Bird & Son, Inc. v. Guarantee Const. Co.

295 F. 451, 1924 U.S. App. LEXIS 3189
CourtCourt of Appeals for the First Circuit
DecidedFebruary 5, 1924
DocketNos. 1634, 1635
StatusPublished
Cited by9 cases

This text of 295 F. 451 (Bird & Son, Inc. v. Guarantee Const. Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bird & Son, Inc. v. Guarantee Const. Co., 295 F. 451, 1924 U.S. App. LEXIS 3189 (1st Cir. 1924).

Opinions

ANDERSON, Circuit Judge.

The first of the above actions was brought by the Guarantee Construction Company against Bird & Son, Inc., to recover $12,432.19, the balance of the contract price of pneumatic apparatus for unloading and conveying ground slate at the factory of Bird & Son, Inc.

The second was brought by. Bird & Son, Inc., against the Guarantee Construction Company, to recover $45,159.80, part payment under the same contract. The cases were tried together to a jury, and a verdict for the Construction Company was returned in each case. They were brought here upon writs of error under a consolidated bill of exceptions. The assignments of error relate to the rulings made by the court and to portions of the charge.

Bird & Son, Inc., is a Massachusetts corporation engaged in the ' manufacture of asphalt-shingle roofing, with a factory at Norwood, Mass. The shingles are made from a certain kind of paper, which is put through a process for saturating it with asphaltum, and then covered on one side with ground slate, which adheres to the asphaltum surface coating of the paper. Ground slate, crushed and screened at the quarries into the required size, is obtained in carload lots. It had been the practice of Bird & Son, Inc., to unload this ground slate by shoveling it from the freight cars into wheelbarrows, from which it was dumped into bins, and then shovelkd from them by hand into trucks as desired, and wheeled to a receptacle, which distributed it upon the surface of the prepared paper as it passed beneath.

As early as April, 1919, Bird & 'Son, Inc., received from the Construction Company an advertising circular, in which it was stated, inter alia:

“The Guarantee Construction Company is an organization of broadly experienced contracting engineers, specializing in the following lines:
“Complete design, construction, and equipment of * * * labor-saving equipment for handling coal, ashes, and other materials in bulk.
“Work of this nature involves a considerable degree of expert knowledge. * * * Our function is to show the economies possible and install the particular sort of equipment which will best accomplish the greatest saving.”

On July 24, 1919, Bird & Son, Inc., sent the Construction Company samples of the “ground slate and soapstone such as we use in the manufacture of our roofing paper,” adding:

“We would be pleased to have you look over these samples and advise us whether they could be handled by your pneumatic system of conveying.”

On August 8, 1919, the Construction Company wrote, referring to a conversation on the day before:

“The pneumatic system will handle these materials very nicely.”

[453]*453And again, on August 19, 1919:

“The surfacing material, samples of which you sent us, is a rather specialized material, and we regret that we cannot refer you to any installations identical with this. However, this material presents a far simpler problem than most of the materials for which we frequently install conveying apparatus. Any proposition that we make to you will he covered by a positive and explicit guaranty of successful operation; also by bond, if you wish.”

There was also evidence that a representative of the Construction Company visited the plant of Bird & Son, Inc., and was shown the process pf applying the slate to the processed paper, including the arrangement for sucking superfluous dust from the ground slate just before it reached the paper, and that the importance of removing dust from the slate was then explained to the Construction Company’s representative.

Several months were taken up in correspondence, in negotiations, in preparing designs, and in making experiments. Bird & Son, Inc., employed the office of Charles T. Main, consulting engineers, to prepare plans and specifications for a system of unloading and storing far more elaborate than were contemplated in the early days of the negotiations.

On December 4, 1919, Bird & Son, Inc., sent a written order “to furnish and install ground slate conveyor and storage bin system as per C. T. Main’s specifications.” This order covered material and construction to cost $49,080. After further negotiations and correspondence, a supplementary order was sent by Bird & Son, Inc., on January 23, 1920, for “extra material as covered by C. T. Main’s letter to us of January 5, 1920, price $8,051.00.”

The specifications as finally agreed upon embodied the pneumatic method, of conveyance throughout. They provided for two stages of conveyance: First, by suction from freight cars to storage bins; and, second, by pressure from storage bins to service bins located over the paper machine. Pressure or suction was to be created by blowers, which were located near the storage bins and near the railroad tracks. There were to be exhausts by the blowers, and also at the service bin, at which dust had an opportunity to escape to the open air.

The record discloses that after the equipment was installed, in the spring of 1921, several attempts were made by the Construction Company to revise the system so as to get rid of the dust that was formed; but the changes made did not cause the system to handle the ground slate at the rate specified, in the contract without the creation of considerable dust and consequent change in the particles of slate. It was found impossible to suck this ground slate into the separator above the storage bins, and then to blow it from the storage tanks to the service bin, at the high rate of speed required by the specifications, without causing a great deal of dust and what was termed a “degradation” of the materials.

It appears from the record that about 10 per cent, of the material was ground into dust and lost in the process of handling, and that the particles of ground slate were reduced in size or so worn and covered with dust that, when they fell upon the specially prepared paper, they would not satisfactorily adhere to it.

[454]*454After repeated tests and prolonged negotiation, Bird & Son, Inc., rejected the apparatus as a failure.

Shortly stated, the pneumatic system thus installed, instead of reducing the amount of dust produced under the old method of handling, enormously increased it, and it also so ground or rounded the rest of the slate as to make it unfit for use in the business of Bird & Son, Inc. This result, practically an entire failure of the new system, was, as the 'court in effect told the jury, a surprise to both parties; for it is obvious that the system would not have been installed, if either the manufacturer or the buyer had supposed that it would be what it proved to he, a complete failure.

The gist of the case, then, is whether the jury should have been instructed, substantially as Bird & Son, Inc., requested, that there was, or might be found to be, an implied warranty by the Construction Company that its conveyor system would convey this slate material, substantially unchanged, or at any rate not so changed as to be unfit for the buyer’s use.

Bird & Son, Inc., requested the following ruling:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Whiting Corporation v. Process Engineering, Inc.
273 F.2d 742 (First Circuit, 1960)
Burke v. Thomas
15 Alaska 385 (D. Alaska, 1955)
Gibson v. De La Salle Institute
152 P.2d 774 (California Court of Appeal, 1944)
Valley Refrigeration Co. v. Lange Co.
8 N.W.2d 294 (Wisconsin Supreme Court, 1943)
MacAndrews & Forbes Co. v. Mechanical Manufacturing Co.
1 N.E.2d 895 (Appellate Court of Illinois, 1936)
Davenport Ladder Co. v. Edward Hines Lumber Co.
43 F.2d 63 (Eighth Circuit, 1930)
Barrett Co. v. Panther Rubber Mfg. Co.
24 F.2d 329 (First Circuit, 1928)
Maritime Trading Co. v. J. M. Preston Co.
20 F.2d 215 (E.D. Michigan, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
295 F. 451, 1924 U.S. App. LEXIS 3189, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bird-son-inc-v-guarantee-const-co-ca1-1924.