Bignall & Keeler Manufacturing Co. v. Pierce, Butler & Pierce Manufacturing Co.

59 Mo. App. 673, 1894 Mo. App. LEXIS 497
CourtMissouri Court of Appeals
DecidedDecember 4, 1894
StatusPublished
Cited by4 cases

This text of 59 Mo. App. 673 (Bignall & Keeler Manufacturing Co. v. Pierce, Butler & Pierce Manufacturing Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bignall & Keeler Manufacturing Co. v. Pierce, Butler & Pierce Manufacturing Co., 59 Mo. App. 673, 1894 Mo. App. LEXIS 497 (Mo. Ct. App. 1894).

Opinion

Bond, J.

The cause of action in controversy in this case is the second count in plaintiff’s petition, which alleges, in substance, a written contract between the parties, made on June 1, 1889, whereby the defendant employed the plaintiff to construct “a nipple machine, guaranteed to cut two thousand nipples per day,” upon an agreement by defendant to forward its ninety days’ acceptance for the price of said nipple machine after its completion and receipt. Said second count further alleges that the machine in question was to be one of new and novel construction, requiring [674]*674much skill, experimenting and testing, in order to perfect it in all of its parts and make it perform the guarantee aforesaid; that plaintiff agreed to use reasonable care and diligence in making it; that it was designed for the special use of the defendant, who was advised from time to time of the progress made, and consented by correspondence to the delays caused by the experiments and tests employed for.the perfecting of the machine; that it was fully completed on the -day of July, 1891, and found after final experiments and tests, to meet the guarantees made upon its sale; that on or about the twentieth day of July, 1891, defendant peremptorily refused to accept said machine, or carry out its contract in respect thereto; wherefore, judgment was prayed for $900, as the contract price of said machine. The answer was a general denial.

The contract between the parties was evidenced by the following letters:

Defendant to plaintiff, May 10, 1889.

“We have been thinking over the matter seriously of purchasing two machines, one for twelve-inch pipe and the other for nipples. We have decided to offer you $2,000 for those two machines complete, if guaranteed to give perfect satisfaction. The nipple machine, you agree to cut from one-fourth inch to two inches, inclusive. You also guarantee same to turn out 2,000 nipples per day. If you can ship us this 12-inch pipe machine inside of thirty days, and the nipple machine within two months, you may enter the order for same, with the understanding that you are -to accept in payment for these two machines our note at four months, we to send you settlement on ■'receipt of machines, if same proves satisfactory, and you also to guarantee to keep them in perfect repair, excepting the natural wear and tear, for a period of six months.”

[675]*675Plaintiff to defendant, May, 23, 1889.

“We could only say *'no’ by telegraph. Our Mr. Bignall made you a proposition when there, and he is nbw of the opinion that he had not thought sufficiently over the matter. It would be utterly impossible to get out the nipple machine in the time mentioned in your letter. His proposition was to ship the 12-ineh machine within thirty days, and four or five months for the other. We are willing to place the order for the 12-inch machine for $1,300; the nipple machine to be a question for future consideration. We have two plans for building it, and are not certain ás yet which will be preferable.”

Defendant to plaintiff, May 27, 1889.

“We are in receipt of your letter of May 23, and after careful consideration, we have concluded to make you two propositions. You state you can ship the 12-inch machine in thirty days. This will be satisfactory, we not being so particular about the time specified for the nipple machine.

“Now, we will either offer you $2^200, the original proposition for the 12-inch machine and - a nipple machine to cut from one-fourth inches upwards; or, we will offer you $2,000 for the 12-inch machine and the nipple machine to cut from one-half inches upwards, with a guarantee, etc., as per our original letter.

“Please state which proposition you prefer to accept.”

Plaintiff to defendant, May 29, 1889.

“We will take the first and original proposition, viz, $2,200 for both machines, as follows:

“The twelve-inch machine to be shipped as soon as possible, or thirty days from date.

“The nipple machine to cut from one-fourth inch to two inches, to be got out .and shipped as soon • as-[676]*676possible. We want to try it most thoroughly before ■ -shipping. - We think we can get the No. 12 out in time, and will make our best endeavors to do so, but may be a week behind.

“Terms: Ninety days’ acceptance upon receipt of No. 12 to cover price of same, and ninety days’ acceptance upon receipt of nipple machine to cover-balance.”

The reference in said letters to machine number 12 may be disregarded, the transaction in that regard being settled.

. Following the making of the above contract the parties engaged in a protracted correspondence, which tended to show the great urgency on part of the defendant for the completion of the machine, and many excuses by plaintiff for the' delay in its construction, based chiefly on the difficulties of making a machine “of entirely new design.” After this correspondence had lasted over two years, defendant on July 16, 1891, canceled its order for the machine, on. the alleged ground of unreasonable delay in its completion. Plaintiff refused to accept such cancellation,, and wrote on July 21, 1891, that the machinewras-oom^lete and ready for a test of its capacity. Defendant replied that it had countermanded the order for the machine, and could not accept the same. Upon the receipt of another letter from plaintiff defendant replied, making a new proposal to take the machine upon new terms and further-guarantees. This was rejected by plaintiff, and thereupon on September 9, 1891, defendant reiterated its refusal to accept the machine, and the correspondence between the -parties closed, and the present suit was-brought.- , -

On the trial parol evidence was adduced tending tosh ow that plaintiff caused work to be done on the machine for about two years; that,' upon a .test of the-[677]*677machine in 1891, it appeared to work properly; that, when it was again tested in the summer of 1893, after a continuance of the present case for that purpose, it cut at the rate of two thousand, four hundred nipples per day.

There was also evidence tending to show that a machine of the general character of the one in suit, if plans had been framed, and no difficult experimenting was required, could be built in six months; and on the other hand, if such a machine “existed only in conception,” and without any plans prepared therefor, two years would not be an unreasonable time for its construction.

Defendant offered'in evidence the deposition of two of its officers, the vice president and secretary, to show the circumstances and statements, under which the order for the machine was given, and the conversation then had between deponents and one Bignall, the contracting agent of the plaintiff. Upon objection to these depositions, on the ground that said Bignall was dead when they were taken, the court, over defendant’s objection, excluded such portions as purported to give the conversation of said Bignall. Thereupon the Court sitting as a jury, after giving and refusing certain instructions, found for plaintiff in the sum of $1,035.25. Erom a judgment on this finding the present appeal was taken.

The first point urged for reversal is the ruling of the trial court in excluding the two depositions offered by defendant, “in so far as they undertake to detail conversations had with Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Minneapolis-Moline Power Implement Co. v. Wright
122 S.W.2d 397 (Missouri Court of Appeals, 1938)
Iola Portland Cement Co. v. Ullmann
140 S.W. 620 (Missouri Court of Appeals, 1911)
O'Neill v. Supreme Council
57 A. 463 (Supreme Court of New Jersey, 1904)
Claes & Lehenbeuter Manufacturing Co. v. McCord
65 Mo. App. 507 (Missouri Court of Appeals, 1896)

Cite This Page — Counsel Stack

Bluebook (online)
59 Mo. App. 673, 1894 Mo. App. LEXIS 497, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bignall-keeler-manufacturing-co-v-pierce-butler-pierce-manufacturing-moctapp-1894.