Bethlehem Steel Corp. v. Tishman Realty & Constr. Co.

72 F.R.D. 33, 1976 U.S. Dist. LEXIS 13969
CourtDistrict Court, S.D. New York
DecidedJuly 23, 1976
DocketNo. 75 Civ. 511(MP)
StatusPublished
Cited by9 cases

This text of 72 F.R.D. 33 (Bethlehem Steel Corp. v. Tishman Realty & Constr. Co.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bethlehem Steel Corp. v. Tishman Realty & Constr. Co., 72 F.R.D. 33, 1976 U.S. Dist. LEXIS 13969 (S.D.N.Y. 1976).

Opinion

OPINION

POLLACK, District Judge.

This is a diversity suit involving a claim for the recovery by the plaintiff, a subcontractor, of moneys due from the defendant, a builder, under five separate subcontracts entered into between the parties pertaining to construction of two forty-four story office buildings, a subterranean garage and an entertainment center in Los Angeles, California, called the California Theme Towers Project.

Defendant (hereafter “Tishman”),1 moves pursuant to Rules 1 and 12, Fed.R.Civ.P., to stay this action pending a determination of five subsequently commenced suits brought by plaintiff against Tishman in California Superior Court for the County of Los Angeles allegedly seeking identical relief as that sought in this action on the same construction subcontracts that are at issue here. In the alternative, Tishman, pursuant to Rule 42(a), Fed.R.Civ.P., seeks consolidation for purposes of pre-trial discovery and trial of the common issues in this action with those in a separate suit it has filed in this Court against the owners of the construction project involved here. Tishman Reaity & Construction Co., Inc. v. Delta Towers Joint Venture, 72 F.R.D. 30, Dkt. No. 76-714, (S.D.N.Y., July 23, 1976). As a final alternative motion, it asks that the owners of the project be impleaded in this action as third party defendants.

Plaintiff (hereafter “Bethlehem”),2, the subcontractor responsible for providing and erecting steel for the project, opposes a stay of this action and cross-moves for partial [35]*35summary judgment in the amount of $3,483,881.81 as an admitted contract balance on the largest of the five subcontracts that form the basis of this action.

The defendants in the companion case in this Court (hereafter “the owners” and “the second action”)3 seek a stay of that action pending the same California litigation.

After wading through the flood of supporting and opposing papers, several inches thick, and for the reasons that appear below, the Court has determined that a stay of this case may be had on condition that Tishman post security as indicated hereafter; and that partial summary judgment will be withheld, without prejudice to renewal on proper papers. The Court also holds in Tishman’s suit against the owners that the same will be stayed pending a determination of the California actions previously mentioned. As a result, Tishman’s motions for consolidation and impleader need not be reached.

I.

The California Theme Towers Project was commenced in 1969 and not completed until October of 1975.

The complaint herein (filed February of 1975) contains six claims, four of which seek moneys allegedly due Bethlehem for extra and additional work done pursuant to four subcontracts with Tishman. Those subcontracts called for the fabrication and erection of reinforcing steel in the Theme Towers complex. Bethlehem asserts that the extra and additional work on this reinforcing steel was caused by defective specifications in plans called for under the prime contract between Tishman and the owners, plans for which Bethlehem was not responsible.

The fifth and sixth claims in the complaint involve an alleged fifth subcontract for the fabrication and erection of structural steel, a subcontract which is unsigned and the terms of which remain at least partially undetermined. The better part of the damages sought by Bethlehem result from the alleged breach of this subcontract and are sought under the fifth and sixth claims. In the fifth claim, plaintiff sues on an alleged subcontract directly, claiming it is owed a contract balance of $3,483,811.81 and extra and additional work payments totalling $801,153.45. Under a quasi-contractual theory, the same damages are sought in the sixth claim as payments for work done and goods sold and delivered. In its crossmotion here, Bethlehem seeks partial summary judgment, apparently on the contract theory set out in the fifth claim, for the contract balance of $3,483,811.81.

In its initial answer, Tishman admitted that it ordered extra and additional work under the five subcontracts but denied liability and asserted that previous payments to Bethlehem comprise all the payment required under the subcontracts. As affirmative defenses going to Bethlehem’s first claim, Tishman contended that by failing to make timely demand for extra and additional work payments Bethlehem waived and is estopped from asserting the right to such payments.

In this initial answer, Tishman also asserted a counterclaim for backcharges alleging that all extra and additional work was caused by Bethlehem’s defective performance and failure to meet progress schedules. On this and previous motions, Tishman has heatedly and persistently contended that it was an innocent party with respect to the delays and extra and additional work that apparently plagued the [36]*36project; i. e., that such problems were caused either by Bethlehem’s alleged defective performance or the owner’s allegedly defective plans.

In June of 1975, Bethlehem commenced the five separate actions in Los Angeles County Superior Court, mentioned above, seeking the same relief against Tishman that is sought in this suit and also naming Prudential, Delta Towers, Lot 8 and PIC Realty Corporation as defendants. These actions were brought to foreclose Bethlehem’s mechanic’s liens on the real property on which the project rests. The filing of the California suits was timed to avoid the bar of California’s statute of limitations on the claims. This Court has been advised that virtually all parties involved in the various construction project disputes, including the Michigan architects over whom this Court would apparently have no jurisdiction, have joined in the California suits. In addition, another Tishman subcontractor, Federal Steel Corporation, has also commenced mechanic’s lien actions in Los Angeles Superior Court4 and two other Tishman subcontractors have filed actions in Los Angeles Superior Court. One such action, by Western Air & Refrigeration, Inc., has been settled, but the other, by Berg Electric Corporation, remains active.

In June of 1975, Tishman sought transfer of this action to the federal district court of the Central District of California pursuant to 28 U.S.C. § 1404(a). After granting a number of continuances requested by the parties, the motion was heard and denied. Bethlehem Steel Corp. v. Tishman Realty & Construction Co., Inc., 404 F.Supp. 1285 (S.D.N.Y.1975).

Then, in January of this year, Tishman moved to implead the owners and to amend its answer to Bethlehem’s complaint in various respects. The impleader motion was denied, but the Court noted that Tishman was at liberty to commence a separate action and subsequently move for consolidation. Leave to move again for impleader was granted in the event that such a consolidation motion was denied. In February of this year Tishman filed the above-described companion case against the owners.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Boyertown Oil Co. v. Osan Manufacturing Co.
514 A.2d 938 (Superior Court of Pennsylvania, 1986)
Rattner v. BD. OF TRUSTEES OF VILLAGE OF PLEASANTVILLE
611 F. Supp. 648 (S.D. New York, 1985)
Companion Life Insurance v. Matthews
547 F. Supp. 836 (S.D. New York, 1982)
Chemetron Corp. v. Cervantes
92 F.R.D. 26 (D. Puerto Rico, 1981)
Maldonado v. Flynn
477 F. Supp. 1007 (S.D. New York, 1979)
Henry Rosenfeld, Inc. v. Himar Sales Corp.
460 F. Supp. 640 (S.D. New York, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
72 F.R.D. 33, 1976 U.S. Dist. LEXIS 13969, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bethlehem-steel-corp-v-tishman-realty-constr-co-nysd-1976.