Bethany Marina Townhouses Phase II Condominium, Inc. v. BMIG, LLC

CourtSuperior Court of Delaware
DecidedJuly 27, 2016
DocketS15C-01-019 ESB
StatusPublished

This text of Bethany Marina Townhouses Phase II Condominium, Inc. v. BMIG, LLC (Bethany Marina Townhouses Phase II Condominium, Inc. v. BMIG, LLC) is published on Counsel Stack Legal Research, covering Superior Court of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bethany Marina Townhouses Phase II Condominium, Inc. v. BMIG, LLC, (Del. Ct. App. 2016).

Opinion

SUPERIOR COURT OF THE STATE OF DELAWARE

E. SCOTT BRADLEY 1 The Circle, Suite 2 JUDGE GEORGETOWN, DE 19947 July 27, 2016

John W. Paradee, Esquire Richard E. Berl, Jr., Esquire Baird, Mandalas & Brockstedt Berl & Feinberg, LLP 6 South State Street 34382 Carpenter’s Way Dover, DE 19901 Lewes, DE 19958

RE: Bethany Marina Townhouses Phase II Condominium, Inc. v. BMIG, LLC, C.A. No: S15C-01-019 ESB

Dear Counsel:

This is my decision on the Motion for Summary Judgment filed by Bethany

Marina Townhouses Phase II Condominium, Inc. (the “Association”), and the Motion

for Partial Summary Judgment filed by BMIG, LLC in this dispute over (1) unbuilt

condominium units owned by BMIG, and (2) unpaid condominium fees for boat slips

owned by BMIG. The unbuilt units at the center of this dispute are 51-53, 60-64, and

112-114.

The Bethany Marina Townhouses Phase II Condominium (“Bethany Marina

II”) was planned to be an expandable 77-unit condominium on 10.57 acres on

White’s Creek in Ocean View, Delaware. The initial condominium declaration

submitted the entire 10.57 acre parcel to the condominium regime, but excepted from

it “the parcels of land required to build the physical additional buildings consisting of seventy-seven (77) additional units...” The submission of “built units” to the

condominium regime was accomplished by preparing an addendum to the declaration

and declaration plan submitting the entire 10.57 acre parcel and once again excepting

the “parcels of land required to build the proposed additional buildings...” The sixth

amendment to the declaration submitted the entire 10.57 acre parcel of land to the

condominium regime and stated the following:

Excepting thereout and therefrom the parcels of land required to build the proposed additional buildings consisting of nineteen (19) additional units as shown on the Declaration Plan recorded among the Land Records of Sussex County, Delaware and identified as follows: Units 51 through 53, Units 60 through 72 and Units 112-114, inclusive.

And also excepting thereout the “pumping station,” “pump house,” “pool,” “pool house,” and “storm water management pond” as shown on said Declaration Plan.

The built and unbuilt units are not described by a metes and bounds

description, but they are shown on the declaration plans. BMIG obtained a deed on

March 23, 2009, conveying to it all of the original developer’s interest and rights in

Bethany Marina II and all lands that were not submitted to the Bethany Marina II

condominium regime.

The declaration gave the developer the right to expand Bethany Marina II by

giving it the right to annex, to be exercised prior to August 29, 2005, the land and

improvements constituting the property of Bethany Marina II. This was later

2 extended to August 29, 2010, by an amendment to the declaration. BMIG did nothing

until June of 2014 when it started work on Unit 53. Construction came to a halt when

the Association’s attorney told BMIG that the time for construction had expired. This

litigation followed.

The Unbuilt Units1

BMIG does not dispute that the time for submitting its lands to the Bethany

Marina II condominium regime has passed. Instead, BMIG argues that its lands were

never submitted to, and are not bound by, the Bethany Marina II condominium

regime. Thus, according to BMIG’s reasoning, it is not subject to any time limits for

construction set forth in the Bethany Marina II condominium documents. I agree.

That is exactly what the sixth amendment provides. It clearly excepted from the

Bethany Marina II condominium regime the parcels of land required to build units 51-

53, 60-72, and 112-114. It also excepted from the Bethany Marina II condominium

regime the pumping station, pump house, pool, pool house and stormwater

management pond. The Association argues that BMIG’s lands are not excepted from

the Bethany Marina II condominium regime because it is not possible to determine

where BMIG’s lands are located because they are not described with a metes and

1 Including the pumping station, pump house, pool, pool house and stormwater management pond.

3 bounds description. I disagree. While there is no metes and bounds description,

BMIG’s lands are shown on the declaration plans in sufficient detail to determine

where they are located. The Association also argues that BMIG was divested of its

lands because the developer only excepted the lands “required to build” the remaining

unbuilt units. The Association reasons that since the time for annexing additional

lands for built units has expired, that there are no lands “required to build” the

remaining units. I disagree. The Bethany Marina II condominium documents simply

do not provide for this event. The sixth amendment does except the lands required

to build units 51-53, 60-72, and 112-114. The condominium documents never

address what is to happen with the excepted lands if they are not annexed in time.

However, the condominium documents do provide that for any lands to be annexed

into the Bethany Marina II condominium regime that an amendment to the declaration

must be prepared and recorded authorizing such annexation. That was never done for

these lands. Thus, BMIG owns the lands required to build units 51-53, 60-64, 112-

114, and the pumping station, pump house, pool, pool house, and stormwater

management free of the Bethany Marina II condominium documents.

The Easement

BMIG needs access to its lands in order to construct improvements on them.

BMIG did acquire the following easement from the original developer:

4 GRANT OF EASEMENT

The Grantor does hereby reserve unto itself an easement to construct fourteen (14) buildings and the remaining portion of the first building as delineated on the said Declaration Plan, and all of the necessary parking lots, walks and other appurtenances requisite to service some or all of said fourteen (14) buildings and the remaining portion of the first building and to provide for the necessary ingress and egress to said building.2

The Association argues that the easement has lapsed because the time limit for

constructing additional buildings has passed. BMIG argues that the easement itself

contains no such limitation. “The terms of an easement are often critical in

determining its scope, as the language of the easement is the primary guide for the

courts.”3

The easement does grant BMIG the right to construct 14 buildings on the

property and all of the necessary parking lots, walks and other appurtenances

requisite to service the 14 buildings. The easement itself has no time limitation for

construction. Indeed, this easement, by its terms, continues during the existence of

the Bethany Marina II condominium. While the other Bethany Marina II

condominium documents do have a time limitation for construction, I have concluded

that BMIG’s unbuilt units are not burdened by that time limitation. Thus, I conclude

2 The easement also provides that it shall be perpetual during the continued existence of the Bethany Marina II condominium. 3 Green v. Templin, 2010 WL 2734147, at *10 (Del. Ch. July 2, 2010).

5 that the plain and unambiguous language of this easement gives to BMIG the

necessary access across the other lands of the Bethany Marina II condominium to

construct its units.

The Assessments for Boat Slips

BMIG purchased 11 boat slips when it acquired its interest in Bethany Marina

Free access — add to your briefcase to read the full text and ask questions with AI