeler’s experts prior to the August 1, 2002 deadline. In addition, the Court Order imposes on both parties a mutual interest in accomplishing the recreation of the design calculations in the most cost effective manner by providing that the costs incurred by both parties will be allocated between the parties by the Court, if the parties “are unable to come to an agreement regarding allocation of such costs.”

The Court will only address the allegations that involve potentially sanctionable conduct. The Court will address whether Black & Veatch failed to cooperate with Foster Wheeler as required by the Court Order: 1) by failing to provide personnel/hardware; 2) by refusing to give assurances requested by Foster Wheeler; 3) by providing Foster W/heeler with an incompatible CD; 4) by delaying its production of documents; 5) by delaying its response to questions in the June 11, 2002 letter; and 6) by making misrepresentations to Foster Wheeler.

1. Failure to Provide Personnel/Hardware:

The Court Order partially granted and partially denied Foster Wheeler’s motion to compel (Docs. 67 and 75). In the motion to compel, Foster Wheeler sought an order requiring, among other things, that Black & Veatch fully cooperate with Foster Wheeler’s engineering and/or computer experts’ inspections and use of Black & Veatch’s computer hardware, software and related technical documents as Foster Wheeler’s experts deemed appropriate to run all Input Files necessary to obtain/or recreate the specific design calculations on the UNIX Platform and/or VAX Platform belonging to Black & Veatch. Because use of Black & Veatch’s hardware was requested, and not granted, the Court finds that Black & Veatch did not violate the Court Order by refusing such request. And, use of Black & Veatch’s engineers was neither requested nor ordered.

However, Black & Veatch was required to cooperate with Foster Wheeler in its efforts to run the Input Files on the VAX and/or UNIX in order to recreate specific design calculations existing at the time of Black & Veatch’s mill orders. Black & [644]*644Veateh argues that recreation of the design calculations “is' not really feasible because the cost would be out of proportion to the PAL claims.”4 *4 The Court Order addressed this very issue, finding that the need for the materials requested outweighed any projected burden on Black & Veateh. Black & Veateh argues that Judge Waxse was misinformed of the cost involved, noting that Judge Waxse apparently accepted Foster Wheeler’s speculation that only 15-20 PPADS runs5 would be needed, rather than the testimony of Black & Veatch’s engineer that almost all the files would need to be rerun to get an accurate representation. Black & Veateh should have either informed Judge Waxse of this, or filed a motion to reconsider. The Court Order provides that “the party resisting discovery has the obligation to provide sufficient detail and explanation about the nature of the burden in terms of time, money and procedure which would be required to produce the requested documents.”6 Thus, although Black & Veateh was not ordered to provide its hardware or engineers, it was required to cooperate with Foster Wheeler’s efforts, whether it thought they were feasible or not.

2. Refusal to give Assurances Requested by Foster Wheeler:

Because Black &

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Abbie v. Shasta County
E.D. California, 2023
Beard v. County of Stanislaus
E.D. California, 2023
Krause v. Krause
E.D. California, 2022
Chaudhry v. Smith
E.D. California, 2020

Cite This Page — Counsel Stack

Bluebook (online)
211 F.R.D. 641, 2002 U.S. Dist. LEXIS 23870, 2002 WL 31777796, Counsel Stack Legal Research, https://law.counselstack.com/opinion/black-veatch-international-co-v-foster-wheeler-energy-corp-ksd-2002.