BGD, LLC v. Stephen K. Burns, Pacer Minerals, LLC, a South Dakota Limited Liability Company, ...

Court of Appeals of Minnesota·Decided June 22, 2026·No. a252055·Unpublished

Opinion

This opinion is nonprecedential except as provided by Minn. R. Civ. App. P. 136.01, subd. 1(c).

STATE OF MINNESOTA

IN COURT OF APPEALS

A25-2055

BGD, LLC,

Appellant,

vs.

Stephen K. Burns,

Respondent,

Pacer Minerals, LLC, a South Dakota Limited Liability Company, et al., Defendants.

Filed June 22, 2026

Reversed and remanded

Rasmusson, Judge

Carver County District Court File No. 10-CV-22-120

Paul W. Chamberlain, John P. Chamberlain, Chamberlain Law Firm, Wayzata, Minnesota (for appellant)

Richard C. Landon, Charles K. Maier, Amy Erickson, Lathrop GPM LLP, Minneapolis, Minnesota (for respondent)

Considered and decided by Larkin, Presiding Judge; Cochran, Judge; and Rasmusson, Judge.

NONPRECEDENTIAL OPINION

RASMUSSON, Judge In this contract dispute, appellant alleged that respondent breached a repayment agreement. In its posttrial findings of fact, conclusions of law, and order for judgment, the

district court accepted the jury’s verdict that respondent breached the repayment agreement and that this breach did not cause appellant damages. Appellant primarily argues that the district court erred by accepting the jury’s logically impossible finding of no causation of damages despite finding a breach of the repayment agreement. Because, under the unique facts of this case, the jury’s finding of no causation of damages is impossible to reconcile with its finding of breach, we reverse and remand for a new trial on damages.

FACTS

Appellant BGD LLC is a Minnesota limited liability company created by Robert Griffith. BGD is owned by a trust controlled by Griffith. Respondent Stephen K. Burns is a businessman who owns, among other ventures, an excavating business. Pacer Minerals Griffith and Burns collaborated in multiple business ventures, but their involvement with Pacer Minerals forms the basis for the issues in this appeal. In 2015, Burns identified an investment opportunity in a South Dakota mining operation and formed Pacer Minerals LLC, a South Dakota limited liability company. Griffith and another individual, R.B., agreed to invest in the project and, along with Burns, initially invested the same amount of money in the operation. In the beginning, everyone had an equal one-third membership stake.

Pacer required substantial cash-call contributions from the members. At some point, R.B. stopped investing in Pacer. After contributing $581,500 in cash, Burns informed Griffith that he lacked funds to meet his investment obligations in Pacer. Griffith believed that Burns still sought to maintain his equal ownership stake in Pacer and accordingly

began contributing Burns’s share through BGD. Griffith and Burns came to an oral agreement that BGD would advance Burns’s share of the contributions and that Burns would repay these funds on a two-for-one basis. Subsequent cash calls resulted in BGD contributing several million dollars by the end of 2018. Repayment Agreement In 2019, the parties addressed their obligations with respect to these contributions in a repayment agreement. 1 The repayment agreement recites that the three members contributed $10,175,878 combined, with Burns contributing $581,500 in cash and BGD contributing $7,989,378 in cash. The repayment agreement additionally recites that BGD and Burns had an “unwritten agreement” that “Burns will repay BGD for the difference in the $581,500 that Burns actually paid to Pacer and Rushmore versus the $3,391,959 that was rightfully Burns’ share of the $10,175,878 total cash paid to Pacer and Rushmore.” 2 Accordingly, the agreement provides that “Burns hereby acknowledges that he is indebted to BGD in the principal amount of $2,810,459.” It added that Burns agrees to repay this amount on a two-for-one basis with accumulated interest.

1 At trial, Burns disputed that he signed this agreement. Burns does not challenge the district court’s acceptance of the jury’s finding that he signed the agreement.

2 The repayment agreement describes Rushmore Reserves LLC as a separate South Dakota

limited liability company of which BGD and Burns owned equal shares. Because the parties only refer to Pacer in their briefs, and because the repayment agreement refers to the contributions to Rushmore and Pacer in the aggregate, we primarily use the term “Pacer” when referring to the two entities throughout this opinion.

Litigation In February 2022, BGD filed a lawsuit against Burns alleging breach of the repayment agreement. Burns filed an answer, counterclaim, and cross-claim. In this filing, Burns raised affirmative defenses including equitable estoppel.

The matter proceeded to a six-day jury trial in September 2024. The court submitted questions regarding both legal and equitable issues to the jury but considered the jury’s findings on the equitable issues as only advisory. Pertinent to the issues on appeal, the jury found that the repayment agreement was an enforceable contract, that Burns signed and breached the contract, but that the breach did not cause damage to BGD. In the district court’s findings of fact, conclusions of law, order for judgment, and judgment, it accepted the jury’s findings on these legal questions, reasoning that it was possible to reconcile the jury’s finding of breach with the finding of no damages.

BGD subsequently moved for amended findings and conclusions, requesting that the district court find and impose damages and enter judgment against Burns in the amount of $12,485,337. In the alternative, BGD requested a new trial on damages. The district court denied the motion.

This appeal follows.

DECISION

BGD appeals the district court’s March 2025 judgment in which it addressed the special-verdict responses and the October 2025 order denying its motion for amended findings and conclusions or a new trial. Specifically, BGD contends that the district court erred by accepting the jury’s logically impossible finding of no causation of damages

despite finding a breach. BGD faces a high bar in challenging the jury’s special-verdict finding that the breach did not cause damages. A reviewing court should not set aside a jury’s special verdict “unless it is manifestly and palpably contrary to the evidence viewed as a whole and in the light most favorable to the verdict.” Raze v. Mueller, 587 N.W.2d 645, 648 (Minn. 1999) (quotations omitted). In reviewing a challenge to a special-verdict answer, appellate courts consider “whether the special verdict answers can be reconciled in any reasonable manner consistent with the evidence and its fair inferences. If the answers to special verdict questions can be reconciled on any theory, the verdict will not be disturbed.” Dunn v. Nat’l Beverage Corp., 745 N.W.2d 549, 555 (Minn. 2008) (quotations and citation omitted); see also Domtar, Inc. v. Niagara Fire Ins. Co., 563 N.W.2d 724, 734 (Minn. 1997) (“[A] jury’s answer to a special verdict form can be set aside only if no reasonable mind could find as did the jury.”).

This case presents a question regarding whether it is possible to reconcile the jury’s finding that the contract breach did not cause damage with the contract language specifying that Burns owes a principal amount of $2,810,459. Contract damages serve to “place the plaintiff in the same situation as if the contract had been performed.” Christenson v. Milde, 402 N.W.2d 610, 613 (Minn. App. 1987). BGD, as the party alleging breach, “has the burden to demonstrate such damages with a reasonable degree of certainty and exactness.” County of Blue Earth v. Wingen, 684 N.W.2d 919, 924 (Minn. App. 2004) (quotation omitted).

Free access — add to your briefcase to read the full text and ask questions with AI

BGD, LLC v. Stephen K. Burns, Pacer Minerals, LLC, a South Dakota Limited Liability Company, ..., (Mich. Ct. App. 2026).

BGD, LLC v. Stephen K. Burns, Pacer Minerals, LLC, a South Dakota Limited Liability Company, ... (BGD, LLC v. Stephen K. Burns, Pacer Minerals, LLC, a South Dakota Limited Liability Company, ...) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Cambern v. Hubbling
238 N.W.2d 622 (Supreme Court of Minnesota, 1976)
Christenson v. Milde
402 N.W.2d 610 (Court of Appeals of Minnesota, 1987)
Domtar, Inc. v. Niagara Fire Insurance Co.
563 N.W.2d 724 (Supreme Court of Minnesota, 1997)
Dunn v. National Beverage Corp.
745 N.W.2d 549 (Supreme Court of Minnesota, 2008)
Raze v. Mueller
587 N.W.2d 645 (Supreme Court of Minnesota, 1999)
County of Blue Earth v. Wingen
684 N.W.2d 919 (Court of Appeals of Minnesota, 2004)
McGuckin v. Harvey
225 N.W. 19 (Supreme Court of Minnesota, 1929)
Moorhead Economic Development Authority v. Anda
789 N.W.2d 860 (Supreme Court of Minnesota, 2010)
Galaxy Wireless, LLC v. Western National Mutual Insurance Company
8 N.W.3d 698 (Court of Appeals of Minnesota, 2024)