Bitterroot River Protective Association, Inc. v. Siebel

2005 MT 60, 108 P.3d 518, 326 Mont. 241, 2005 Mont. LEXIS 62
CourtMontana Supreme Court
DecidedMarch 9, 2005
Docket03-753
StatusPublished
Cited by6 cases

This text of 2005 MT 60 (Bitterroot River Protective Association, Inc. v. Siebel) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bitterroot River Protective Association, Inc. v. Siebel, 2005 MT 60, 108 P.3d 518, 326 Mont. 241, 2005 Mont. LEXIS 62 (Mo. 2005).

Opinion

JUSTICE WARNER

delivered the Opinion of the Court.

¶1 Kenneth F. and Judith A. Siebel ( “Siebels”) and the Montana Department of Natural Resources and Conservation (“DNRC”) appeal from an Order on Petition for Judicial Review entered on August 4, 2003, in the District Court for the First Judicial District, Lewis and Clark County. Such order denied the Siebels’ applications for beneficial water use permits and held in favor of the Bitterroot River Protective Association (“BRPA”). The BRPA cross-appeals from the same judgment and order on separate grounds. We affirm.

¶2 We determine that the first issue presented is dispositive and thus address only the following issue on appeal:

¶3 Did the District Court err in concluding that the Siebels’ original applications for beneficial water use were “strawmen” or “sham” applications, and the proposed amendments to those applications *243 constituted new applications which must be denied as the Bitterroot River subbasin was closed when they were filed?

I. FACTUAL AND PROCEDURAL BACKGROUND

¶4 The Siebels submitted four applications to appropriate water in the Bitterroot River Basin in Ravalli County on March 19,1999. This filing was 10 days before the legislature closed the Bitterroot River subbasin to new water appropriations on March 29,1999. Sections 1, 3, Ch. 205, L. 1999 (codified at § 85-2-344(2), MCA).

¶5 The Siebels own a large ranch known as the Bitterroot Springs Ranch and filed these applications to appropriate water to develop four ponds-the North Pond, Southeast Pond, Vetsch Pond and Triple Pond-for the beneficial use of wildlife. At the request of the Siebels’ consultant, Land and Water, Inc. (“Land and Water”), the DNRC delayed processing the applications.

¶6 On March 24, 2000, the Siebels amended the application for the North Pond. The amendment requested permission to appropriate more than double the volume of water requested in the original application, documented a change in the place of use, and added recreation as a beneficial use.

¶7 On June 15, 2000, the DNRC wrote to Siebels’ Land and Water consultant, Karl Uhlig (“Uhlig”), informing him of deficiencies in the amended North Pond permit application and requesting additional justification for the volume and flow rate needed to support the stated beneficial uses. The letter said such information had to be received within 30 days of receipt of the letter or the Siebels could lose their priority date for the North Pond application.

¶8 The Siebels submitted amendments to the remaining three applications on June 23, 2000. The Siebels’ amended Southeast Pond application requested a volume increase from 28.8 acre-feet to 952.66 acre-feet. The Siebels also changed the point of diversion, the place of use, the means of diversion, and added fish and recreation as beneficial uses.

¶9 The amended application for the Triple Pond increased the requested volume from 74.8 acre-feet to 1,025.2 acre-feet, increased the proposed depth of the pond from 3 to 25-30 feet and added fish and recreation as beneficial uses.

¶10 The amended application for the Vetsch Pond requested an increase in volume from 45.6 acre-feet to 899.3 acre-feet, changed the means and place of diversion, and added fish and recreation as beneficial uses.

*244 ¶11 On July 7, 2000, the Siebels responded to the DNRC’s letter of June 15, stating they needed more time to gather the requested information and that they would respond by the end of August. On July 10, 2000, the DNRC sent another letter to Uhlig, at Land and Water, stating all of the applications were deficient in that the volume and flow rate for the requested beneficial uses required further justification. The DNRC indicated the applications would be denied if the requested information was not provided by August 31, 2000.

¶12 On September 28, 2000, Uhlig responded to the DNRC’s letters. On October 13,2000, the DNRC sent another letter to Uhlig informing him the applications were still incomplete and were lacking justification for the proposed volume and flow. On October 19, 2000, the DNRC again requested additional information from Uhlig, giving him 30 days to respond. Again the DNRC stated the applications would be denied if the information was not timely provided. On October 27, 2000, the Siebels provided the DNRC with the requested information.

¶13 Thereafter, the DNRC published Notice of Application and accepted objections from the public on the Siebels’ applications. The BRPA objected to the applications on the grounds that the Siebels had failed to satisfy the beneficial use requirements. The Montana Department of Fish, Wildlife and Parks, the U.S. Fish and Wildlife Service, and local resident, Jim Johnston, also objected. The DNRC scheduled a contested case hearing for November 27, 2001.

¶14 Prior to the hearing, all of the objectors except the BRPA stipulated that they would withdraw their objections if the Siebels would agree to reduce the amount of water requested for each pond. The Siebels reduced the amount of water requested for the Southeast Pond to 331.20 acre-feet, reduced the amount for the Triple Pond to 812.7 acre-feet, reduced the amount for the Vetsch Pond to 342.50 acre-feet, and reduced the amount for the North Pond to 1364.90 acre-feet.

¶15 Also prior to the hearing, the BRPA filed a Motion to Terminate the Applications, alleging the amendments were submitted in bad faith, the amended applications were new applications, and the alleged deficiencies in the applications were not cured within the time allowed by statute. The Hearing Examiner denied the Motion and denied a subsequent request to certify the Motion to the DNRC Director.

¶16 The Hearing Examiner concluded the Siebels had not proven that the quantity of water requested was the minimum amount necessary for the proposed beneficial use; had not provided evidence to establish a direct correlation between the amount of water requested and the *245 need for that amount of water to sustain the proposed beneficial uses of fish, wildlife and recreation; and had not proven the proposed use was a beneficial use for which a water right could be granted. Accordingly, on March 6, 2002, the Hearing Examiner denied the Siebels’ applications.

¶17 The Siebels filed exceptions to the Hearing Examiner’s decision. Oral argument was held on May 8, 2002, and the DNRC issued its Final Order on July 29, 2002, reversing the decision of the Hearing Examiner and granting all four of the Siebels’ applications. The DNRC concluded the Siebels had proven that the amount of water requested was “reasonably necessary” to support the proposed beneficial uses.

¶18 BRPA petitioned the District Court for review.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kirk White v. State Fund
2013 MT 187 (Montana Supreme Court, 2013)
Hyperion I & II
2013 S.D. 10 (South Dakota Supreme Court, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
2005 MT 60, 108 P.3d 518, 326 Mont. 241, 2005 Mont. LEXIS 62, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bitterroot-river-protective-association-inc-v-siebel-mont-2005.