Bigley Trucking Corp. v. United States

149 F. Supp. 141, 137 Ct. Cl. 903, 1957 U.S. Ct. Cl. LEXIS 183
CourtUnited States Court of Claims
DecidedMarch 6, 1957
DocketNo. 38-55
StatusPublished
Cited by2 cases

This text of 149 F. Supp. 141 (Bigley Trucking Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bigley Trucking Corp. v. United States, 149 F. Supp. 141, 137 Ct. Cl. 903, 1957 U.S. Ct. Cl. LEXIS 183 (cc 1957).

Opinion

Opinion

per curiam:

This case was referred by the court, pursuant to Buie 45 (c), to C. Murray Bernhardt, a commissioner of the court, with directions to make findings of fact and recommendations for conclusions of law. The commissioner has done so in a report filed December 19, 1956. When more than 15 days elapsed after the filing of this report and neither party gave notice in writing of an intention to except to the commissioner’s findings or recommendations, the defendant filed a motion for judgment in accordance with the recommendations of the commissioner. Since the court agrees with the recommendations and findings of the commissioner, as hereinafter set forth, it hereby adopts the same as the basis of its judgment in this case, and judgment will be entered for plaintiff in the amount of $38.40.

It is so ordered.

OPINION OP THE COMMISSIONER

The plaintiff, Bigley Trucking Corporation, whose name itself adds confusion to the activities it shares with its closely affiliated and commonly owned sister organization, Bigley Brothers, Inc., sues to recover an unpaid balance on a contract with the Army to haul 300 creosoted wooden antenna pole sections from a railroad siding at La Plata, Maryland, to an open field within the reservation of the Army Bemote Beceiving Station, three miles distant from La Plata. The sum in suit represents amounts withheld by the Government for the value, less salvage, of three poles which were damaged in the course of plaintiff’s transit operation.

[905]*905In addition to defending on the ground of plaintiff’s negligence, the Government contends that plaintiff is not entitled to sue because Bigley Brothers, Inc., actually performed the contract, and that plaintiff’s liability as an insurer is fixed by the terms of the contract and by the contractor’s status as a common carrier, which status plaintiff denies.

The 800 pole sections in question had been manufactured and tapered in matched pairs so that each pair would constitute, when spliced together, a single, continuously tapered antenna pole 150 feet in length, the top section being about 60 feet in length, and the bottom section being about 90 feet and weighing approximately four tons. The sections were individually mated by being machined to fit at the spliced ends, and the sections of one pair were not interchangeable with sections of other pairs. They had been purchased by the defendant in Oregon and were consigned to the Army Remote Receiving Station, La Plata, Maryland, arriving at La Plata by rail at various times in January and February 1952.

On January 30,1952, defendant’s agent telephoned plaintiff and two other concerns he had selected from the classified section of the Washington, D. C., telephone directory and requested price quotations for removal of the poles from freight cars at La Plata and their hauling to and unloading at a selected site at the Remote Receiving Station. After Mr. Gilmartin, the Washington manager of the joint offices of plaintiff and Bigley Brothers, Inc., inspected the location to which the poles were to be hauled, he telephoned on the same day to defendant’s agent a price quotation which the latter accepted as the low bid. The defendant’s agent orally instructed plaintiff to proceed immediately in order to curtail demurrage, and stated that a purchase order numbered 166 would meanwhile be mailed to plaintiff. Plaintiff apparently had had little or no previous experience with Government contracts and, since Mr. Gilmartin had been given no further advice from defendant’s agent as to the details of the contract other than the bare essentials related above, when the formal, signed purchase order arrived at plaintiff’s office on February 4 incorporating by reference and attaching the standard General Provisions, these con[906]*906ditions constituted additions to the oral agreement, particularly paragraph 6 of the General Provisions reading as follows:

Except as otherwise provided in this contract, (i) the Contractor shall be responsible for the supplies covered by this contract until they are delivered at the designated delivery point, regardless of the point of inspection; and (ii) the Contractor shall bear all risks as to rejected supplies after notice of rejection.

Upon receipt of the purchase order Mr. Gilmartin filed if away without question or demur.

Meanwhile, plaintiff proceeded with performance on January 31 as directed, using employees who were on the payroll of Bigley Brothers, Inc., a pole trailer and a low-bed trailer, each drawn by a tractor and owned by Bigley Brothers, Inc., and a truck-mounted crane and other loading equipment owned by Bigley Trucking Corporation. On February 2 a bottom pole section was damaged when, after being unloaded with other pole sections onto the trailer being operated by the contractor at the La Plata railroad siding, its spliced end was splintered when it was accidentally swung into the side of a freight car while being maneuvered through close quarters.

On February 5 the spliced end of another bottom pole section was splintered when it fell from the tractor end of the tractor trailer at the Army Remote Receiving Station. On this occasion the field on which the pole sections were to be unloaded was wet and muddy from rainfall the preceding day. The selected storage site was about 100 yards off of the reservation road, and so the contractor’s loaded vehicles had to traverse the intervening stretch of open field to unload. After several loads had been successfully deposited, in crossing the field with another load the left rear wheel of the trailer fell into a muddy hole up to its axle. Plaintiff’s employees then endeavored to extricate the mired vehicle with its load of pole sections by pulling it out with a truck attached to the front of the tractor. However, as the horizontal tension of the tow was applied a %" steel safety cable, which besides the poles themselves was the sole connecting link between the tractor and the trailer, parted, and the ends of the [907]*907pole sections resting on the rear end of the tractor fell four or five feet to the earth, splintering the spliced end of a pole section. Although plaintiff contended that the selection of the dumping site and mode of extrication of the vehicle were dictated by defendant’s agents so as to make defendant responsible, the evidence indicates plaintiff’s concurrence in the former and defendant’s mere acquiescence in the latter.

Either because plaintiff’s employees objected to continued use of the site where the damage occurred, or because defendant desired to deposit the remaining poles elsewhere, another site was mutually agreed upon by the parties and activities resumed. Later on the same day, February 5, at the new site, the incident repeated itself and another bottom pole section was broken in half when it fell from the rear of the tractor as the result of the safety cable parting when a tow truck endeavored to extricate the trailer which had managed to get itself mired again.

The damage to the three pole sections not only made them unusable for their intended purpose, but also rendered useless the companion pole sections which the damaged sections ivere specially machined to fit. The contracting officer found plaintiff to be negligent and, in paying plaintiff for its services, withheld from the $8,600 contract price the sum of $1,732.40, representing the $2,111.40 cost price of the six sections rendered unusable, less their salvage value of $379.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

George Bohannon Transportation, Inc. v. Davis
323 F.2d 755 (Tenth Circuit, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
149 F. Supp. 141, 137 Ct. Cl. 903, 1957 U.S. Ct. Cl. LEXIS 183, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bigley-trucking-corp-v-united-states-cc-1957.