Bierlein v. Gagnon

96 N.W.2d 473, 255 Minn. 143, 1959 Minn. LEXIS 579
CourtSupreme Court of Minnesota
DecidedApril 3, 1959
Docket37,559
StatusPublished
Cited by9 cases

This text of 96 N.W.2d 473 (Bierlein v. Gagnon) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bierlein v. Gagnon, 96 N.W.2d 473, 255 Minn. 143, 1959 Minn. LEXIS 579 (Mich. 1959).

Opinion

Knutson, Justice.

This is an appeal from an order denying defendants’ motion for amended findings of fact, conclusions of law, and order for judgment or, in the alternative, for a new trial in a proceeding to foreclose a mechanics lien.

Sometime prior to 1954 defendants decided to build a house on the hills overlooking the Minnesota River Valley not far north of the city of Shakopee. The description of the tract of land on which they desired to build is of no importance to a decision of this case.

During the early part of 1954, defendants employed Thorshov & Cerny, an architectural firm in Minneapolis, to prepare for them detailed plans and specifications for the home they wished to build. Such plans and specifications were completed during the summer of 1954 and were submitted to several contractors in the Twin Cities area for the purpose of procuring bids. The bids received were opened in the office of the architects on October 28, 1954, and ranged from $36,000 to $45,000. After a discussion with the architects, defendants rejected all bids. It was the opinion of the architects that substantial savings *145 could be made in labor and material by using a builder and procuring material from a source closer to the land on which the house was to be built.

Thereafter, defendants called at the Henry Simons Lumber Company in Chaska and discussed budding the house with them. On the first visit they refused to disclose their names or where they intended to build the house because they did not want to be solicited for the business. However, at a later visit they did so, and, through the manager of this lumber yard, Paul J. Murphy, they met Ray J. Bierlein, one of the copartners of Chaska Construction Company, plaintiffs in this action. The plans and specifications theretofore prepared by Thorshov & Cemy were submitted to Bierlein so that he could prepare an estimate of the cost of constructing the house. After procuring estimates on the cost of plumbing, wiring, material, and other items which probably would be sublet and which were essential to the complete construction of the house, and on the basis thereof, he estimated that the house, in order to be built according to the plans and specifications of the architects, would cost $45,000. Thereafter, at the request of defendants, the plans and specifications were altered by Henry Simons Lumber Company with the object of reducing the cost. Defendants stated that they wanted to keep the cost down to about $28,000. From this point on the testimony of' plaintiffs and defendants is in irreconcilable conflict. Defendants claim that plaintiffs undertook to build the house for $28,000. Plaintiffs claim that on the basis of the revised plans and specifications they estimated that the house could be built for $34,000. No written contract was ever entered into. Construction began in the late fall of 1954 and was discontinued in 1956 after the house was substantially completed. Defendants have paid plaintiffs $11,000 to appy upon the cost. Failing to obtain payment of the balance claimed to be due, plaintiffs filed a mechanics lien.

In the trial of a foreclosure of the mechanics lien, the court found that plaintiffs were entitled to recover, in addition to what they had been paid, the sum of $22,163.58 and ordered a sale of the premises to pay the unpaid balance and expenses of the foreclosure, including an attorney’s fee of $3,000. On this appeal from an order denying their motion for amended findings, conclusions of law, and order for *146 judgment or for a new trial, defendants contend: (1) That the evidence compels a finding that the parties entered into an oral contract under which plaintiffs were obligated to build the house for $28,000; (2) that the evidence does not sustain a finding that plaintiffs’ contribution in labor and material was of the reasonable value found by the court; (3) that the evidence compels a finding that plaintiffs knowingly filed a lien statement claiming more than was justly due; (4) that plaintiffs are estopped from claiming more than $28,000; and (5) that the attorneys’ fees allowed by the court are excessive.

In contending that the evidence compels a finding that the parties entered into a contract under which plaintiffs were obligated to build the house according to the plans and specifications as revised by Henry Simons Lumber Company, defendants would have us disregard the testimony of Ray J. Bierlein and other supporting evidence. Even defendants’ own testimony does not bear them out. We may admit, for the purpose of this decision, that defendants continually insisted that they wanted to keep the cost at $28,000, but that of itself does not establish a contract in the face of plaintiffs’ testimony that they continued to advise defendants that the house could not be built for that amount. It is evident from an examination of the evidence that the parties never did come to a common understanding as to the cost of the house. Defendant Theodore J. Gagnon, among other things, testified:

“From the time the basement was begun we tried to have several discussions with the Chaska Construction Company to arrive at a figure, and there was plenty of time for that, but all I got was evasions.”

Further than that, after the house was started, numerous changes were made at the request of defendants, adding to the cost. Among others, it might be mentioned that the house was made 2 feet wider than the original plans called for, at the request of defendants; heating was changed from hot air to hot water; the location of windows and the type of construction of a fireplace were changed; and much work which originally had been done had to be done over again because of changes desired by defendants. Defendants admitted that they expected that these changes would add to the cost. They claim that the increased costs occasioned by some of the changes were offset by *147 other changes which decreased the cost, but the evidence amply sustains a finding that the many changes that were made added materially to the cost of the house. The manner in which the cost of these changes was handled belies the existence of a contract. Nowhere does there appear any evidence that the parties agreed on the cost of such changes or that the parties should be given either a credit or a debit therefor. If there had been a contract, surely the parties would have agreed also on who was to stand the expense of the increased costs or receive credit for decreased costs, when there were such, and how much they should be.

At one time plaintiffs furnished a statement to Twin City Federal Savings and Loan Association in which they estimated the cost of the house would be $28,882.11. The statement was in support of defendants’ application for a loan. Defendants claim that this statement shows that plaintiffs had entered into a contract to build the house for that amount. At best, it was only an estimate intended to assist defendants in obtaining a loan. It was not conclusive on the issue of whether the parties had entered into a contract. Its evidentiary value was for the trial court to determine.

Without going into more detail, we are convinced that the evidence sustains the court’s finding that the parties never did enter into a contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gardner v. Hatch
408 N.W.2d 879 (Court of Appeals of Minnesota, 1987)
RB Thompson, Jr. Lumber v. Windsor Dev.
383 N.W.2d 357 (Court of Appeals of Minnesota, 1986)
Poppler v. O'CONNOR
235 N.W.2d 617 (Supreme Court of Minnesota, 1975)
O'DONNELL v. McGee Trucks, Inc.
199 N.W.2d 432 (Supreme Court of Minnesota, 1972)
Obraske v. Woody
199 N.W.2d 429 (Supreme Court of Minnesota, 1972)
Malmin v. Grabner
163 N.W.2d 39 (Supreme Court of Minnesota, 1968)
Sorenson v. Cargill, Inc.
163 N.W.2d 59 (Supreme Court of Minnesota, 1968)
Hunker Ex Rel. Estate of Jernigan v. Melugin
391 P.2d 407 (New Mexico Supreme Court, 1964)
Larson-Roberts Electric Co., Inc. v. Burdick
127 N.W.2d 163 (Supreme Court of Minnesota, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
96 N.W.2d 473, 255 Minn. 143, 1959 Minn. LEXIS 579, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bierlein-v-gagnon-minn-1959.