2023 IL App (1st) 220266 No. 1-22-0266 Opinion filed June 12, 2023 First Division
IN THE
APPELLATE COURT OF ILLINOIS
FIRST DISTRICT
) LISA BITSKY and THOMAS BITSKY, ) ) Plaintiffs, ) ) v. ) ) THE CITY OF CHICAGO, a Municipal ) Corporation; CH2M HILL ENGINEERS, INC.; ) EXP FEDERAL INC., f/k/a/ Teng & Associates, ) Inc.; and ARCADIS U.S. INC., f/k/a The Rise ) Group, LLC, All d/b/a/ CTR Joint Venture; ) ENVIRONMENTAL DESIGN Appeal from the Circuit Court ) INTERNATIONAL, INC. (EDI), an Illinois of Cook County. ) Corporation; CH2M HILL ENGINEERS, INC., ) Individually; EXP FEDERAL, INC., f/k/a Teng ) & Associates, Inc., Individually; and ARCADIS Nos. 17 L 1845 ) U.S. INC., f/k/a The Rise Group, LLC, and No. 19 L 8025 (cons.) ) individually; SANCHEZ CONSTRUCTION ) SERVICES, INC., f/k/a Sanchez Construction ) Company, an Illinois Corporation; RELIABLE The Honorable ) CONSTRUCTION AND EQUIPMENT Joan E. Powell, ) COMPANY, an Illinois Corporation; Judge, presiding. ) PRECISION CEMENT COMPANY, INC.; and ) EDWARD A. MCGINLEY, Individually and ) Director of Precision Cement Company, Inc., ) ) Defendants ) ) (Lisa Bitsky, Plaintiff-Appellant; Sanchez ) Construction Services, Inc.; Reliable ) Construction and Equipment Company; Precision ) Cement Company, Inc.; and Edward A. ) McGinley, Defendants-Appellees). ) 1-22-0266
JUSTICE HYMAN delivered the judgment of the court, with opinion. Justice Coghlan concurred in the judgment and opinion. Justice Pucinski specially concurred, with opinion.
OPINION
¶1 In 2011, the City of Chicago (City) undertook a water restoration project to replace
underground water mains and install sidewalks and ramps adhering to the Americans with
Disabilities Act. The City hired CTR Joint Venture (CTR) as the project engineer and Sanchez
Constructions Services (Sanchez) as project contractor. Sanchez subcontracted the sidewalk
and ramp work to Reliable Construction and Equipment Company (Reliable), which verbally
subcontracted the cement work to Precision Cement Company, Inc. (Precision).
¶2 After the water main work was completed at the intersection, the resulting sidewalk had an
elevated section. The City and CTR inspected the work and approved it as compliant with the
contract terms, the City’s specifications, and ADA requirements.
¶3 Several years later, Lisa Bitsky was injured when her husband, Thomas Bitsky, tripped and
fell into her, while walking on the elevated sidewalk near that intersection. Believing the
elevated sidewalk was responsible for her injuries, Bitsky brought construction negligence
claims against the City and CTR Joint Venture, later adding Sanchez, Reliable, Precision, and
Precision’s owner, Edward McGinley.
¶4 After settling with the City and CTR, Bitsky proceeded against Reliable, Sanchez, and
Precision, which, after extensive discovery, filed separate motions for summary judgment.
Among their arguments: (i) they followed the plans and specifications provided by the City
and CTR when installing the sidewalk and, thus, owed no legal duty to Bitsky, (ii) Bitsky failed
to show proximate cause between her injuries and their work, (iii) the elevated sidewalk was
-2- 1-22-0266
an open and obvious condition, and (iv) they had no notice of the alleged dangerous condition
created by the raised sidewalk.
¶5 After a hearing, the trial court granted summary judgment to defendants, finding that
because they followed the requirements of their contracts and the plans, specifications, and
instructions the City and CTR provided them, they had no duty to Bitsky, specifically citing
the Illinois Supreme Court’s decision in Hunt v. Blasius, 74 Ill. 2d 203 (1978). Further, the
court noted the City and CTR inspected and approved defendants’ work.
¶6 Bitsky argues that (i) a material question of fact exists as to whether defendants deviated
from the plans when they constructed the sidewalk, (ii) the court erred in relying on Hunt and
should have applied traditional negligence factors, and (iii) if summary judgment on the
negligence counts is reversed, the court also should reverse summary judgment on her
husband’s loss of consortium claims. We agree with the trial court that Hunt is controlling, and
defendants had no duty to Bitsky where they followed the city’s plans, specifications, and
instructions. So, we affirm.
¶7 Background
¶8 Lisa Bitsky and her husband, Thomas Bitsky, were leaving a restaurant on Milwaukee
Avenue after dinner with friends Alan and Christine Brown. The couples were walking to their
cars, with Lisa Bitsky and Christine Brown walking a few feet ahead of their husbands. While
next to a building at 1286 N. Milwaukee Avenue, Thomas stumbled and fell forward, hitting
the back of Lisa’s knee with his neck and shoulder. Lisa fell forward, hitting the sidewalk with
her left leg, requiring surgery on her tibia and ankle.
¶9 Thomas did not know what caused him to fall, saying his left foot suddenly stumbled, and
when he tried to put his right foot down to catch himself, “there was nothing under it.” A
-3- 1-22-0266
photograph, introduced during depositions, shows the sidewalk abutting the building at 1286
N . Milwaukee is elevated with a 2-foot-wide by 8.29-foot-long elevation that increased from
zero inches up to 5.25 inches.
~ • ~ Water Restoration Project
,i 11 The area of the accident was pait of a 2011 water restoration project the City of Chicago
unde1took to replace and restore underground water mains and constmct sidewalks that comply
with ADA requirements. The City's Depa1tment of Transportation (COOT) hired an ai·chitect
-4- 1-22-0266
to prepare ADA design standards (CDOT standards) for contractors to use when constructing
ADA sidewalks and sidewalk ramps.
¶ 12 The City hired CTR Joint Venture as an engineering consultant on the project. CTR was
responsible for developing design and construction drawings and identifying corners that
needed restoration to bring the sidewalks into compliance with ADA and CDOT standards.
CTR contracted to ensure full compliance with ADA codes and standards.
¶ 13 Reliable was the general contractor. Reliable subcontracted with Sanchez to build ADA-
compliant curbs and sidewalks. Sanchez verbally subcontracted the concrete work to Precision.
¶ 14 Saeed Siddiqui, CTR’s restoration inspection engineer, testified by deposition that
restoration work on the project consisted of (i) pouring cement over the open trench area, after
the water main pipe had been replaced, and (ii) fixing damaged streets and sidewalks. Siddiqui
said the contractor and subcontractors did not build the elevated sidewalk, variously referred
to as a “property line curb,” a “barrier curb,” or a “Type-B curb” (hereafter, “property line
curb”). The property line curb preexisted the project and was part of the foundation of the
building at 1286 N. Milwaukee Avenue. Siddiqui said that when coming across a preexisting
property line curb, the practice is not to destroy it but to build a ramp around it. Siddiqui said
a property line curb is covered under the City’s ADA standards (CDOT ADA standard B-1-6)
and can be used, “where necessary,” when, for instance, a sidewalk has varying elevations or,
as here, a building’s foundation is exposed. Standard B-1-6 does not specify exact sizes and
dimensions for a property line curb, which depends on the needs at a specific corner.
¶ 15 Siddiqui testified he inspects the finished work to ensure it complies with ADA regulations
and follows the specifications required by the contract. If the contractor did not follow plans,
specifications, and instructions, the contractor would not get paid.
-5- 1-22-0266
¶ 16 A CTR engineer, Christopher May, testified he oversaw the repair sites and ensured the
sidewalk ramps met CDOT specifications and ADA standards. After defendants completed the
work, May conducted a quality control inspection of the sidewalk. His initial report indicated
that the corner of Milwaukee Avenue and Paulina Street did not pass inspection. But in June
2013, a CTR quality assurance inspector determined the corner to be ADA compliant.
¶ 17 Reliable was responsible for installing the water main but did not perform concrete or
sidewalk installation work. According to Todd Chianelli, Reliable’s superintendent on the
project, CTR forwarded quality control issues to Reliable, which sent them to Sanchez for
making the repairs. CTR then returned to inspect and approve the work. For Reliable to receive
final payment, which it did, CTR had to approve the sidewalks and ramps as compliant with
ADA and CDOT standards.
¶ 18 Sanchez’s project manager, Michael Byrne, testified that the company used CDOT and
ADA standards to construct the sidewalk and ramps in compliance with the City’s
specifications. Byrne was not at the Milwaukee and Paulina intersection during the work but
received quality control reports from Chris May at CTR and forwarded them to Precision, the
concrete subcontractor. Byrne said property line curbs are common in sidewalk construction,
and the one at Milwaukee and Paulina was consistent with similar repairs.
¶ 19 Joe Haughey, owner and president of Sanchez Construction, testified that the company
installed nearly 100 property line curbs in Chicago. He said CDOT design standard B-1-6, used
here, was a safe design, not dangerous or defective, and fully complied with the City’s
specifications and ADA standards. He also said nothing in the CDOT standards requires a
property line curb to be a certain height or width, and the contractor can decide based on the
requirements of the specific situation.
-6- 1-22-0266
¶ 20 Edward McGinley owned Precision, the concrete subcontractor, until it went out of
business in 2016. McGinley testified that Precision was responsible for installing the concrete
and “poured the job *** per the ADA codes.” Precision used design standard B-1-6 at that
corner because of the exposed foundation, the need to comply with slope specifications and
placement of the keystone at that corner. He considers the design to be safe.
¶ 21 Precision’s foreman, Richard Bong, said after Sanchez removed the sidewalk, Precision
installed the ramp and sidewalk. He chose design standard B-1-6 from the CDOT standards
“because that’s really the only one you can use in that corner.” He further said the property
line curb could not have been made five to six inches wide (rather than 24 inches) due to an
obstruction from the building and because the running slope had a minimum size of four feet
“so we matched the running slope sidewalk to the landing to the property line.” He
acknowledged the property line curb at that corner was not intended for people to walk on. He
also acknowledged that Chris May inspected the sidewalk and found it failed, but he thought
May misunderstood that it was a property line curb. Nonetheless, Bong went to the site, fixed
any deficiencies, and ensured compliance with ADA standards.
¶ 22 Bitsky submitted handwritten affidavits from the store owner and the store owner’s friend,
attesting to the hazardous condition created by the elevated sidewalk. The store owner stated
he asked the workers about the elevated sidewalk during construction and warned them it
would be a tripping hazard, and they told him it was “in the plan.” He said pedestrians trip over
the elevated sidewalk almost daily. He contacted the City and his alderman numerous times,
asking that the sidewalk be leveled, but “gave up *** because nothing was being done.”
Similarly, his friend stated he had seen people fall across the sidewalk and he fell on a winter
day when snow covered the sidewalk. He also contacted the alderman’s office to no avail.
-7- 1-22-0266
¶ 23 Anthony Koldan, a CDOT employee, inspected the corner after the City received a call in
August 2013. Koldan said the property line curb was necessary to protect the foundation and
get the proper elevation for ADA compliant ramps. He said that, on inspection, “no
construction issue was found” and “this would have been exactly the way that I would have
instructed this to be built.”
¶ 24 Bitsky retained Dr. Elliot Dudnik, who has a Ph.D. in civil engineering, as an expert to
review the circumstances of the fall. Dudnik issued a report that the intersection was unsafe
and dangerous and that certain conditions there contributed to and proximately caused Thomas
Bitsky’s fall. Specifically, he opined that Thomas Bitsky took a misstep and fell into his wife
because of a change in elevation of the sidewalk, creating a hazardous condition with no
warning. He further stated a barrier constructed to protect the exposed portion of a building’s
foundation (i) should not exceed six inches in width (the area where Thomas fell was 24 inches
wide) and should not be more than a quarter inch high to avoid creating a tripping hazard, (ii)
should wrap around the side of the building rather than create a drop-off, and (iii) should have
had a rounded top. In short, Dudnik asserted defendants deviated from the contract
requirements and plans and the CDOT ADA standards.
¶ 25 Procedural History
¶ 26 Bitsky initially sued the City alone, alleging two counts of negligence in constructing the
sidewalk and two counts on her husband’s behalf for loss of consortium. She later amended
her complaint to add CTR and other defendants. On February 25, 2020, Bitsky filed a 24-count
fourth amended complaint alleging, in part, negligence against Sanchez (count XV), Reliable
-8- 1-22-0266
(count XVII), and Precision (count XIX). Counts XVI, XVIII, and XX, were derivative loss of
consortium counts against each.
¶ 27 Each defendant filed a motion for summary judgment. Precision and Reliable argued, in
part, that (i) they had no duty to a third party where the sidewalk met ADA plans,
specifications, and standards, (ii) Bitsky could not prove proximate cause, and (iii) the alleged
condition of the sidewalk was open and obvious. They also argued Thomas Bitsky’s
intervening negligence by allegedly failing to keep a proper lookout. Sanchez similarly claimed
they owed no duty to the Bitsky: (i) they followed the City’s plans and specifications, which
did not create an unreasonably dangerous condition, (ii) their contract with Reliable created no
duty to Bitsky, and (iii) traditional factors limit the scope of any duty. They also argued Bitsky
presented no “affirmative proof” that the condition of the sidewalk caused her injuries.
¶ 28 Bitsky argued, in response, that material questions of fact remained to bar summary
judgment, including (i) whether defendants had a duty to Bitsky to build an ADA compliant
sidewalk, (ii) whether defendants failed to follow the contract plans and specifications and
exercised their discretion in constructing a sidewalk that created a dangerous condition, (iii)
whether the elevated sidewalk was the proximate cause of Bitsky’s injuries, and (iv) whether
the elevation was open and obvious. Bitsky also argued that defendants owed them a duty of
care under traditional negligence factors.
¶ 29 After a hearing, the trial court granted all three motions for summary judgment “for the
reasons stated on the record.” The court said, “even if I were to agree *** that open and obvious
is a jury question, and *** proximate cause is probably a jury question,” under the holding in
Hunt v. Blasius, “an independent contractor *** is not liable to third persons for injuries once
the completed work had been accepted by the state” with certain exceptions, including “if the
-9- 1-22-0266
work done was imminently dangerous to life or health of third persons.” The court noted that
defendants “had some discretion ·here, [but] it’s not discretion in a vacuum. Everything ·has
to be *** compliant, and if it’s not, it’s supposed to be signed off on, approved, changed, or
*** supervised by CTR, the City [and]***the CDOT people who even come up with the
plans.”· The court concluded that because the City and CTR approved the work, defendants
had no duty to third parties. The trial court denied Bitsky’s motion to reconsider.
¶ 30 Analysis
¶ 31 Standard of Review
¶ 32 Summary judgment applies where “the pleadings, depositions, and admissions on file,
together with the affidavits, if any, show that there is no genuine issue regarding any material
fact and that the moving party is entitled to a judgment as a matter of law.” 735 ILCS 5/2-
1005(c) (West 2020). The court construes the pleadings, depositions, admissions, and
affidavits strictly against the movant and liberally in favor of the opponent. Adams v. Northern
Illinois Gas Co., 211 Ill. 2d 32, 43 (2004). “A triable issue precluding summary judgment
exists where the material facts are disputed, or where, the material facts being undisputed,
reasonable persons might draw different inferences from the undisputed facts.” Id. Summary
judgment should be granted where the movant’s right is clear and free from doubt. Id. We
review the grant of summary judgment de novo. Argonaut Midwest Insurance Co. v. Morales,
2014 IL App (1st) 130745, ¶ 14.
¶ 33 Hunt and Defendants’ Duty to Plaintiff
¶ 34 Bitsky argues the trial court erred in relying on Hunt, 74 Ill. 2d 203, and that Jarosz v.
Buona Cos., 2022 IL App (1st) 21018,1 controls and supports reversal. Jarosz was issued after
-10- 1-22-0266
the summary judgment order and thus not addressed by the trial court. Nonetheless, Jarosz is
distinguishable, and the trial court properly relied on Hunt.
¶ 35 In Hunt, the State of Illinois hired Fosco Fabricators (Fosco) to construct and install a
highway exit sign in strict conformity with standards set by the State. Hunt, 74 Ill. 2d at 206.
Fosco followed those specifications, and the State approved and accepted the work. Id. at 206-
07. More than three years later, a car veered off the highway and collided with the post, killing
two occupants and injuring three. Id. at 206. A lawsuit for negligence and strict liability was
filed against multiple parties, including Fosco. Id. Eventually, only Fosco remained. Id.
¶ 36 Fosco moved for summary judgment. Id. It submitted an uncontroverted affidavit
establishing it designed, constructed, and installed the sign and post in strict conformity with
the specifications required by the State of Illinois. Id. at 206-07. The trial court granted Fosco’s
motion, finding that because Fosco was an independent contractor, it was relieved from
liability to any third parties once the State approved and accepted the work it performed. Id. at
207. The appellate court affirmed, and the plaintiffs appealed.
¶ 37 The court observed that the old “general rule of nonliability ha[d] been discarded” (id. at
209), after reviewing the history of independent contractor liability to third parties for work
completed and accepted by the contracting party. Instead, the court would examine the
negligence claim under the traditional rules of liability for negligence actions—by analyzing
whether there was a duty, a breach of that duty, and proximate causation of injury from the
breach. Id. In addressing the duty prong, the court stated, “[a]n independent contractor owes
no duty to third persons to judge the plans, specifications or instructions which he [or she] has
merely contracted to follow.” Id. If the contractor performs the specifications provided to it
-11- 1-22-0266
“carefully,” the contractor “is justified in relying upon the adequacy of the specifications
unless they are so obviously dangerous that no competent contractor would follow them.” Id.
¶ 38 The court found the plaintiffs failed to allege the specifications the State gave Fosco for
the exit sign were so flawed as to put Fosco on notice that the sign would be dangerous and
likely to cause injury. Id. at 210. The court further found the plaintiffs failed to set forth facts
from which the court could infer that the State’s specifications “were so glaringly dangerous
Fosco should have refrained from complying with the specifications.” Id. Because the plaintiffs
failed to make these allegations, no basis existed on “which Fosco can be held liable in
negligence for merely complying with the State’s contract specifications.” Id.
¶ 39 Nearly 45 years later, in Jarosz, the appellate court followed the holding in Hunt (as it
must) but denied summary judgment, absent uncontroverted evidence defendants were
following specifications provided in a contract. Jarosz, 2022 IL App (1st) 210181 ¶ 36.
¶ 40 The plaintiff in Jarosz tripped and fell outside a Buona Beef restaurant. Id. ¶ 5. The plaintiff
briefly lost consciousness and did not know what caused her to fall. A doorstep near where she
fell had been installed by Mobile Lock and Safe, Inc. (Mobile Lock) Id. Mobile Lock moved
for summary judgment, arguing that, as the installer of the doorstop for the property owner, it
did not owe plaintiff a duty of care. Id. ¶ 17. The trial court agreed. Id. ¶¶ 17-18. The plaintiff
argued on appeal that the completed and accepted work doctrine, on which Mobile Lock relied,
was no longer valid, Mobile Lock owed her a duty of care as a matter of law, and genuine
issues of material fact remained as to breach of duty and proximate cause.
¶ 41 In reversing the trial court, the appellate court noted that “in Illinois, the completed and
accepted work doctrine no longer is determinative of the question of liability.” Id. ¶ 30. Citing
Hunt, the court stated that, in assessing contractor liability toward a third party, “traditional
-12- 1-22-0266
principles of negligence govern” (id.)—namely, whether (i) the defendant owed her a duty of
care, (ii) the defendant breached that duty, and (iii) the breach proximately caused her injuries.
Id. ¶ 32. The court further stated, “In Hunt, the defendant provided an uncontroverted affidavit
establishing that the highway exit ‘sign and supporting posts were designed, constructed and
installed by [the defendant] in strict conformity to specifications mandated by the State of
Illinois.’ Id. at 206.” Id. ¶ 35.
¶ 42 The appellate court determined that, unlike in Hunt, “there is no uncontroverted evidence
that Mobile Lock selected and installed the doorstop in strict conformity to specifications
mandated by the Buona entities.” Id. ¶ 36. The court noted that Buona employees testified they
did not give Mobile Lock employees instructions on where to put the doorstop, except to say
which door needed the doorstop. Id. Rather, they relied on Mobile Lock’s employees to install
the doorstop in a proper and safe location. Id. That testimony contradicted the deposition
testimony of another employee, who was “certain” someone from the Buona corporate office
decided the location. Id.
¶ 43 Absent “uncontroverted evidence,” “Mobile Lock cannot rely on the defense discussed in
Hunt for contractors who merely follow plans, specifications, or instructions for which they
were contracted.” Id. Accordingly, the appellate court applied the four duty factors to
determine duty: “(1) the reasonable foreseeability of the injury, (2) the likelihood of the injury,
(3) the magnitude of the burden of guarding against the injury, and (4) the consequences of
placing that burden on the defendant” (id. ¶ 34). After discussing the factors, the appellate
court determined Buona had a duty to the plaintiff and reversed summary judgment. Id. ¶ 47.
¶ 44 Relying on Jarosz, Bitsky contends the trial court erred in granting summary judgment
because (i) the accepted work doctrine no longer applies to contractors and (ii) the court should
-13- 1-22-0266
have applied traditional negligence principles. While true that the accepted work doctrine no
longer shields contractors and subcontractors from all liability, the Jarosz court acknowledged
that under Hunt, “[a]n independent contractor owes no duty to third persons to judge the plans,
specifications or instructions which he has merely contracted to follow.” (Internal quotation
marks omitted.) Id. ¶ 35. Thus, “[i]f the contractor carefully carries out the specifications
provided him, he is justified in relying upon the adequacy of the specifications unless they are
so obviously dangerous that no competent contractor would follow them” when there is
uncontroverted evidence “[a]n independent contractor owes no duty to third persons to judge
the plans, specifications or instructions which he has merely contracted to follow.” (Internal
quotation marks omitted.) Id.
¶ 45 Here, as in Hunt, defendants presented uncontroverted evidence of having followed the
City’s and CTR’s plans, specifications, and instructions. CDOT prepared ADA design
standards, including design standard B-1-6, which defendants used. Standard B-1-6 allows for
a property line curb “where necessary.” As multiple witnesses testified, property line curbs are
used when, as here, a building’s foundation is exposed. Further, standard B-1-6 does not
require specific dimensions. Although Bitsky’s expert issued a report that the elevated
sidewalk did not meet CDOT ADA standards, as the trial court noted, the City and CTR
inspected the area and approved all of the work as compliant with CDOT and ADA standards.
¶ 46 Furthermore, nothing in the record suggests the plans the City and CTR provided to
defendants were “obviously dangerous.” An obviously dangerous condition has been found,
where, for instance, a defendant manufactured and supplied an underground propane gas tank
without a plug for the drain, allowing gas to escape that could lead to an explosion. See Paul
Harris Furniture Co. v. Morse, 10 Ill. 2d 28 (1956). (The trial court discussed these cases
-14- 1-22-0266
involving obvious danger and found them distinguishable.) Although Bitsky asserts that the
elevated sidewalk was “unreasonably dangerous,” she does not argue the plans and
specifications were so obviously dangerous that no competent contractor would follow them.
¶ 47 Bitsky’s contention that the trial court failed to consider all of the evidence presented,
including the report and deposition of her expert, is without merit. The trial court considered
the expert’s report and deposition testimony. Bitsky’s attorney cited both documents in her
argument, and the trial court referred to them several times. Indeed, the trial judge read directly
from the expert report’s conclusion that the elevated sidewalk did not meet CDOT ADA
standards. The court held, however, that although defendants had some discretion in
constructing the sidewalks under the guidelines provided, the City and CTR approved the work
as compliant with contract requirements and CDOT ADA standards.
¶ 48 Given our agreeing with the trial court’s finding that defendants had no duty to Bitsky, we
need not address her arguments regarding proximate cause, whether the elevated sidewalk was
an open and obvious condition or the loss of consortium claims.
¶ 49 Affirmed.
¶ 50 JUSTICE PUCINSKI, specially concurring:
¶ 51 The confluence of necessary and welcome ADA sidewalks, with Chicago’s existing and
sometimes very old sidewalks and buildings creates a menace that I have personally observed
all over the city. I am actually surprised that more people are not injured walking normally and
colliding with elevated or lowered sidewalks or elevated corners like this one. I emphatically
urge the City of Chicago to review its codes and inspection procedures to improve warning
marks for pedestrians encountering these hazards.
-15- 1-22-0266
Bitsky v. City of Chicago, 2023 IL App (1st) 220266
Decision Under Review: Appeal from the Circuit Court of Cook County, Nos. 17-L-1845, 19-L-8025; the Hon. Joan E. Powell, Judge, presiding.
Attorneys Robert G. Black, of Law Offices of Robert G. Black, P.C., of for Naperville, for appellant. Appellant:
Attorneys Adam S. Kreuzer and Jeffrey S. Barger, of Esp Kreuzer Cores, for LLP, of Wheaton, for appellee Sanchez Construction Services, Appellee: Inc.
John J. Moroney and Michelle L. Bisognani, of Franco Moroney Buenik, LLC, of Chicago, for appellee Reliable Construction and Equipment Company.
Stephen Brandenburg, of Cameli & Hoag, P.C., of Chicago, for other appellees.
-16-