Bethlehem Shipbuilding Corp. v. West & Dodge Co.

285 F. 474, 1922 U.S. App. LEXIS 1985
CourtCourt of Appeals for the First Circuit
DecidedDecember 18, 1922
DocketNo. 1548
StatusPublished

This text of 285 F. 474 (Bethlehem Shipbuilding Corp. v. West & Dodge Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bethlehem Shipbuilding Corp. v. West & Dodge Co., 285 F. 474, 1922 U.S. App. LEXIS 1985 (1st Cir. 1922).

Opinion

BINGHAM, Circuit Judge.

This is an action of contract brought by the West & Dodge Company against the Bethlehem Shipbuilding Corporation and is defended by the United States as the sole party in interest. There was a trial by jury in the Massachusetts District Court and a verdict directed for the plaintiff upon which judgment was entered for $19,133.57, with costs of suit, and this writ of error was brought by the defendant.

In its declaration the plaintiff alleges that it made a contract with the defendant by which it agreed to furnish certain oil burners, oil burner air cones, and oil burner holders for thq equipment of 40 boats and the defendant was to pay therefor the Sum of $3,223 per boat; that the plaintiff made and delivered the parts in accordance with the terms of the contract, but the defendant, though it paid for the parts for 35 boats, neglected and refused to pay for the parts for the remaining 5 boats, and owed the plaintiff therefor the sum of $16,115, plus interest from January 22, 1919, when said sum became due and payable.

In its amended answer the defendant admitted the making of the contract for the burners, etc., at the rate of $3,223 per boat, the manufacture and delivery of the burners, the payment of a sum equivalent to full payment under .the contract for burners for 35 boats and its refusal to pay the balance of the claim. And for further ariswer it alleged that it made a contract with the United States whereby it was to construct for the United States 40 torpedo boat destroyers on the cost plus basis; that the oil burners, etc., were ordered and used by the defendant in the construction of said 40 torpedo boat destroyers; that the plaintiff at all times knew that the oil burners called for by the contract were to be used in the 40 torpedo boat destroyers; and that by the express terms of each of said contracts the price payable to the plaintiff for the oil burners, etc., was subject to the determination of the Compensation Board, an agency of the United States constituted as provided in the contract between the United States and the defendant.

And further answering the defendant alleged that previous to the contract in question it had made three contracts with the United States for the construction of torpedo boat destroyers and received from the plaintiff proposals for oil burners, etc., similar in all respects to the oil burners sued for, at the price of $3,300 per boat for two of said contracts, and $3,350 per boat for the third contract and the contract mentioned in the plaintiff’s declaration; that all of said contracts were as to price subject to the approval of the Compensation Board, the plaintiff well knowing that said oil burners were to be used in said torpedo boat destroyers; that the contracts or orders having been approved, ex» [476]*476cept as to price, the defendant, at the instigation of the Compensation Board, repeatedly called on the plaintiff to furnish for the Compensation Board information as to the cost of the manufacture of the oil burners; that, the information not being forthcoming, the plaintiff, on being further pressed for the cost data, stated that the cost of the manufacture of the oil burners, as far as the plaintiff was able to judge, was about 85 per cent, of the price quoted in the plaintiff’s proposal to the defendant; that later the defendant, in response to the plaintiff’s request for remittances on account of the work delivered, procured the approval of a tentative price of $3,223 per boat in connection with the material already shipped; that thereafter the plaintiff requested the defendant to submit to the Compensation Board a proposal that it would accept $3,223 per boat for the burners under all four contracts; that the defendant, as requested, submitted the proposal, and that -the board, under date of April 13, 1918, approved the same; that the plaintiff, in submitting said proposal, intended to represent to the Compensation Board that the price of $3,223 for the oil burners was a fair and reasonable price, based upon the cost of manufacture, and die! not include any unreasonable or exorbitant profit; that the Compensation Board relied on said representation, and in consequence of said reliance approved the price; that the representation was false, and that the price included a grossly unfair, unreasonable, and exorbitant profit to the plaintiff over and above the cost of manufacture; and the defendant further alleged that in consequence of said false representation the action of the Compensation Board in approving the price was void and of no effect, and was not binding on the defendant.

At the close of all the evidence the court instructed the jury to return a verdict for the plaintiff for the amount claimed, on the ground that the defense of fraud had not been made out, as there was no evidence on which a finding could be made that the letter of March 4, hereafter discussed, ever came to the attention of the Compensation Board and influenced its action in approving the price of $3,223; and the question raised by the defendant’s assignment of error is whether there was any evidence submitted at the trial from which the jury would have been warranted in finding that the plaintiff, in seeking the approval of a price of $3,223 per boat for the oil burners, represented that the cost of production was such that the price proposed would give only a fair profit, and influenced the board in approving the same.

The evidence showed that the defendant, on December 6, 1917, entered into a contract with the United States for the construction of 40 torpedo boat destroyers to be built at the defendant’s Union plant at San Francisco, Cal.; that in said contract it was provided that the government should pay the cost of the work, and in addition thereto a lump sum as compensation to the contractor; that provision therein was made for a Compensation Board, whose duty it was to ascertain, estimate, and determine the actual cost of the work stipulated in that contract ; that it also contained the following:

“The contractor shall use every endeavor to. obtain the material, machinery, equipment, appurtenances, supplies, etc., under this contract at the lowest possible prices, and shall in no ease knowingly pay higher prices than arerequiréd by the existing market conditions nor higher prices than are or [477]*477would lb© paid for similar materials, etc., purchased at the same time and under like circumstances and conditions for other work in progress in the yard. Specifications and guaranties of all materials, machinery, and equipment, and the agreements under which such are purchased shall he subject to the approval of the department, and orders, prices and awards shall he subject to the approval of the Compensation Board.”

This contract with the government was authorized under the Acts of Congress approved March 4, 1917 (39 Stat. 1168), and October 6, 1917 (40 Stat. 371, 383), in the former of which it was provided that—

“No purchase of structural steel, ship plates or machinery shall be made at a price in excess of a reasonable profit above the actual cost of manufacture.” 39 Stat. 1195.

It also appeared that on December 11, 1917, the defendant, through its Union Iron Works Company, placed an order with the plaintiff for oil burners, oil burner air cones, and oil burner holders for 40 boats in accordance with specifications forwarded with a previous order No.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
285 F. 474, 1922 U.S. App. LEXIS 1985, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bethlehem-shipbuilding-corp-v-west-dodge-co-ca1-1922.