Beuttas v. United States

122 Ct. Cl. 295, 1952 U.S. Ct. Cl. LEXIS 101, 1952 WL 5940
United States Court of Claims·Decided May 6, 1952·No. Nos. 47866, 47867, 47868·Published

Opinion

MaddeN, Judge,

delivered the opinion of the court:

The plaintiffs in these three cases are members of a partnership which has been engaged in the construction and contracting business for some thirty-seven years. They made three separate contracts with the Government, through its Federal Public Housing Authority, to build three war housing projects. Each of the three contracts is the basis for one of the instant suits.

Each contract was awarded after competitive bidding which the Government had invited. Its invitations to the plaintiffs and others had included instructions to bidders, the specifications for the proposed project, and the form of the proposed contract. Paragraph 13 of the instructions to bidders contained the following language:

The attention of the contractor is directed to * * * Executive Order 9301 (8 Fed. Beg. 1825) and to the regulations and directives, if any, issued under such [327] Executive Order by tbe War Manpower Commission or the Chairman thereof.

Article 11, paragraph (d) of the Form of Contract included in the invitation contained the following language:

* * * This contract is subject to Executive Order 9301, Establishing a Minimum Wartime Workweek of Forty-eight Hours, and to the regulations and directives, if any, issued under such Executive Order by the War Manpower Commission or the Chairman thereof.

Executive Order 9301, quoted in our Finding 7, provided in effect that an employer would not be regarded as making the most effective utilization of his manpower if he worked his employees less than forty-eight hours per week. The order expressly provided, however, that statutes and labor agreements providing for premium pay of time and one-half for work in excess of a specified workweek should not be affected by the order. The plaintiffs learned of Executive Order 9301 shortly after it was issued on February 9, 1943. As we have seen, they were also expressly advised of it in the Government’s invitation for bids.

The contract involved in No. 47866 related to the Hebble Homes project at Fairfield, Ohio, which was in the Dayton area. The invitation for bids was issued March 1, 1943. The plaintiffs submitted their bid on March 18. The contract was awarded to them and was dated March 30. On that day they were instructed to proceed immediately with the work.

The contract involved in No. 47867 related to the Ardella Homes project at Akron, Ohio. The invitation for bids was issued March 9, 1943; the plaintiffs entered their bid on March 19; the contract was awarded to them and was dated March 30, and on April 2 they were instructed to begin the work on April 5.

The contract involved in No. 47868 related to the SouthEast Homes project at Akron, Ohio. The invitation for bids was dated March 29,1943; the plaintiffs entered their bid on April 8; the contract was awarded to them and was dated April 19, and on April 28 they were instructed to begin the work on May 1.

[328] When Joseph H. Beuttas, the partner who acted for the plaintiffs in executing the contracts, went to the Regional Office of the Federal Public Housing Authority in Cleveland, Ohio, on March 30,1943, to sign the formal contracts for the Hebble Homes and the Ardella Homes projects, he raised a question as to the inclusion of the reference to Executive Order No. 9301 in the contract. It would seem that he had no basis for objection, since the proposed contract for which he and his competitors, if any, had bid, expressly provided that the contract should be subject to it. But, regardless of the full notice which he had, he had computed his bid on these two projects on the basis of a 40-hour week, and had included no item for possible Saturday overtime. A discussion ensued between him and the agent of the Government who was presenting the contracts to him for signature but who was not a contracting officer.

On March 15, 1943, the Washington office of the Federal Public Housing Authority had notified its Regional Offices that thereafter no express mention of Executive Order No. 9301 should be made in contracts for housing; that the order had the force of law which contractors should be deemed to have knowledge of without express mention. The Government’s agent, after consultation with superiors, told Mr. Beuttas that it did not make any difference whether Executive Order 9301 was mentioned in the contract or not since it had the force of law; that it did not make any difference anyway because Akron was not in the War Manpower shortage area. By the last statement he meant, as the parties understood, that the War Manpower authorities had not yet, at that time, issued the necessary local orders requiring employers in the Akron area to put the forty-eight hour week into effect. He thereupon caused to be added to the contract an addendum stating that references in the contract to Executive Order 9301 were deleted.

The plaintiffs urge that the deletion by the Government’s agent of a provision of the contract burdensome to the plaintiffs, at the plaintiffs’ request, shows that it was the intention of the parties to modify the contract by relieving the plaintiffs of the obligation which would have been, imposed by the deleted provision. Assuming that the deleted provision was [329] a contractual obligation and nothing more, and that the person who made the deletion had the authority from his principal to modify the contract, the deletion would normally have the effect which the plaintiffs urge. In the instant case there are, however, several other circumstances which must be considered.

Free access — add to your briefcase to read the full text and ask questions with AI

Beuttas v. United States, 122 Ct. Cl. 295, 1952 U.S. Ct. Cl. LEXIS 101, 1952 WL 5940 (cc 1952).

122 Ct. Cl. 295 (Beuttas v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

E. & F. Construction Co. v. United States
89 F. Supp. 541 (Court of Claims, 1950)
John A. Johnson Contracting Corp. v. United States
98 F. Supp. 154 (Court of Claims, 1951)