Black Hardware Co. v. Mt. Vernon-Woodberry Mills, Inc.

72 S.W.2d 303, 1934 Tex. App. LEXIS 550
CourtCourt of Appeals of Texas
DecidedApril 20, 1934
DocketNo. 9930.
StatusPublished
Cited by4 cases

This text of 72 S.W.2d 303 (Black Hardware Co. v. Mt. Vernon-Woodberry Mills, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Black Hardware Co. v. Mt. Vernon-Woodberry Mills, Inc., 72 S.W.2d 303, 1934 Tex. App. LEXIS 550 (Tex. Ct. App. 1934).

Opinion

PLEASANTS, Chief Justice.

This suit was brought by appellee against appellant to recover damages for the alleged breach of a contract for the sale by appellee and purchase by appellant of 200 rolls of cotton duck manufactured by appellee.

The petition alleges that the contract for breach of which the suit is brought was made about January 27, 1930, by defendant and the. Turner-Halsey Company, the duly authorized agent of plaintiff. The contract is set out in full in the petition and by its terms the plaintiff agreed to sell and defendant agreed to purchase' 200 rolls of cotton duck manufactured by plaintiff to be designated and specified out of a list attached to the contract of many different grades, widths, and prices of cotton duck manufactured by plaintiff. The pleaded contract further provides that the defendant had 90 days in which to make such specification, and if defendant did not make the specification within the 90 days, plaintiff had the right to specify from the list attached to the contract the 200 roils to be purchased by the defendant. It is then alleged, in substance; that the defendant did not make the specification within 90 days, but that after the execution of the contract, defendant in performance thereof specified a number of shipments to Be made by plaintiff to defendant, such specifications being made from the list attached to the contract; that some of these shipments were made during the months of February, March, and April before the expiration of the 90 days; that plaintiff did not at the expiration of the 90 days exercise its right to specify the remaining portions of the 90 rolls contracted to be purchased by the defendant, but forebore to make such specifications for a reasonable length of time to permit defendant to fully comply with its contract; that the extension of this provision of the contract was recognized by both plaintiff and defendant in correspondence and transactions between them and by tacit understanding, and the defendant is now es-topped to deny that the extension of the 90-day provision of the contract was acquiesced in by it and in no way destroyed the contract or lessened the full force of its other provisions ; that in the months of February, March, April, May, June, July, August, September, October, and November of 1930 the defendant continued to specify and give shipping orders, and the plaintiff continued to ship under said contract of January 27, 1930, and at the prices specified and named in said contract, until in December of said year 47 rolls of the 200 rolls had been specified and delivered to the defendant under the contract. No further specifications or shipping directions were received by plaintiff thereafter.

It is then alleged that no final repudiation of the contract was made by the defendant until on or about February 1, 1931, when plaintiff’s representative called upon defendant at its office in Galveston, at which time defendant expressly notified plaintiff of its intention to repudiate its contract; that plaintiff was ready, able, and willing at all times during and after the execution of the contract and up to the time of its repudiation by defendant to fully comply with all the provisions of the contract; that 'because of the breach of its contract by the defendant and its refusal to specify the remaining 153 rolls of duck it could and would have specified and ordered under the contract, plaintiff has the right to now make such specification and to recover the difference between the market price of such cotton duck rolls at Galveston at the time of the breach of the contract and their price as fixed by the contract.

The petition first specifies the largest staple size of cotton duck within the range allowed under the contract and alleges that because of depreciation in the market value of the duck so specified plaintiff is entitled to recover from defendant the sum of $12,393. It is then alleged in the alternative, that if plaintiff is not entitled to make the specification of the large sized and higher priced cotton duck as a basis for fixing its damages, it' should recover the difference between the market value of cotton duck of the average size and price of the 47 rolls specified and purchased by defendant under the contract before its repudiation, which the petition alleges to be $2,500.

The defendant answered by a general demurrer, a number of special exceptions, the nature of which so far as material in the decision of the questions presented by this appeal will be hereinafter indicated, also by a *305 general denial and a special plea that the contract was without consideration, unilateral, and void for lack of mutuality.

The cause was tried in the court below without a jury and resulted in a judgment in favor of plaintiff. The original entry of the judgment fixed the amount of plaintiff’s recovery at the sum of $1,779.73, tout on motion of plaintiff, made and heard after adjournment of the court, the defendant having been duly notified and appearing by its attorney, the court found that there was an unintentional, mathematical clerical error in the calculation of the amount stated in the original judgment, and that the amount should have been the sum of $1,998.94. The original judgment was ordered corrected in the respect indicated ■by a judgment then rendered and entered nunc pro tunc.

The trial court at the request of appellant filed conclusions of fact and law which contain the following fact findings:

“1. On or about the 27th day of January, 1930, plaintiff and defendant entered into a contract by the terms of which plaintiff agreed to sell and defendant agreed to purchase 200 rolls of cotton duck, under the terms and conditions contained in Exhibit #1, by the pertinent provisions of which said rolls were to be specified by defendant before the expiration of ninety days from the date of said contract, from a list of duck of varying widths and grades, which list was incorporated into said contract by reference. Said list, dated February 13, 1927, contained prices upon each specification, grade or size of duck, over a range from 22 inch #12 to 90 inch #2/0, and from 32‡ per yard to $5.97 per yard, although the highest staple goods within the range allowed in said contract was 120 inch #4 wide duck listed at $3.16 per yard. The contract price of the 200 rolls covered was 37½% and 5% off of said list price on Mt. Yernon wide and sail duck, and 35% and 5% off of said list price on Woodberry sail duck. The above names and description of the duck referred to are trade names, of well defined signification in the duck business, known to both parties. Said contract contained the following provision:
“ ‘The ¡buyer agrees that any balance of this contract unspecified within the required time, may, at seller’s option, be delivered at seller’s selection, either of staple goods within the range allowed in this contract or of goods like those already specified under it, as though specified by the buyer.’
“2. During the ninety days succeeding the execution of the contract, the defendant made certain specifications of cotton duck thereunder, but did not specify the entire 200 rolls; thereafter, and until some time in January, 1931, both plaintiff and defendant treated the-contract as in full force and effect in all respects, save and except with respect to the time limitation for the specifications to be made toy defendant, and in this respect both parties treated the contract time as extended for a reasonable length of time.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

TLC Hospitality, LLC v. Pillar Income Asset Management, Inc.
570 S.W.3d 749 (Court of Appeals of Texas, 2018)
Untitled Texas Attorney General Opinion
Texas Attorney General Reports, 1981
Pace Corporation v. Jackson
284 S.W.2d 340 (Texas Supreme Court, 1955)
Willhelm Lubrication Co. v. Brattrud
268 N.W. 634 (Supreme Court of Minnesota, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
72 S.W.2d 303, 1934 Tex. App. LEXIS 550, Counsel Stack Legal Research, https://law.counselstack.com/opinion/black-hardware-co-v-mt-vernon-woodberry-mills-inc-texapp-1934.