Bethlehem Shipbuilding Corp. v. West & Dodge Co.

10 F.2d 289, 1926 U.S. App. LEXIS 2200
CourtCourt of Appeals for the First Circuit
DecidedJanuary 26, 1926
DocketNo. 1851
StatusPublished
Cited by2 cases

This text of 10 F.2d 289 (Bethlehem Shipbuilding Corp. v. West & Dodge Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bethlehem Shipbuilding Corp. v. West & Dodge Co., 10 F.2d 289, 1926 U.S. App. LEXIS 2200 (1st Cir. 1926).

Opinion

JOHNSON, Circuit Judge.

The Bethlehem Shipbuilding Corporation, Limited, hereinafter called Bethlehem, having entered into a written contract with the United States to construct for it torpedo boat destroyers on a cost plus profit basis, on December 11, 1917, gave to the West & Dodge Company, hereinafter called West & Dodge, purchasing orders for oil burners, oil burner air cones, and oil burner holders for 40 boats, at a price of $3,300 for each boat, in accordance with the latter’s proposal, subject to the approval of the Compensation Board created by the Navy Department.

West & Dodge delivered, all of the equipment called for, and has received pay for that furnished for 35 boats.

In this action of contract it seeks to. recover the amount due for the equipment furnished for the remaining five boats at the rate of $3,223 per boat, which it claims was the amount approved by the Compensation Board, and which Bethlehem had notified it that it would pay.

The ease has been here twice before — the first time upon a demurrer to the defendant’s answer, and the case was remanded to the District Court in order that the .defendant might, if it saw fit, amend its'answer so as to include as a defense that the approval of the Compensation Board was obtained by a fraudulent representation.

The answer was so amended, and the ease came on for trial before a jury in the District Court, where a verdict was directed for the plaintiff, because, in the opinion of the presiding judge, there was no evidence that the Compensation Board had knowledge of the fraudulent representation alleged to have been made. This court held, however, that there was evidence which would warrant a jury in finding that the approval of the Compensation Board was obtained by a fraudulent representation, and reversed the judgment of the court below. A jury has now returned a verdict for the plaintiff, and the case has been brought here upon a writ of error by the defendant.

When the ease was first before this court, it was held that, although the contract between the United States government and the Bethlehem was one on a cost plus profit basis, this provision did not apply to subcontracts made by it, and therefore not to the contract with West & Dodge.

The issue of whether there was a fraudulent representation made by West & Dodge, which induced the Compensation Board to give its approval to the contract price of $3,223 per boat, has now been passed upon [291]*291by a jury, and a verdict returned for the plaintiff.

The errors assigned are: The denial of the defendant’s motion for a directed verdict; the refusal to give certain instructions; the admission of evidence and statements made by counsel for the plaintiff in addressing the jury in his closing argument.

If there was any evidence which would sustain a verdict for the plaintiff, the request for a directed verdict was properly refused.

The evidence discloses that, while, under the terms of the contract between Bethlehem and the government, the price to be paid by it under its contract with West & Dodge for the equipment which the latter was to furnish was to be approved by the Compensation Board, and West & Dodge were requested by Bethlehem to submit a statement of the cost of the equipment which it had contracted to furnish, that it had negleeted to do so, because it had been unable to ascertain the cost with any degree of accuracy.

The president of West & Dodge testified that his company was a small one, employing about 25 men, and that, because .of this contract, it was necessary to enlarge the number of its employees to about 150, to purchase additional tools and machinery and acquire another plant; that it was also engaged in the performance of other work at the time work was being pushed upon the equipment for these destroyers; that it was difficult to separate the cost which should be allocated to the equipment for the burners; that the work was being pushed day and night, Sundays included, and the furnishing of any detailed statement of costs was impossible. Upon repeated requests from Bethlehem to furnish such a statement,- West & Dodge, under (late of March 4, 1918, stated in a letter to Bethlehem:

“The cost of these oil burners, so far as we have been able to judge, is about 85 per cent, of the price we quoted you.”

In reply to this statement, West & Dodge received from Bethlehem, March 6, 1918, a letter in which Bethlehem stated:

“As you have been informed in previous correspondence, before the prices appearing in these orders will be approved by the Compensation Board it will be necessary for you to furnish a detailed cost statement justifying the prices quoted. If fabrication has not proceeded sufficiently far to permit of such a statement, a detailed estimate of costs should be submitted for the board’s consideration”— and stating in substance that, until the government’s wishes were complied with, price approval would not be forthcoming, and therefore it would be impossible to pass the invoices rendered for payhient until such approval, and that it therefore would be much to the advantage of West & Dodge to expedite the submission of a cost statement in every way possible. After the receipt of this letter, the president of West & Dodge had an interview with H. P. Readmon, assistant to the purchasing agent of Bethlehem, in which he testified that he told Mr. Readmon that it was impossible for him to give the costs, due to the tremendous volume of business of his company and its limited bookkeeping department; that Readmon said that there was another concern that was building the same kind of a burner; that its accounts had been audited and the Compensation Board was satisfied that $8,223 was a good fair price, and had approved it; and that he then told Mr. Readmon that he would be willing to take the contract for the whole business for $3,223 per boat.

Bethlehem secured the approval of a tentative price of $3,223 per boat in connection with material which had already been shipped and invoiced by West & Dodge, and so informed the latter, but still called for a statement showing the cost of equipment of at least one boat. In reply to this, West & Dodge wrote Bethlehem, under date of April 2, 1918, in part, as follows:

“In connection with furnishing the cost statements which has been the subject of previous correspondence between us, we beg to advise that we have still been unable to get these in shape, owing to a change in our bookkeeping department and pressure 'of business; but we would be willing, as we have already explained to Mr. Readmon, taking into consideration the number of boats we are now working on, to suggest that we make a flat rate of $3,223 per boat on all of the orders above mentioned, provided the necessary approval could be abtained at once, and we could have the assurance that our bills for this amount would be approved and remitted for promptly, so that we would not be delayed in going ahead. Will you accordingly submit this proposition to the necessary authorities and advise us at once.”

Upon the orders covered by the contract in suit, Bethlehem obtained, on April 13, 1918, approval of the cost inspector acting under the direction of the Compensation Board, as follows:

“It being understood that the subcontractor is. willing to accept a price of $3,223 per [292]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Khalid v. Microsoft Corporation
W.D. Washington, 2019
Fidelity & Casualty Co. of New York v. Niemann
47 F.2d 1056 (Eighth Circuit, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
10 F.2d 289, 1926 U.S. App. LEXIS 2200, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bethlehem-shipbuilding-corp-v-west-dodge-co-ca1-1926.