Big Band, Inc. v. Williams

202 N.W.2d 121, 87 S.D. 24, 1972 S.D. LEXIS 91
CourtSouth Dakota Supreme Court
DecidedNovember 15, 1972
DocketFile 11026
StatusPublished
Cited by13 cases

This text of 202 N.W.2d 121 (Big Band, Inc. v. Williams) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Big Band, Inc. v. Williams, 202 N.W.2d 121, 87 S.D. 24, 1972 S.D. LEXIS 91 (S.D. 1972).

Opinion

BIEGELMEIER, Judge.

This action is based on a contract whereby plaintiff was to manufacture and distribute and defendant was to buy a quantity of cattle guards invented by defendant, a rancher turned inventor. Altered and amended as to the number only as hereafter mentioned, the contract provided defendant would buy 500 of the guards over a period of six months at $100 each. Provision for payment was that defendant “will advance * * * $40.00 * * * for each cattle guard manufactured and available for sale” and “pay the remaining * * * $60.00 for each cattle guard as he [defendant] removes it from stock or at the time it is shipped to a dealer or distributor.” Big Band agreed to pay defendant a royalty of $5 for each guard manufactured and sold by it. The complaint alleged defendant failed and refused to accept and pay for the “quantity specified in the * * * contract.” Defendant’s answer included a counterclaim. While there was no statement in the complaint of performance of the contract on its behalf or that it had manufactured all or any part of the guards or defendant had removed any guards from stock or shipped them to a dealer, the evidence showed plaintiff did manufacture a quantity of the guards and defendant sold some of them. The unit is both a gate and a guard; it permits passage of vehicles but because of the construction it impedes or discourages cattle from crossing it.

Trial was to the court. On findings of fact and conclusions of law, the court entered a judgment which dismissed defendant’s counterclaim and awarded plaintiff $29,446.99 damages.

*27 It appears the contract as first written and signed provided that defendant would buy 1,000 guards. During production, which began in January 1970, the parties changed the contract by striking out the 1,000 figure, inserting 500 in lieu thereof and initialing the change; otherwise it remained as written, including the original date of January 13, 1970. By reason of some suggestion in the briefs of an earlier oral contract and a lack of consideration for one of them and therefore doubt as to the contract before the court, we note that SDCL 53-8-6 provides:

“A contract not in writing may be altered in any respect by consent of the parties, in writing, without a new consideration, and is extinguished thereby to the extent of the alteration.”

SDCL 53-8-7 next provides: “A contract in writing may be altered by a contract in writing without a new consideration * * *”, Here the contract was so altered by defendant and the same officer of plaintiff who negotiated and signed it for plaintiff. The contract as first written extinguished the prior oral -agreement, if there was one, under SDCL 53-8-6, and the alteration made in writing of the contract as first written was a valid alteration thereof under SDCL 53-8-7. Neither required a new consideration and the contract as so altered is the only contract between the parties before the court for decision. See Williams v. Superior Airways, 78 S.D. 148, 99 N.W.2d 224.

The trial court found plaintiff manufactured 424 guards, of which 25 were sold by plaintiff. Of the 399 manufactured for defendant, 130. wére delivered to him and 29 to Williams’ dealers; this left a balance of 240 guards on hand and 101 not built. From plaintiff’s evidence that the cost of material was $42.61 and the cost of labor was $9.89, the trial court found the cost of each cattle guard was $52.50 plus $12.50 for overhead or a total of $65, leaving a profit to plaintiff of $35 per guard.

The trial court’s findings were in considerable detail and involved various charges and credits. Mention of some of these will be made. At the outset the amounts here mentioned are in accord with the trial court’s findings, undisputed or admitted.

*28 The serious question involved is damages. Plaintiff consistently contended in the trial court and contends here that this action is one for recovery of damages from breach of contract under SDCL 21-2-1 and that the U.C.C. does not apply as neither the trial judge in his opinion nor counsel in their briefs here have cited and argued any provisions of the U.C.C.; therefore, we review the judgment so far as this action is concerned under SDCL 21-2-1 and 21-1-5 which have been cited and argued.

SDCL 21-2-1 provides:

“For the breach of an obligation arising from contract, the measure of damages, except where otherwise expressly provided by this code, is the amount which will compensate the party aggrieved for all the detriment proximately caused thereby, or which, in the ordinary course of things, would be likely to result therefrom. No damages can be recovered for a breach of contract which are not clearly ascertainable in both their nature and their origin.”

SDCL 21-1-5 reads:

“Notwithstanding the provisions of these statutes, no person can recover a greater amount in damages for the breach of an obligation than he could have gained by the full performance thereof on both sides [with exceptions not here applicable] * * (emphasis supplied)

When the action is for breach of contract, plaintiff is entitled to recover all his detriment proximately caused by the breach, not exceeding the amount he would have gained by full performance. The issue is what he is entitled to under his contract, less the cost of fully completing it in accord with its terms. Davis v. Tubbs, 7 S.D. 488, 64 N.W. 534, citing the predecessor of SDCL 21-1-5. Applying these guides to the facts here, the judgment must be reversed.

In our opinion special tooling costs of $5,502 are not an allowable damage. Plaintiff’s brief admits that at the time of the initial contract “it was not within the contemplation of the *29 parties to (1) build a paint shop; (2) construct or buy overhead racks, a special rod cleaner and jigs.” It claims this was done after the contract was entered into either “because of demands by appellant or because of the new nature of the product”. This constitutes no reason to charge this cost to defendant. That plaintiff was required to buy all tools necessary to perform the contract was a matter to consider when it entered into the contract. The purchase price of tools, other equipment or the erection of a building are not charges that can be made against a party to a contract to manufacture a product therewith.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John Morrell & Co. v. Halbur
476 F. Supp. 2d 1061 (N.D. Iowa, 2007)
Alma Group, L.L.C. v. Weiss
2000 SD 108 (South Dakota Supreme Court, 2000)
Alma Group
2000 SD 108 (South Dakota Supreme Court, 2000)
Bad Wound v. Lakota Community Homes, Inc.
1999 SD 165 (South Dakota Supreme Court, 1999)
Centrol, Inc. v. Morrow
489 N.W.2d 890 (South Dakota Supreme Court, 1992)
Ducheneaux v. Miller
488 N.W.2d 902 (South Dakota Supreme Court, 1992)
Mash v. Cutler
488 N.W.2d 642 (South Dakota Supreme Court, 1992)
Regan v. Moyle Petroleum Co.
344 N.W.2d 695 (South Dakota Supreme Court, 1984)
Goodwyn v. Sencore, Inc.
389 F. Supp. 824 (D. South Dakota, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
202 N.W.2d 121, 87 S.D. 24, 1972 S.D. LEXIS 91, Counsel Stack Legal Research, https://law.counselstack.com/opinion/big-band-inc-v-williams-sd-1972.