Big City Dynasty Corp v. FP Holdings, L.P.

District Court, D. Nevada·Decided May 14, 2021·No. 2:19-cv-02078·Unknown

Opinion

BIG CITY DYNASTY CORP. and RYAN Case No.: 2:19-cv-02078-APG-NJK RADDON, Order Granting in Part the Plaintiffs’ Plaintiffs Motion for Summary Judgment and Denying the Defendant’s Motion for v. Summary Judgment FP HOLDINGS, L.P., [ECF Nos. 46, 50] Defendant

Plaintiff Ryan Raddon is an internationally known DJ performing under the stage name Kaskade and the principal of plaintiff Big City Dynasty Corp. Raddon and Big City entered into an Artist Residency Agreement with defendant FP Holdings, Inc., which is the ultimate owner of The Palms Casino & Resort in Las Vegas. The parties’ agreement concerned Raddon’s services as a resident performer at KAOS nightclub at The Palms in 2019 and 2020. There is no dispute that the parties’ agreement is valid and enforceable, that the plaintiffs did not breach the agreement, and that FP anticipatorily breached the agreement in November 2019 by closing KAOS nightclub and refusing to schedule any more performances in 2019 or 2020. The parties dispute only the proper measure of the plaintiffs’ damages. The plaintiffs move for summary judgment, arguing that they are entitled to the full amount of the compensation they would have received had FP performed, that the sum became due and payable in full upon FP’s anticipatory breach, and that subsequent events have no bearing on that amount. They also contend that they had no duty to mitigate and that they are entitled to attorney’s fees, costs, and prejudgment interest. / / / / FP opposes and moves for summary judgment, arguing that the plaintiffs must prove that FP’s breach caused their damages. FP asserts the plaintiffs cannot show the breach caused all the claimed damages because in March 2020, the Covid-19 pandemic led to Nevada’s Governor issuing shutdown orders that would have made the parties’ performance impossible for the remainder of 2020. FP concedes that it owes $1,200,000 for the seven shows that should have

taken place in 2019 after KAOS closed, less any amount the plaintiffs unreasonably failed to mitigate. And it contends that, considering only one quarter of 2020 was available for shows, the plaintiffs should be compensated for only 7.5 shows in 2020 before the shutdown orders in March 2020. But FP contends it already paid an advance on the 2020 performances that would cover this amount, so it owes nothing further for 2020. FP also argues that its mitigation defense should not be decided as a matter of law because the plaintiffs cite unpersuasive authority for the proposition that they need not mitigate and because the plaintiffs unreasonably spent only one week exploring other opportunities. Finally, FP contends that because the case is not over, the plaintiffs have not established they are

prevailing parties entitled to fees and costs under the agreement. The parties are familiar with the facts, so I repeat them here only where necessary to resolve the motions. I grant in part the plaintiffs’ motion. FP’s failure-to-mitigate defense fails. I deny the remainder of the plaintiffs’ motion and FP’s motion because genuine disputes remain regarding the plaintiffs’ damages. Summary judgment is appropriate if the movant shows “there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). A fact is material if it “might affect the outcome of the suit under the governing law.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). A dispute is genuine if “the evidence is such that a reasonable jury could return a verdict for the nonmoving party.” Id. The party seeking summary judgment bears the initial burden of informing the court of the basis for its motion and identifying those portions of the record that demonstrate the absence of a genuine issue of material fact. Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1986). The

burden then shifts to the non-moving party to set forth specific facts demonstrating there is a genuine issue of material fact for trial. Sonner v. Schwabe N. Am., Inc., 911 F.3d 989, 992 (9th Cir. 2018) (“To defeat summary judgment, the nonmoving party must produce evidence of a genuine dispute of material fact that could satisfy its burden at trial.”). I view the evidence and reasonable inferences in the light most favorable to the non-moving party. Zetwick v. Cnty. of Yolo, 850 F.3d 436, 440-41 (9th Cir. 2017). A. Amount of Damages The amount of the plaintiffs’ damages largely turns on two questions. First, the parties dispute whether post-breach events can be considered in measuring damages. Second, they

dispute whether the plaintiffs unreasonably failed to mitigate their damages. 1. Post-Breach Events The plaintiffs contend that upon FP’s anticipatory breach in November 2019, the contract provides that the plaintiffs were entitled to the entire amount of unpaid compensation for all the contemplated performances for the remainder of 2019 and 2020. They contend that amount became immediately due and payable under the agreement, so post-breach events cannot reduce that amount. FP responds that causation is an essential element of the plaintiffs’ breach of contract claim, and post-breach events can be considered to determine whether the breach caused the claimed damages. FP argues that because the shutdown orders would have made both parties’ performance impossible as of March 2020, FP’s anticipatory breach in 2019 did not cause any damages after March 2020. The contract calls for the plaintiffs to perform at the Palms’ nightclub or dayclub 30 times in 2019 and 30 times in 2020. ECF No. 46-5 at 2. Section 2(c) of the contract sets forth the plaintiffs’ compensation for these performances. The plaintiffs were entitled to $300,000 for

each performance.1 ECF No. 46-5 at 3. The parties agreed FP would pay the performance fees in stages, with half paid up front for each year and the remainder after each performance was completed. For 2019, FP had to pay $2,250,000 within 10 days of executing the agreement, $2,250,000 within five business days of January 1, 2019, and $150,000 within five business days of each completed performance. Id. at 4. FP paid the two advance fees totaling $4,500,000 and $150,000 for each performance completed in 2019. ECF No. 50-1 at 3. FP did not pay for seven performances in 2019 that did not take place.2 FP admits that it owes $1,200,000 for those seven performances (aside from the issue of mitigation). The fee structure was similar for 2020. FP had to pay $2,250,000 within five business

days of September 30, 2019. ECF No. 46-5 at 4. FP paid this amount. ECF No. 50-1 at 5. FP also had to pay $2,250,000 within five business days of January 1, 2020, and $150,000 within five business days of each performance in 2020. ECF No. 46-5 at 4. FP has not paid the January 2020 advance or $150,000 for any of the 30 performances that were supposed to occur in 2020. The contract contains this force majeure clause: [I]f either party’s presentation of a show is prevented, rendered impossible or materially frustrated by any act, requirement or regulation or action of any public authority or bureau, . . . act of God, . . . or any other cause beyond either party’s

Free access — add to your briefcase to read the full text and ask questions with AI

Big City Dynasty Corp v. FP Holdings, L.P., (D. Nev. 2021).

Big City Dynasty Corp v. FP Holdings, L.P. (Big City Dynasty Corp v. FP Holdings, L.P.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Sheehan & Sheehan v. Nelson Malley & Co.
117 P.3d 219 (Nevada Supreme Court, 2005)
Victoria Zetwick v. County of Yolo
850 F.3d 436 (Ninth Circuit, 2017)
Sonner v. Schwabe N. Am., Inc.
911 F.3d 989 (Ninth Circuit, 2018)