Bienville Parish School Board v. Thrash Construction Services, LLC, American Testing Lab, LLC, Yeager, Watson & Associates, Inc., Keystone Retaining Wall Systems, Inc., Lewis Stone, LLC, and North American Specialty Insurance Company
Opinion
Judgment rendered December 18, 2024.
Application for rehearing may be filed within the delay allowed by Art. 2166, La. C.C.P.
No. 56,021-CA
COURT OF APPEAL
SECOND CIRCUIT
STATE OF LOUISIANA
*****
BIENVILLE PARISH SCHOOL Plaintiff-Appellant BOARD
versus
THRASH CONSTRUCTION Defendants-Appellees SERVICES, LLC, AMERICAN TESTING LAB, LLC, YEAGER, WATSON & ASSOCIATES, INC., KEYSTONE RETAINING WALL SYSTEMS, INC., LEWIS STONE, LLC, AND NORTH AMERICAN SPECIALTY INSURANCE COMPANY
*****
Appealed from the
Second Judicial District Court for the Parish of Bienville, Louisiana Trial Court No. 44-637
Honorable Charles Glenn Fallin, Judge
*****
COOK, YANCEY, KING & GALLOWAY Counsel for Appellant By: Robert Kennedy, Jr.
KEAN MILLER, LLP Counsel for Appellee, By: Michael D. Lowe Thrash Construction Services, LLC
KREBS FARLEY, PLLC Counsel for Appellee, By: Jonathan S. Ord North American Specialty Insurance
Company
PIPES, MILES, BECKMAN, LLC Counsel for Appellee, By: Emily Ellis Ross North American Specialty Insurance
Company
HAILEY, McNAMARA, MAYER, Counsel for Appellee, SMITH, BERNARD, LLC American Testing Lab, By: Darren Albert Patin LLC
MAYER, SMITH & ROBERTS, LLP Counsel for Appellee, By: Caldwell Roberts, Jr. Yeager, Watson & Associates, Inc.
BERNHARD, LLC Counsel for Appellee, By: Matthew J. Guy Keystone Retaining Wall Systems, Inc.
COLVIN, SMITH, McKAY & BAYS Counsel for Appellee, By: James Henry Colvin, Jr. Lewis Stone, LLC
*****
Before COX, HUNTER, and ELLENDER, JJ.
ELLENDER, J.
The Bienville Parish School Board (“BPSB”) appeals a judgment that sustained peremptory exceptions of peremption and dismissed all claims against two defendants, Thrash Construction Services LLC (“Thrash”) and its bond issuer, North American Specialty Insurance Company (“NASIC”). For the reasons expressed, we affirm.
FACTUAL BACKGROUND
In 2014, BPSB sought to upgrade its athletic facility at Gibsland-
Coleman High School by installing an all-weather track. It obtained a bond issue, hired an architect, and put the project out for bid. In December 2014, it awarded the contract to Thrash, executing a standard-form agreement (“the Agreement”) for $2,455,898. NASIC underwrote the performance and payment bonds. BPSB issued a notice to proceed in January 2015, with a projected completion date of January 10, 2016.
The architect’s plans specified building three MSE (mechanically stabilized earth) retaining walls; Thrash hired a subcontractor for this. However, at some point in the process, after a major rain event, Thrash discovered the MSE walls were unstable; in fact, they were moving. The parties brought in a professional engineer, who inspected and reported in January 2017 that the MSE walls would have to be destroyed. After several meetings seeking remediation, on May 25, 2018, BPSB terminated the Agreement.
PROCEDURAL HISTORY
Even before termination, on January 8, 2018, BPSB filed this suit against Thrash and NASIC, the architects, subcontractors, and others.
Without mentioning the Public Works Act, the petition sought damages for defective design, construction, and workmanship of the project.
Thrash and NASIC responded with dilatory exceptions of prematurity seeking to dismiss or stay the action. In the Agreement, the parties had elected to include a binding dispute resolution clause.1 The general conditions of the Agreement, § 15.4.1, recited that a demand for arbitration “shall be made in writing, delivered to the other party to the Contract, and filed with the person or entity administering the arbitration.” With respect to the time of the demand, § 15.4.1.1, stated:
A demand for arbitration shall be made no earlier than concurrently with the filing of a request for mediation, but in no event shall it be made after the date when the institution of legal or equitable proceedings based on the Claim would be barred by the applicable statute of limitations. For statute of limitations purposes, receipt of a written demand for arbitration shall constitute the institution of legal or equitable proceedings based on the Claim.
After a hearing in July 2018, the district court granted the exceptions.
By judgment of August 7, 2018, the court ordered that all claims against Thrash and NASIC were “stayed, pending completion of arbitration.”
Over five years later, in August 2023, Thrash filed a peremptory exception of peremption; NASIC soon filed its own similar exception. They asserted that any claim against a contractor or its surety in connection with a public works project was subject to a five-year peremptive period under the Public Works Act, R.S. 38:2189. They showed that since the stay issued, BPSB had never instituted a claim for arbitration and, thus, had missed the five-year deadline incorporated by § 15.4.1.1. They argued the claim was extinguished and the suit should be dismissed.
1 The Agreement is an AIA® Document A101™-2007.
BPSB opposed the exceptions. It conceded that R.S. 38:2189 was a peremptive period but argued that its timely suit interrupted or suspended this, and that the claim was viable “pending completion of arbitration.” Since the stay was still in force, BPSB contended, the claim was still alive even though over five years had passed with no request for arbitration.
After a hearing in November 2023, the district court granted the exceptions of peremption and rendered judgment dismissing BPSB’s claims against Thrash and NASIC. BPSB appealed.
APPLICABLE LAW
Contracts have the effect of law for the parties. Bonilla v. Verges Rome Architects, 23-00928 (La. 3/22/24), 382 So. 3d 62; Warsaw Country Store LLC v. Bryan Ashley Enters. Inc., 55,403 (La. App. 2 Cir. 1/10/23), 378 So. 3d 757. Interpretation of a contract is the determination of the common intent of the parties. La. C.C. art. 2045. When the words of a contract are clear and explicit and lead to no absurd consequences, no further interpretation may be made in search of the parties’ intent. La. C.C. art. 2046. Bonilla v. Verges Rome Architects, supra.
A provision in any written contract to settle by arbitration a controversy thereafter arising out of the contract shall be “valid, irrevocable, and enforceable, save upon such grounds as exist at law or in equity for the revocation of any contract.” La. R.S. 9:4201. Louisiana law strongly favors arbitration. Aguillard v. Auction Mgmt. Corp., 04-2804 (La. 6/29/05), 908 So. 2d 1; Iberia Bank v. Dalton Const. LLC, 52,752 (La. App. 2 Cir. 6/26/19), 277 So. 3d 829.
The relationship between arbitration and litigation is stated in the Louisiana Binding Arbitration Law, La. R.S. 9:4202:
If any suit or proceedings be brought upon any issue referable to arbitration under an agreement in writing for arbitration, the court in which suit is pending, upon being satisfied that the issue involved in the suit or proceedings is referable to arbitration under such an agreement, shall on application of one of the parties stay the trial of the action until an arbitration has been had in accordance with the terms of the agreement, providing the applicant for the stay is not in default in proceeding with the arbitration.
The time limit for asserting a claim on a public contract is stated in the Public Works Act, specifically La. R.S. 38:2189:
Any action against the contractor on the contract or on the bond, or against the contractor or the surety or both on the bond furnished by the contractor, all in connection with the construction, alteration, or repair of any public words let by the state or any of its agencies, boards or subdivisions shall prescribe 5 years from the substantial completion * * * or acceptance of such work, whichever occurs first, or of notice of default of the contractor unless otherwise limited in this Chapter.
The five-year period of 38:2189 is peremptive. State v. McInnis Bros.
Free access — add to your briefcase to read the full text and ask questions with AI
Bienville Parish School Board v. Thrash Construction Services, LLC, American Testing Lab, LLC, Yeager, Watson & Associates, Inc., Keystone Retaining Wall Systems, Inc., Lewis Stone, LLC, and North American Specialty Insurance Company (Bienville Parish School Board v. Thrash Construction Services, LLC, American Testing Lab, LLC, Yeager, Watson & Associates, Inc., Keystone Retaining Wall Systems, Inc., Lewis Stone, LLC, and North American Specialty Insurance Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.