Bethlehem Shipbuilding Corp. v. West & Dodge Co.

269 F. 100, 1920 U.S. App. LEXIS 1811
CourtCourt of Appeals for the First Circuit
DecidedDecember 1, 1920
DocketNo. 1467
StatusPublished

This text of 269 F. 100 (Bethlehem Shipbuilding Corp. v. West & Dodge Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bethlehem Shipbuilding Corp. v. West & Dodge Co., 269 F. 100, 1920 U.S. App. LEXIS 1811 (1st Cir. 1920).

Opinion

JOHNSON, Circuit Judge.

Judgment was rendered against the plaintiff in error, hereinafter called the 'defendant, in the District Court of the United States for the District of Massachusetts, in an action brought against it by the defendant in error, hereinafter called the plaintiff, to recover the price which had been fixed hy the Compensation Board of the Navy Department for oil burners, oil burner cones, and oil burner holders for five torpedo boat destroyers which had been delivered in accordance with the defendant’s order. The plaintiff filed a demurrer to the defendant’s answer, which was sustained by the District Court, and this is assigned as error.

The following facts are admitted by the answer:

The defendant, on the 6th day of December, A. D. 1917, entered into a written contract with the United States to construct for it 40 torpedo boat destroyers at San Francisco and Alameda, Cal.

The contract was authorized by the Naval Appropriation Act of March 4, 1917 (39 Stat. 1195), and by the Urgent Deficiency Act of October 6, 1917 (40 Stat. 345). The former act contains the following provision:

"No purchase of structural steel, ship plates, or machinery shall be made at a price in excess of a reasonable profit above the actual cost of manufacture.”

The contract provided that the government should pay for the vessels upon a cost plus profit basis, but that the total profit to be paid to the defendant for each tjoat was not to exceed $135,000, if its actual cost should equal or exceed the estimated cost of $1,500,000, and should the actual cost be less than the estimated cost the defendant was to be allowed as his profit, in addition to $135,000 on each boat, one-half the amount by which the actual cost of each fell short of the estimated cost.

It also provided that a compensation board, created by the Navy Department, should ascertain, estimate, and determine the actual cost of each boat, and that it should also approve orders, prices, and awards made by the defendant for materials, machinery, and equipment under the following provision:

“The contractor shall use every endeavor to obtain the materials, machinery, equipment, appurtenances, supplies, etc., under this contract at the lowest possible prices, and shall in no case knowingly pay higher prices than required by the existing market conditions nor higher prices than are or would be paid for similar materials, etc., purchased at the same time and under like circumstances and conditions for other work in progress in the yard. Specifications and guaranties of all materials, machinery and equipment, and the agreements under which such are purchased shall be subject to the approval of the department, and orders, prices, and awards shall be! subject to the approval of the Compensation Board.”

[102]*102Another provision authorized the contractor to place special contracts for any parts or materials on a cost plus profit basis.

The defendant ordered from the plaintiff oil burners, oil burner air cones, and oil burner holders at the price of $3,350 per boat, “subject to the approval of the Compensation Board.”

The Compensation Board took up with the plaintiff the matter of price, and procured a reduction from $3,350 to $3,223 per boat, and upon April 13, 1918, sent the following communication to the defendant :'

“April 18, 1918.
“To Bethlehem Shipbuilding Corporation, Fore River Plant, Quincy, Mass.
“Subject: Purchase Order F-1211-17 on West & Dodge for Oil Burners.
“1. It being understood that the subcontractor is willing to accept a price of $3,223 per boat for oil burners covered by the above order, this office herewith gives formal approval of the above order at that price, $3,223 per boat.
“W. R. Main, by direction.”

On April 16, 1918, the defendant sent the following communication to the plaintiff:

“April 16, 1918.
“West & Dodge Company, 167 Oliver Street, Boston, Mass.—Gentlemen: We are pleased to advise you that we are authorized to make final award of Union Plant’s purchase order F-1211-17 by the Compensation Board, Navy Department, Washington, D. C., and that you may proceed with this order at $3,223.00 per boat.
“Very truly yours, Bethlehem Shipbuilding Corp’n, Ltd.
“By H. P. Readmon, Acting Purchasing Agent.”

The plaintiff delivered to the defendant the oil burners, oil burner, cones, and oil burner holders called for by the above order for 40 destroyers, and was paid by the defendant for all that it furnished for 35 at the price which had been approved by the Compensation Board.

On or about March 1, 1919, subsequent to the delivery by the plaintiff of the oil burner equipment for all the destroyers, and the payment by the defendant for all that had been furnished for 35, the defendant was notified by the Navy Department that it had investigated the plaintiff’s cost of manufacturing this oil equipment, and that the price of $3,223 per boat was in excess of a reasonable profit above its cost, and that it rescinded its approval of this price, and gave its approval for the price of $1,915 per boat, plus the sum of $267.95, the cost of ■certain bronze castings for each.

In substance the answer sets up as a defense that, because the government’s contract with the defendant was made under the act of Congress of March 4, 1917, the subcontract made by the defendant with the plaintiff is subject to the provision in that act which has been quoted ; and, although the subcontract was not expressly made upon a cost plus profit basis, as the defendant had a right to make it, if authorized by the department under the terms of the defendant’s contract, yet it was impliedly made upon this basis, and it alleges upon information •and belief, afforded by the notice of the department, that the price of $3,223 per boat was in excess of a reasonable profit above the actual cost to the plaintiff for the manufacture of said oil burner equipment and that the price of $1,915 per boat, plus $267.95, the cost of bronze [103]*103castings per boat, would yield at least a reasonable profit above the cost to plaintiff for the manufacture and delivery thereof; that the alleged contract is illegal and of no force and effect; that, as it has already paid the plaintiff the sum of $112,805, and the whole cost for the oil burner equipment for the 40 torpedo boats, plus $267.95, the cost of bronze castings per boat, was only $87,318, on the basis of $1,915 for the oil equipment per boat, as fixed in the order of the Compensation Board rescinding its former approval, it owes the plaintiff nothing.

[ 1 ] The questions raised and which have been argued are: First, whether, because of the provision in the act of Congress of March 4, 1917, the contract between the plaintiff and the defendant was impliedly upon a cost plus profit basis, or a contract between the defendant and plaintiff under the quoted provision of the defendant’s contract, which contemplates the purchase of material, subject to approval as to terms and specifications by the department and as to prices and awards by the Compensation Board.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Moore
95 U.S. 760 (Supreme Court, 1878)
Hahn v. United States
107 U.S. 402 (Supreme Court, 1883)
United States v. Alabama Great Southern Railroad
142 U.S. 615 (Supreme Court, 1892)
Brown v. United States
113 U.S. 568 (Supreme Court, 1885)

Cite This Page — Counsel Stack

Bluebook (online)
269 F. 100, 1920 U.S. App. LEXIS 1811, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bethlehem-shipbuilding-corp-v-west-dodge-co-ca1-1920.