Binkhorst Lake Access

Vermont Superior Court·Decided October 20, 2009·No. 286-12-07 Vtec·Published

Opinion

STATE OF VERMONT

ENVIRONMENTAL COURT

} In re: Binkhorst Lake Access } Docket No. 286-12-07 Vtec (Appeal of Wool) } }

Decision and Order on Renewed Motions for Summary Judgment

Appellants Michael and Martha Wool appealed from a decision of the Zoning

Board of Adjustment (ZBA) of the Town of Charlotte, upholding the Zoning

Administrator’s determination that certain work performed on Appellees Mark and

Julie Binkhorst’s property was “exempt from permitting.” Appellants are represented

by Hobart F. Popick, Esq.; Appellee is represented by Stuart M. Bennett, Esq.; and the

Town is represented by William E. Flender, Esq.

In March of 2009, the Court issued a decision and order on the parties’ motions

for summary judgment, which resolved Question 1 and several issues raised by

Questions 2, 3, and 4 of the Statement of Questions. That decision concluded that a

number of facts were either in dispute or had not been provided to the Court, so that

the remainder of Questions 2, 3, and 4 could not be resolved at that time. In re:

Binkhorst Lake Access, No. 186-12-07 Vtec, slip op. at 5–8. (Vt. Envtl. Ct. Mar. 9, 2009)

(Wright, J.). The parties requested an opportunity to submit additional facts and

arguments to the Court by motion, and submitted a Joint Supplemental Statement of

Undisputed Material Facts to the Court. Appellees submitted a Supplemental

Statement of Disputed Material Facts, and Appellants submitted a supplemental

memorandum in support of their motion.

The following facts are undisputed unless otherwise noted, in addition to the

facts as described in the March 2009 decision.

1 The narrow parcel of land at issue in this appeal, also known as the “Windmill”

lot (“the property”), is located in the Shoreland zoning district between Hills Point Road

and Lake Champlain. It is approximately 350 feet in length, running west from Hills

Point Road to Lake Champlain. The property gradually widens from only

approximately 50 feet in width at Hills Point Road to approximately 100 feet in width at

Lake Champlain.

Beginning in 2007, Appellees engaged in the following four categories of

contested activities on the property: landscaping, electrical service to the pump house,

improvement to the traveled way on the property, and installation of a culvert.

Appellees performed landscaping on the property, including pruning and

removing trees, shrubs, and underbrush; placing and grading topsoil; and planting

grass, plants, and trees. All of this landscaping activity occurred more than 100 feet

from the Lake Champlain shoreline.

A pump house for a water supply system serving persons not party to this

appeal is located on the property within 100 feet of the shoreline. Prior to the work at

issue in this appeal, the electrical service to the pump house was connected by a

electrical wire to an existing electric service pedestal on Hills Point Road. By 2006, that

electrical wire had partially surfaced and had become a hazard. In 2006, Appellees

contracted to have a trench dug from the pump house along the north side of the

property, in order to bury the wire in conduit. However, the wire was not in fact buried

at that time, leaving the trench open through the winter of 2006–07. During this period,

the trench eroded to create a shallow ditch running along the north side of the property,

causing some flooding in the pump house and in the basement of the house on the

adjoining property to the south. As part of the work at issue in this appeal, in 2007

Appellees had a trench excavated in which a PVC electrical conduit containing a new

electrical wire was buried, running from the electric service pedestal on Hills Point

Road to the pump house. 2 Prior to the work at issue in this appeal, the property was vegetated with trees,

bushes, and underbrush, and contained an unimproved traveled way with a grass

surface, extending from Hills Point Road to the lake. Appellees had removed debris

from the lot prior to 2006, including the remains of a windmill and rails from a boat

launching system. The traveled way was used occasionally by pedestrians or vehicles

for access to the pump house and to the lake shore. Those served by the water supply

system have an easement over the property to access the pump house. The traveled

way was in need of regrading and reseeding to maintain it in useable condition. In the

work at issue in this appeal, Appellees improved the surface of the traveled way by

installing a so-called “soft” road surface, which consisted of covering the traveled way

with gravel and then topping it with a layer of topsoil and grass. This work began at a

point near Hills Point Road and extended for approximately 150 feet toward the lake.

Since the distance between Hills Point Road and the shoreline is 350 feet, and the work

on the traveled way only extended for 150 feet toward the lake, this activity did not

extend within 100 feet of the shoreline of Lake Champlain.

Also prior to the work at issue in this appeal, an existing town culvert running

under Hills Point Road emptied onto the property at the west side of the road. In order

to address issues of flooding caused by the water draining onto the property through

the existing town culvert, Appellees installed a new culvert running the length of the

property, from the existing town culvert to a point located 50 to 75 feet from the lake

shore. Installation of the culvert consisted of excavating a ditch, installing in the ditch a

15-inch culvert pipe the length of the ditch, and placing fill to cover the culvert and the

ditch. The area around the lake end of the culvert was graded and a course of rip rap

was laid from the end of the culvert to approximately 30 feet from the shoreline.

None of the work at issue in this appeal involved the cutting or removal of trees

or shrubs within 100 feet of the shoreline of Lake Champlain.

3 Town of Charlotte Land Use Regulations

Under § 1.3(C) of the Town of Charlotte Land Use Regulations (Regulations), all

“land development” must be specifically authorized by the Regulations, exempted from

the Regulations under state statute or § 9.2,1 or approved in accordance with § 2.3

(Application of District Standards). The March 2009 decision resolved that the work at

issue constitutes “land development.” See In re: Binkhorst Lake Access, slip op. at 5.

The work must therefore qualify as exempt under § 9.2 or Appellees must apply for a

zoning permit for it under § 9.3.

Uses and structures that are exempt from the Regulations under § 9.2(A) do not

require a zoning permit or approval. Section 9.2(B) provides the mechanism for

appealing a Zoning Administrator’s exemption decision to the ZBA, as was done in the

present case. The § 9.2(A) exemptions relevant to the work at issue in this appeal

include: § 9.2(A)(1), exempting “normal maintenance and repair of existing structures,

utilities and infrastructure which does not result in any change to the footprint or height

of the building . . . or change in use”; § 9.2(A)(4), exempting “[m]inor grading and

excavation associated with normal road, driveway, and parking area maintenance”; and

§ 9.2(A)(5), exempting “[l]andscaping, for example: installation of plants, soils, arbors,

terraces, and patios.”

In addition, because the property is located partially within 100 feet of the

Free access — add to your briefcase to read the full text and ask questions with AI

Binkhorst Lake Access, (Vt. Ct. App. 2009).

Binkhorst Lake Access (Binkhorst Lake Access) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.