B.F. Saul Real Estate Investment Trust v. McGovern

683 S.W.2d 531, 1984 Tex. App. LEXIS 6756
CourtCourt of Appeals of Texas
DecidedDecember 5, 1984
Docket08-83-00096-CV
StatusPublished
Cited by19 cases

This text of 683 S.W.2d 531 (B.F. Saul Real Estate Investment Trust v. McGovern) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
B.F. Saul Real Estate Investment Trust v. McGovern, 683 S.W.2d 531, 1984 Tex. App. LEXIS 6756 (Tex. Ct. App. 1984).

Opinion

OPINION

WARD, Justice.

The Plaintiff, Hugh McGovern, by paying a fee of $240,000.00, obtained from the Defendant B.F. Saul Real Estate Investment Trust a standby loan commitment for $12,000,000.00 on the proposed construction of a hotel. When the project was abandoned, the Plaintiff sued to recover the $240,000.00 retained by the Trust on the theory that it was an unenforceable penalty rather than valid consideration for the loan commitment. Trial was to the court without a jury which entered judgment for the Plaintiff. Findings of fact and conclusions of law were requested and filed. We reverse and render.

The case stems from the Plaintiff's attempt to develop a first class hotel in downtown El Paso. A lender not involved in this controversy, First of Denver Real Estate Investment Trust, agreed to provide the Plaintiff with a $12,000,000.00 construction loan if the Plaintiff could find a satisfactory permanent loan commitment. The Plaintiff made an unsuccessful attempt to find such a lender. Instead, on March 29, 1974, he entered into the standby commitment with the Defendant. From a practical point, no loan would have ever been made under this $12,000,000.00 commitment. Rather, the standby commitment would have allowed construction to begin, and provided the Plaintiff more time to find an acceptable permanent loan commitment with which to pay the construction loan. It was a hedge. The Plaintiff would have wanted the traditional permanent loan since the standby loan, if made, would have required interest at the highest limit and payment within a short period of time. A traditional permanent loan would allow repayment over twenty-five to thirty years and at a more reasonable rate of interest. Though the standby commitment was made, First of Denver declined to make the construction loan for legitimate reasons which had been provided for in its own agreement. No other lender could then be found to make the construction loan.

The standby loan commitment in question as made on March 29, 1974, stated that Mr. McGovern could obtain in April, 1978, a standby loan of $12,000,000.00 provided the following conditions had been met:

*533 1. The borrower had paid $240,000.00 to the Trust for the first two years of the commitment period.
2. Commencement of construction of the proposed improvements had begun within 180 days of the date of the commitment.
3. The borrower had paid an additional $120,000.00 for the third year of the commitment period not less than thirty days prior to the expiration of the first two years.
4. The borrower had paid an additional $120,000.00 for the fourth year of the commitment period not less than thirty days prior to expiration of the third year.
5. The borrower had given at least one hundred twenty (120) days’ advance written notice of its desire to fund the standby loan during the month of April, 1978.
6. The borrower had paid as additional interest the sum of $360,000.00 not later than the first advance of funds under the standby loan.

The critical provision in the contract regarding the commencement of construction was paragraph 24(D) and was as follows:

(D) Construction of the proposed improvements shall be within 180 days after the date of the commitment or the commitment fee will be forfeited as liquidated damages to the lender and the commitment shall become void.

Mr. McGovern was unable to commence construction within the 180-day period prescribed by paragraph 24(D). By July, 1975, Mr. McGovern had abandoned his efforts to find any construction financing and at that time claimed that his inability to arrange for such financing was because the Saul Trust commitment was worthless and he demanded that the commitment be rescinded and his fee returned. The Trust refused to return the $240,000.00 commitment fee which had been paid and this litigation resulted.

The Plaintiff brought suit alleging fraud, mutual mistake, breach of warranty and unenforceable penalty. At the first trial, the jury returned a verdict rejecting each of the Plaintiffs contentions. Instead of granting judgment on the verdict, the trial judge granted a new trial. Mr. McGovern then, by stipulation, waived all of his claims except for the issue of unenforceable penalty. The parties waived a jury and proceeded to trial before the court on the one theory and with an additional stipulation that all the evidence of the first trial could be considered as part of the record of the second trial. Judgment was then entered for the Plaintiff, the court finding as a matter of law that the $240,000.00 forfeiture was an unenforceable penalty.

For all practical purposes, the facts are not in dispute since the Defendant makes only one attack on the findings of fact filed by the trial court. As previously noted, Paragraph 24(D) of the contract provided that unless construction began within 180 days of the commitment, the commitment would be void and the $240,000.00 would be forfeited as liquidated damages. The trial court found that construction did not begin within the 180 days and the Defendant’s fifth point is a factual insufficiency attack on this finding. In the second trial, Mr. McGovern offered no evidence in support of his claim but rested immediately after his attorney’s opening statement. In the first trial, Mr. McGovern took the position and offered evidence to the effect that construction did in fact begin. What the Defendant overlooks is that in the first trial, the Defendant undertook to prove and did provide evidence that construction did not commence within 180 days of the commitment. As an example, Mr. Cronin, an expert witness for the Defendant, testified at the first trial that from his investigation, construction had not started on time. Having reviewed all of the evidence on this matter together with the inferences arising therefrom, the fifth point is overruled.

Points of Error Nos. One through Four advance essentially the same argument. The Defendant contends that the $240,-000.00 was valid consideration for holding *534 open the loan commitment, not a penalty as the trial court found. That argument requires examination of the consideration provisions of the contract. When the parties agreed to the loan commitment on March 29, 1974, the Plaintiff paid the Defendant $240,000.00 to hold the commitment open until April, 1976. The standby loan could only be made, however, in April, 1978. To keep the commitment alive from April, 1976, to April, 1978, an additional payment of $120,000.00 was required for each of the two twelve-month periods. Further fees and notice were required if the Plaintiff ever actually called on the Defendant to make the loan.

The Plaintiffs argument that Special Provision 24(D) of the standby commitment provided for an unenforceable penalty rather than liquidated damages is based on the premise that this ease is controlled by Stewart v. Basey, 150 Tex. 666, 245 S.W.2d 484 (1952).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SCHUYLER CO-OP. ASS'N v. Sahs
755 N.W.2d 802 (Nebraska Supreme Court, 2008)
Berens & Tate v. Iron Mt. Info. Mgmt.
747 N.W.2d 383 (Nebraska Supreme Court, 2008)
Kelly v. Gaines
181 S.W.3d 394 (Court of Appeals of Texas, 2005)
Roger Kelly v. Russell Gaines
Court of Appeals of Texas, 2005
In Re Rally Partners, L.P.
306 B.R. 165 (E.D. Texas, 2003)
William A. McIntosh v. State
Court of Appeals of Texas, 2002
Michael T. Castaldo v. State
Court of Appeals of Texas, 2000
Casa El Sol-Acapulco, S.A. v. Fontenot
919 S.W.2d 709 (Court of Appeals of Texas, 1996)
Valdina Farms, Inc. v. Brown, Beasley & Associates, Inc.
733 S.W.2d 688 (Court of Appeals of Texas, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
683 S.W.2d 531, 1984 Tex. App. LEXIS 6756, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bf-saul-real-estate-investment-trust-v-mcgovern-texapp-1984.