DECISION

Pursuant to a decree of this court dated November 6, 1979, the Essex South Registry District of the Land Court issued to Donald E. Besser and J uliet Besser, of Beverly in the County of Essex, husband and wife, as tenants by the entirety, Certificate of Title No. 49543 (Exhibit No. 1) in which they were named as the registered owners of the latid described therein. Reference is made in said [521]*521Certificate of Title to a plan, drawn by Essex Survey Service, Inc., dated September 6, 1976, as modified and approved by the court. A copy of the decree plan (Exhibit No. 16) is attached hereto as Appendix “A”. In August of 1980, the defendants, Douglas M. Moody and Emily A. Moody, also of Beverly, acquired title from Elizabeth M. Sheffield by deed dated August 1, 1980 and recorded with Essex South District Deeds, Book 6723, Page 002 (Exhibit No. Í4) to a parcel of land, with the buildings thereon, situated off Prince Street, and adjoining the Besser premises on the southwest.

In the spring of 1981, the defendants acting through a contractor commenced the repair and restoration of an existing sea wall to end, or at least impede, the undermining by the Atlantic Ocean of a comer of the Moody swimming pool. The placement of the retaining wall in relation to the common property line led to the initial dispute between the parties. It was followed by a disagreement as to a deck, railings and fence about the pool. Finally, on J uly 8, 1981, the complaint was filed in the present proceeding in which the plaintiffs asked the court to rule that their boundaries were as shown on the decree plan and to order the defendants '> to remove that portion of the retaining wall which encroached on the Besser land. Subsequently, the complaint was amended, and a temporary restraining order and later a preliminary injunction were entered restraining certain specified activities on the land described in said Certificate of Title No. 49543. The defendants answered that they had been without knowledge of the registration proceedings, that their survey showed the boundary line located further to the east, that they acted in good faith, that the only encroachment is 4.31 feet of the retaining wall which they stand ready to remove and by amendment and counterclaim that the plaintiffs consented tó the placement of the retaining wall.

At the pre-trial conference, the defendants’ attorney disclaimed specifically any question of fraud in the registration decree. Kozdras v. Land/Vest Properties, Inc., Mass. (1980)1. It was agreed that the two principal issues in the case were whether any encroachments for which the defendants were responsible existed, and if so, to what extent. Questions which surfaced in the stormy summer of 1981 relative to the zoning ordinance and its possible violation play no part in the present proceeding.

A trial was held at the Land Court on November 9 and 20 and December 8, 1981 at which a stenographer was appointed to record and report the testimony. All exhibits introduced into evidence are incorporated herein by reference for the purpose of any appeal.

On all the evidence, I find and rule as follows:

1. The filed plan in Registration Case No. 39351 (Exhibit No. 2) contained an error of transcription in which the bearing on the line here in question appears as N.27' 54’ 06” W, rather than N.26*' 54’' 06” W, which is correct. This mistake was perpetuated on the decree plan so the property lines did not close if the original bearing was held.2

2. The filed plan shows offsets to the apron of the Moody swimming pool so the disputed common boundary line can be recaptured using the iron pipe shown on the decree plan and the two offsets. The Land Court disc at the southeasterly end of the line now has disappeared (presumably a victim of the ocean’s action) but a drill hole in lead remains which marks the former location of the Land Court disc.

3. The defendants- in purchasing the Sheffield property after the completion of the registration proceedings understood the property line to be further to the northeast. However, Mrs. Sheffield had [522]*522received notice of the registration proceedings and filed no objection. At the most, there may have been, if litigated, an honest disagreement as to the location of the line, but the registration decree is now final, and the defendants do not attack it. See, General Laws, c. 185, sec. 45.

4. On May 21 of last year, wooden forms were placed oh the Moody, land preparatory to the pouring of the concrete for the retaining wall and its footing. On the previous May 12, drilling began for the two-inch holes in the ledge to be pinned with inch and one-half'steel rods rising in a vertical direction and then strung horizontally with other reenforcing rods.

5. The Bessers testified that they were unaware of the drilling and did not realize that the retaining wall was being constructed until late in the afternoon of May 21 when they saw the forms. A meeting was scheduled for the following morning to discuss the matter. The Bessers testified that they told the Moodys, their contractor, and subsequently the subcontractor, that the proposed retaining wall encroached on the Besser land. They also expressed displeasure with the height and proposed appearance of the wall. The subcontractor proposed cutting back the wall, and dropping it down to preserve the view. The point at which it drops down is about .7 of a foot on the Bessers’ side of the line (Exhibit No. 5). The Bessers’ testimony is to the effect that on May 22 they told the Moodys of their, objections, that the Moodys insisted on going forward and that the Bessers then said, “If you are going to pour the wall anyway, at least cut it down in height.” The Moodys understood the Bessers to be complaining only of the height of the wall and that the Bessers were content for the project to continue if "the wall were dropped down. The plaintiffs’ version of the events of May 22 appear to more nearly reflect the actual occurrences of that date, and the court so finds. However, it also is clear to the court that the defendants, did not believe the wall encroached and agreed to pay the additional expense of lowering the height of a portion of it in a neighborly gesture designed to meet the objections of the plaintiffs.

6. Some preliminary work was done even before the wall was poured in preparation for filling the area between the apron of the pool and the sea 'wall. Railroad ties were placed to retain the fill. After the wall was in'place, the fill was put in the cavity, and Mr. Besser initiated conversations about the deck. The Moodys then delayed going forward with the deck during the period of June 15 t© J uly 2, and their contractor fulfilled other obligations. Finally, a meeting was held at which the parties and their attorneys were present. A suggestion was made by the attorney for the plaintiffs that the deck be catty-cornered at the ocean and near the common line,/rather than going out in a straight line to the sea wall, and Mrs. Moody understood the next day that the plaintiffs were agreeable to this. Since that time, a see-through railing has been installed at the edge of the sea wall, plantings have been made and a cedar picket fence installed on the defendants’ side of the boundary line which decreases in height as it nears the sea wall (Exhibit No. 20). Photographs of the pool and its appurtenances before and after the improvements of last summer form a part of Exhibit No. 20.

7. The Bessers in actuality were not satisfied, and this litigation is the result.

8. Exhibit No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peters v. Archambault
278 N.E.2d 729 (Massachusetts Supreme Judicial Court, 1972)
Blood v. Cohen
113 N.E.2d 448 (Massachusetts Supreme Judicial Court, 1953)
Hodgkins v. Farrington
5 L.R.A. 209 (Massachusetts Supreme Judicial Court, 1889)
Lynch v. Union Institution for Savings
34 N.E. 364 (Massachusetts Supreme Judicial Court, 1893)
Harrington v. McCarthy
48 N.E. 278 (Massachusetts Supreme Judicial Court, 1897)
Kershishian v. Johnson
96 N.E. 56 (Massachusetts Supreme Judicial Court, 1911)
Szathmary v. Boston & Albany Railroad
214 Mass. 42 (Massachusetts Supreme Judicial Court, 1913)
Congregation Beth Israel v. Heller
231 Mass. 527 (Massachusetts Supreme Judicial Court, 1919)
Marcus v. Brody
149 N.E. 673 (Massachusetts Supreme Judicial Court, 1925)
Tramonte v. Colarusso
152 N.E. 90 (Massachusetts Supreme Judicial Court, 1926)
Crosby v. Blomerth
154 N.E. 763 (Massachusetts Supreme Judicial Court, 1927)
Nelson v. American Telephone & Telegraph Co.
170 N.E. 416 (Massachusetts Supreme Judicial Court, 1930)
Tyler v. City of Haverhill
172 N.E. 342 (Massachusetts Supreme Judicial Court, 1930)
Malinoski v. D. S. McGrath, Inc.
186 N.E. 225 (Massachusetts Supreme Judicial Court, 1933)
Geragosian v. Union Realty Co.
289 Mass. 104 (Massachusetts Supreme Judicial Court, 1935)
Ferrone v. Rossi
42 N.E.2d 564 (Massachusetts Supreme Judicial Court, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
3 Mass. Supp. 520, Counsel Stack Legal Research, https://law.counselstack.com/opinion/besser-v-moody-masslandct-1982.