Birchwood Land Dev. Corp. v. Ormond Bushey & Sons, Inc.

Vermont Superior Court·Decided October 7, 2011·No. S0946·Published

Opinion

Birchwood Land Dev. Corp. v. Ormond Bushey & Sons, Inc., No. S0946-08 CnC (Tomasi, J., Oct. 7, 2011)

[The text of this Vermont trial court opinion is unofficial. It has been reformatted from the original. The accuracy of the text and the accompanying data included in the Vermont trial court opinion database is not guaranteed.]

VERMONT SUPERIOR COURT

SUPERIOR COURT CIVIL DIVISION Chittenden Unit No. S0946-08 CnC

Birchwood Land Development Corp., │ Plaintiff, │ │

v. │ │

Ormond Bushey & Sons, Inc., │ Defendant. │ │

Findings Of Fact, Conclusions Of Law, And Order This matter came for trial before the Court on February 7; February 9; April 4;

and April 5, 2011. Both parties were represented by counsel and provided testimonial and documentary evidence to the Court. The Court also conducted a view of the development site at issue. Based on the foregoing, the Court makes the following findings of fact and conclusions of law.

FINDINGS OF FACT AND OVERVIEW OF CLAIMS I. The Principal Dispute Between the Parties This matter arises out of a construction project undertaken in Essex, Vermont.

Birchwood Land Development Company (“Birchwood”) entered into two contracts for the required work with Ormond Bushey & Sons, Inc. (“Bushey”). The first contract was designated the Rosewood Contract or the Rosewood Contract. The

second was designated the Tanglewood Contract or the Tanglewood Project.1 Both projects were designed to create roadways and building lots that might be sold by Birchwood. As the area was essentially wild and overgrown, the projects involved significant grading of the area, removal of trees and stumps, installation of sewers and utilities, and the paving the newly created roadways, among other things.

The main dispute between the parties centers around excavated sand that Bushey removed from both projects. Bushey used or sold the sand and, through its principal Dean Henry, claims it had a right to do so under the Contracts. Birchwood, through its owner Owen Jenkins, insists that the sand was its property and that Bushey removed it and expropriated it for its own gain in violation of the Contracts. Birchwood refused to make final payments to Bushey under the Contracts based on the sand issue. Both parties have sued for breach of contract based on the above-described conduct. As discussed below, there are other minor issues that divide the parties as well. II. Matters Resolved by Agreement or Prior Court Ruling During trial, the parties resolved a number of disputes between them by agreement and submitted a Stipulation to the Court on those points. For example, as noted, Birchwood refused to pay certain sums allegedly owing to Bushey under the Tanglewood Contract. It did so based on its belief that Bushey actually owed Birchwood money with regard to its claims for sand taken from the site. The parties

1In addition, there was a related third contract specifically concerning the construction of a sewer line.

stipulated that the amount owing to Bushey for work performed under the Tanglewood Contract is $23,511.28. This sum is to be offset, in whole or in part, based on the determination of this Court concerning whether Birchwood is owed damages on its sand claim.

In addition, at trial, the Court entered judgment as a matter of law in Bushey’s favor concerning Birchwood’s claim regarding a sink hole at the site. III. The History of Excess Sand The trial in this matter focused on whether Bushey was required under the Contracts to keep excess sand generated by the projects at the site. While the Court will assess the contractual provisions later, it makes the following factual determinations with regard to the parties’ understandings and actions concerning excess sand.

On June 15, 2006, the parties met with the Zoning Administrator for the Town of Essex. He reminded them that, unless they obtained a special permit, any excess materials, including sand, would need to remain on site. The Town was concerned about the generation of dirt and traffic from any removal operation. Ex. 74 (9/6/06).

Soon thereafter, on June 18, Jenkins walked the site with Chase. They discussed possible locations where excess sand could be deposited. They identified some locations where the fill might be used in the future to help create an access to adjacent property.

In September 2006, Scott Myrick took over as Bushey’s superintendent for the project. Jenkins met with Myrick on September 6 and confirmed that excess

material was to be placed in designated fill sites. Ex. 74 (9/6/06). A second conversation with Myrick later that month reiterated that excess material was to be placed in the fill sites. Ex. 74 (9/28/06).

In October 2006, Jenkins received a call from a person who lived near the project inquiring whether she might purchase excess sand. Jenkins indicated to her that she could have some of the sand, but she need the approval of the Town and Bushey.

In or about the same period, the Town received a complaint that sand was being exported off site and that no silt fence had been erected. The Town investigated, spoke with Myrick and told him to cease taking sand off site.

As the Tanglewood Project was about to begin major activity, the parties held a pre-construction meeting with the Town. The Town had received a complaint from neighbors about truck traffic and dust generated in connection with moving sand. The Town, again, informed the parties that the subdivision regulations did not permit removal of sand from the site. Jenkins questioned whether it could be removed for his own personal use, and the Town agreed. The Town indicated that sand could be removed solely for non-commercial/personal uses. It also noted, however, that if the Town received complaints about that process, Jenkins would need to apply for a special permit. Ex. 74 (5/11/07); see Ex. 29 (noting Town’s view that trucking sand off site is inconsistent with regulations).

In 2007, Randy Maxfield replaced Myrick as superintendent at the project. On or about May 14, 2007, he identified a pile of sand that was impeding some of the

construction efforts. He asked Jenkins what Jenkins wished him to do with the sand. Jenkins told Maxfield to either deposit it in the fill sites at the Tanglewood project or take it to his Route 2A property. Ex. 74 (5/14/07).

On May 14 or 15, 2007, Jenkins had similar telephone conversations with Henry. Jenkins told Henry to put sand in fill sites at the project. Jenkins said that any additional excess fill should be taken to Jenkins’ Route 2A property, and he agreed to pay Bushey their normal rate -- $65.00 per hour -- to take the materials to that location. Henry confirms this direction, although he adds that, in a prior call Jenkins indicated he did not care what happened to the sand. Even accepting Henry’s testimony, it is undisputed that Jenkins almost immediately called Henry back and said to take any excess fill to Route 2A. That conversation and direction is further confirmed by Jenkins’ May 15, 2007 letter to Henry in which he states: “Lastly, this shall confirm that I have requested that you haul any and all excess sand fill and topsoil to my property at 106 Colchester Road (Route 2A) in Essex and that I have agreed to pay for such trucking at your normal hourly rate.” Ex. 13. Indeed, Jenkins indicates that the May 15 letter shall be deemed a Change Order, and thus part of the Tanglewood Contract.

The last load of sand that Jenkins received from the project at either of his off-

site locations was on June 15, 2007. He assumed there was no additional excess sand and heard nothing different from Bushey.

On July 13, 2007, Jenkins visited the project and saw a truck leaving with a load of sand. He followed the vehicle to the Albert D. Lawton School. Bushey was

working on another project at the school at the time. The truck deposited the load of sand from the Birchwood project at the Lawton project site.

Free access — add to your briefcase to read the full text and ask questions with AI

Birchwood Land Dev. Corp. v. Ormond Bushey & Sons, Inc., (Vt. Ct. App. 2011).

Birchwood Land Dev. Corp. v. Ormond Bushey & Sons, Inc. (Birchwood Land Dev. Corp. v. Ormond Bushey & Sons, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Sullivan v. James R.
2011 VT 37 (Supreme Court of Vermont, 2011)
Fly Fish Vermont, Inc. v. Chapin Hill Estates, Inc.
2010 VT 33 (Supreme Court of Vermont, 2010)
Ferrisburgh Realty Investors v. Schumacher
2010 VT 6 (Supreme Court of Vermont, 2010)
R&G Properties, Inc. v. Column Financial, Inc.
2008 VT 113 (Supreme Court of Vermont, 2008)
EBWS, LLC v. Britly Corp.
2007 VT 37 (Supreme Court of Vermont, 2007)
West Investment Co. v. Moorhead
262 P.2d 322 (California Court of Appeal, 1953)
Stewart v. Basey
245 S.W.2d 484 (Texas Supreme Court, 1952)
VanVelsor v. Dzewaltowski
385 A.2d 1102 (Supreme Court of Vermont, 1978)
Wharton v. Tri-State Drilling & Boring
2003 VT 19 (Supreme Court of Vermont, 2003)
Berlin Development Corp. v. Vermont Structural Steel Corp.
250 A.2d 189 (Supreme Court of Vermont, 1968)
P.F. Jurgs & Co. v. O'Brien
629 A.2d 325 (Supreme Court of Vermont, 1993)
Villeneuve v. Beane
2007 VT 75 (Supreme Court of Vermont, 2007)
Tour Costa Rica v. Country Walkers, Inc.
758 A.2d 795 (Supreme Court of Vermont, 2000)
Ainsworth v. Franklin County Cheese Corp.
592 A.2d 871 (Supreme Court of Vermont, 1991)
TROMBLY PLUMBING & HEATING v. Quinn
2011 VT 70 (Supreme Court of Vermont, 2011)
Downtown Barre Development v. C & S Wholesale Grocers, Inc.
2004 VT 47 (Supreme Court of Vermont, 2004)
Downtown Barre Development v. GU Markets of Barre, LLC
2011 VT 45 (Supreme Court of Vermont, 2011)
Wakeman v. Wheeler & Wilson Manufacturing Co.
4 N.E. 264 (New York Court of Appeals, 1886)
Johnson v. Rule
164 A. 681 (Supreme Court of Vermont, 1933)