Bethlehem Steel Corp. v. Pennsylvania Public Utility Commission

680 A.2d 1203, 1996 Pa. Commw. LEXIS 290
CourtCommonwealth Court of Pennsylvania
DecidedJuly 12, 1996
StatusPublished
Cited by2 cases

This text of 680 A.2d 1203 (Bethlehem Steel Corp. v. Pennsylvania Public Utility Commission) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bethlehem Steel Corp. v. Pennsylvania Public Utility Commission, 680 A.2d 1203, 1996 Pa. Commw. LEXIS 290 (Pa. Ct. App. 1996).

Opinions

NARICK, Senior Judge.

Bethlehem Steel Corporation (Bethlehem), Energy Pipeline Corporation (Pipeline), Energy Production Company (Production), Union Drilling, Inc., New Jersey Natural Resources Company and Bessie 8 (Petitioners, collectively) appeal from an order of the Pennsylvania Public Utility Commission (PUC) reversing the decision of Administrative Law Judge (ALJ) James D. Porterfield and ordering Petitioners to file an application for a certificate of public convenience. The single issue for our disposition is whether the PUC erred in holding that Petitioners were subject to its jurisdiction because they engaged in providing a public utility service to or for the public. The relevant facts are as follows.

Until 1982, Production produced and sold natural gas to various interstate pipelines and to local distribution companies. However, in late 1982, Production’s traditional customers began to decrease their gas purchases, causing Production to find alternative markets in commercial and industrial end-users. To this end, Production contacted numerous potential customers within a twenty-mile radius of Production’s leasehold interests in Indiana County, and eventually, Production entered into discussions with Bethlehem about providing natural gas service to its Johnstown plant. The discussions with Bethlehem culminated in the execution of a gas sales contract between Production and Bethlehem. The gas was to be delivered by pressurized trucks, but due to unforeseen difficulties, no gas was ever delivered under this agreement.

Subsequently, the owners of Production formed a new corporation, Pipeline, and both companies entered into a new agreement with Bethlehem (Bethlehem Agreement) on January 26, 1984, and amended January 3, 1985. Under the terms of this contract, Production would provide natural gas for Bethlehem’s Johnstown plant, and Pipeline would make its best efforts to construct a pipeline for transporting the natural gas from the gas fields directly to the Johnstown plant. Bethlehem provided some of the financing for the construction of the pipeline.

By agreement of June 7, 1984, a joint venture, called Bessie 8, was formed in order to raise capital for the pipeline project. The venturers included Production, Pipeline, Union Drilling, Inc. and New Jersey Natural Resources Co. Bessie 8 successfully capitalized the project, and by February, 1985, the twenty-one mile pipeline was completed and gas was flowing. Neither Production nor Pipeline applied for a certificate of public convenience to operate the pipeline. Shortly thereafter, Frank Ross, the president of Production, offered to provide the same service to Anchor Glass Container Corporation (Anchor Glass), using the Bessie 8 project as a model. However, no further action was taken on the matter.

Approximately nine months later, Peoples’s Natural Gas (PNG) filed a complaint against Bessie 8 and the individual venturers alleging that Petitioners’ provision of natural gas services was in violation of Section 1101 of the Public Utility Code, 66 Pa.C.S. § 1101, which requires that any proposed public utility obtain a certificate of public convenience before lawfully beginning to offer, render, furnish or supply public utility service within the Commonwealth.

Petitioners admit that they are providing uncertificated service to Bethlehem’s Johns-town plant, but they deny they are subject to PUC jurisdiction, because they are not a public utility. Section 102 of the Public Utili[1205]*1205ty Code1 defines “public utility” in pertinent part as follows:

(1) Any person or corporations now or hereafter owning or operating in this Commonwealth equipment or facilities for:
(1) Producing, generating, transmitting, distributing or furnishing natural or artificial gas, electricity, or steam for the production of light, heat, or power to or for the public for compensation.
(v) Transporting or conveying natural or artificial gas ... by pipeline or conduit, for the public for compensation.
(2) The term public utility does not include:
(i) Any person or corporation, not otherwise a public utility, who or which furnishes service only to himself or itself.
(iii) Any producer of natural gas not engaged distributing such gas directly to the public for compensation.

The ALJ held that because the natural gas production and the transportation facilities of the Bessie 8 joint venture were exclusively dedicated, by contract, to the use of Bethlehem’s Johnstown works, and because the entire Bessie 8 system contained no interstate pipeline connections, no intrastate pipeline connections, no public utility connections, nor any connections or sources of gas other than Pennsylvania native field production, the service was private in nature.

In contrast, the PUC ruled that the Bessie 8 pipeline was a public utility. The PUC cited Production’s wide solicitation efforts, prior to entering into a contract with Bethlehem, apparently designed to obtain industrial customers, as well as their successful effort to get a customer, Bethlehem, and then the later solicitation of Anchor Glass, after the pipeline was completed, as evidence that they held themselves out as a public utility.2 Moreover, the PUC also found that the facts in the PUC case, Equitable Gas Co. v. Dane Baird, Dane Baird Investments, Inc., and PFP Pipeline Co. (Dane Baird, President), Docket No. C-844525 (Pa.P.U.C. September 4, 1985), were strikingly similar to those in the present case. In Dane Baird, the PUC held that the pipeline company, although having only one customer, was providing a public utility.

Under Section 335 of the Code, 66 Pa.C.S. § 335, the PUC is the ultimate fact-finder, weighing evidence and resolving conflicts in testimony. Pennsylvania Electric Co. v. Pennsylvania Public Utility Commission, 81 Pa.Cmwlth. 285, 473 A.2d 704 (1984). The scope of appellate review in PUC cases is limited to a determination of whether constitutional rights have been violated, an error of law has been committed, or the Commission’s findings and conclusions are not supported by substantial evidence. Barasch v. Pennsylvania Public Utility Commission, 507 Pa. 430, 490 A.2d 806 (1985). Whether the PUC correctly applied the legal standard for determining whether a utility serves the public and is subject to PUC jurisdiction, is a question of law, subject to plenary review. Wattman v. Pennsylvania Public Utility Commission, 142 Pa.Cmwlth. 44, 596 A.2d 1221 (1991), affirmed without opinion, 533 Pa. 304, 621 A.2d 994 (1993).

[1206]*1206There is no bright line rule for determining whether a utility is providing public utility service. However, a number of cases are helpful in specifying the criteria which are important in making this determination. In Drexelbrook Associates v. Pennsylvania Public Utility Commission, 418 Pa. 430, 212 A.2d 237

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Borough of Olyphant v. Pennsylvania Public Utility Commission
861 A.2d 377 (Commonwealth Court of Pennsylvania, 2004)
Energy Pipeline, Inc. v. Public Utility Commission
726 A.2d 1128 (Commonwealth Court of Pennsylvania, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
680 A.2d 1203, 1996 Pa. Commw. LEXIS 290, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bethlehem-steel-corp-v-pennsylvania-public-utility-commission-pacommwct-1996.