Big Lost River Irrigation Co. v. Davidson

121 P. 88, 21 Idaho 160, 1912 Ida. LEXIS 111
CourtIdaho Supreme Court
DecidedJanuary 16, 1912
StatusPublished
Cited by13 cases

This text of 121 P. 88 (Big Lost River Irrigation Co. v. Davidson) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Big Lost River Irrigation Co. v. Davidson, 121 P. 88, 21 Idaho 160, 1912 Ida. LEXIS 111 (Idaho 1912).

Opinion

STEWART, C. J.

This action was brought by appellant to condemn 861.45 acres of land as a right of way for a dam and reservoir site. The complaint is in the ordinary form and states all the facts required by Rev. Codes, see. 5216. Respondents admit in their answer that the land described in the plaintiff’s complaint is necessary for the proper and convenient construction of the dam and reservoir mentioned in the complaint and the permanent flooding occasioned thereby, and also admit and allege as an affirmative defense that respondents are the owners and in possession of the northwest quarter of the southeast quarter and the northeast quarter of the southwest quarter of section 5, township 7 north of range 25, east of Boise meridian, containing eighty acres in area, and that said eighty acres will also be required and taken by the flooding of the same in the construction of the dam proposed on the land sought to be condemned.

To the affirmative matter thus alleged in the answer there seems to have been no reply by the appellant. It will thus be seen that the only issue presented in the pleadings was the value of the land to be taken. The right to take the land described in the complaint and the necessity for such taking is admitted by the answer, and the description of the land as alleged in the complaint is also admitted by the answer, and the allegation in the answer as to the necessity for taking eighty additional acres is not denied or put in [166]*166issue, and therefore must have been admitted by the appellant, leaving for determination the value of the land described in the pleadings as the only issue to be determined in said cause. A jury was called and a verdict rendered by the jury in the following form:

“We, the jury duly sworn and impaneled in the above-entitled action, find for the defendants and assess defendants’ damages in. the sum of $55,593.” Upon this verdict the trial court entered the following judgment:
“This cause came on regularly for trial. The said parties appeared by their attorneys. A jury of twelve persons was regularly impaneled and sworn to try said cause. Witnesses on the part of plaintiff and defendant were sworn and examined. After hearing evidence, the argument of counsel and instructions of the court, the jury retired to consider their verdict, and subsequently returned into court and being called, answer to their names and say they find a verdict for the defendant.
“Wherefore, by virtue of the law, and by reason of the premises aforesaid, it is ordered, adjudged and decreed that the said defendants have and recover from said plaintiff the sum of Fifty-five Thousand Five Hundred Ninety-three Dollars, with interest thereon at the rate of seven per cent per annum from the date hereof until paid, together with said defendants’ costs and disbursements incurred in this action, amounting to the sum of- Dollars.”

From this judgment this appeal was taken. The transcript contains the complaint and answer upon which the case was tried, and the verdict of the jury and the judgment.

Four errors are assigned: First, that the court erred in entering an unconditional personal judgment against the appellant. Second, the court erred in entering a judgment which failed to describe the land for which damages had been assessed, and which failed to show whether the damages or compensation assessed included only the land described in the complaint or whether it also included the land described in the answer, which appellant contended it did not require. Third, the court erred in condemning the land to appellant’s [167]*167use upon payment of the sum awarded. Fourth, the court erred in entering judgment upon a verdict in direct contravention of the statutes, and which was erroneous for the following reasons: (a) It did not describe the land, (b) The award was in a lump sum. (c) Each source of compensation or damages was not separately assessed as required by sec. 5220 of the Rev. Codes, (d) It did not show what was allowed for the improvements situated on the premises and alleged to be of the value of $2,500.' (e) It did not show what compensation or damage was allowed for the forty acres described, which respondents contend had a special value, (f) It did not show the compensation or damage allowed for the remaining 901.45 acres of land alleged to be of the value of $75 per acre, and constituting several tracts, (g) The verdict does not show whether the jury found that the appellant would damage or acquire for right of way the additional eighty acres of land owned by the respondents, and which they allege in their answer would be flooded by the reservoir. And the verdict does not show what damages, if any, were assessed against appellant on account of said land.

The evidence and the instructions of the trial court are not contained in the transcript, and much of the argument made by counsel for appellant is answered by the verdict of the jury upon the evidence, and the presumption is that the court fully advised the jury as to their duties in finding a verdict in such case. It is first contended by counsel for appellant that in a proceeding for the condemnation of property for public use under the eminent domain provisions of the statute, a personal judgment cannot be rendered against the plaintiff, and that the verdict of the jury must in form show that the jury found upon each of the questions covered by sec. 5220 of the Rev. Codes. The consideration of such question involves the procedure under the eminent domain statute of the state enacted for the purpose of carrying out the provisions of the constitution. Sec. 14, art. 1 of the constitution provides:

“The necessary use of lands for the construction of reservoirs or storage basins, for the purpose of irrigation, or for [168]*168the rights of way for the construction of canals, ditches, flumes or pipes to convey water to the place of use, for any useful, beneficial or necessary purpose, or for drainage; or for the drainage of mines, or the working thereof, by means of roads, railroads, tramways, cuts, tunnels, shafts, hoisting works, dumps, or other necessary means to their complete development or any other use necessary to the complete development of the material resources of the state or the preservation of the health of its inhabitants, is hereby declared to be a public use, and subject to the regulation and control of the state.
“Private property may be taken for public use, but not until a just compensation, to be ascertained in a manner prescribed by law, shall be paid therefor. ’ ’

It will thus be seen that under the provisions of the constitution private property may be taken for public use, but not until just compensation, ascertained in a manner prescribed by law, shall be paid therefor. This provision of the constitution limits the power of the legislature in providing the proceedings for the taking of private property for public use, in that before such property can be so taken a just compensation must be first ascertained and the payment therefor made. (Portneuf Irr. Co., Ltd., v. Budge, 16 Ida. 116, 18 Ann. Cas. 674, 100 Pac. 1046; Knowles v. New Sweden Irr. Dist., 16 Ida. 217, 101 Pac. 81; Pyle v. Woods, 18 Ida. 674, 111 Pac. 746; Idaho & Western Ry. Co. v. Columbia Conference etc., 20 Ida. 568, 119 Pac. 60; Bensley v. Mountain Lake Water Co., 13 Cal. 306, 73 Am. Dec. 575; Cook v. South Park Commrs., 61 Ill. 120; Chicago & Mil. R. R. Co. v. Bull, 20 Ill. 218; Johnson v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Telford Lands LLC v. Cain
303 P.3d 1237 (Idaho Supreme Court, 2013)
State Ex Rel. Symms v. City of Mountain Home
493 P.2d 387 (Idaho Supreme Court, 1972)
City of Caldwell v. Roark
437 P.2d 615 (Idaho Supreme Court, 1968)
County of Maricopa v. Paysnoe
319 P.2d 995 (Arizona Supreme Court, 1957)
Yellowstone Pipe Line Company v. Drummond
287 P.2d 288 (Idaho Supreme Court, 1955)
Renninger v. State
213 P.2d 911 (Idaho Supreme Court, 1950)
Village of Lapwai v. Alligier
207 P.2d 1025 (Idaho Supreme Court, 1949)
Vallejo & Northern Railroad v. Reed Orchard Co.
162 P. 914 (California Court of Appeal, 1916)
Colusa v. Superior Court of County of Glenn
161 P. 1011 (California Court of Appeal, 1916)
Reed Orchard Co. v. Superior Court
128 P. 9 (California Court of Appeal, 1912)
Kelley v. Clark
121 P. 95 (Idaho Supreme Court, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
121 P. 88, 21 Idaho 160, 1912 Ida. LEXIS 111, Counsel Stack Legal Research, https://law.counselstack.com/opinion/big-lost-river-irrigation-co-v-davidson-idaho-1912.