Besen v. State

17 Misc. 2d 119, 185 N.Y.S.2d 495, 1959 N.Y. Misc. LEXIS 3915
CourtNew York Court of Claims
DecidedApril 14, 1959
DocketClaim Nos. 32701, 34212
StatusPublished
Cited by2 cases

This text of 17 Misc. 2d 119 (Besen v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Besen v. State, 17 Misc. 2d 119, 185 N.Y.S.2d 495, 1959 N.Y. Misc. LEXIS 3915 (N.Y. Super. Ct. 1959).

Opinion

Alexander Del Giorno, J.

The claimant herein purchased some 36 acres of raw land in Rockland County for $36,320 by deed dated March 7, 1952. He actually went into possession of the property in December, 1951, on the basis of his contract [122]*122to purchase and started planning a development known as “ Besen Park”, later to he known as “ Lake Estates”. He had surveys made, lots and roads staked out, trees cut down. He proceeded to build two model homes, set up his field office, hired the necessary persons to supervise the job of development and to deal with proposed purchasers, had descriptive literature made out and advertised in the New York Times. Most of these efforts were either completed or in an advanced stage of accomplishment before he took title.

During this period he also submitted his planned development to the Town Board of Ramapo and the State Department of Health for approval. Many changes were suggested by the Town Planning Board on the preliminary maps of the subdivision. The final approved map indicates that some 32 lots had been disapproved for building development by the State Department of Health because of improper drainage in those lots. The testimony shows that these lots could be approved on subsequent application if the subsoil conditions were changed to a degree permitting approval, and then could be utilized for home building. Claimant did most of these things before taking title.

He testified that he was proceeding with the development of his acreage for home building when on about June 27, 1952, he was advised by letter by the Monsey Heights Water Company that his application for a water supply on his development would not be processed further because the Thruway was coming through his property. Except for some little odds and ends performed to December, 1952, claimant did no more work on the development after June 27, 1952.

After receiving the letter from the Monsey Heights Water Company, claimant returned to prospective purchasers all the deposits on what he called binders ” for 36 houses. Meanwhile immediately after the above events of 1952, Besen went to Phillipsburg, N. J. where he bought land, developed 400 lots, built and sold 110 houses and finally sold outright 200 of those lots in 1954. He was a very busy builder and lost no time, for he completed quite a few developments in addition to Phillipsburg and disposed of the houses therein, all between 1952 and 1955. The so-called deposits, except for two, were applications for credit approved by the V. A. or F. H. A. They had no binding force. They do disclose, however, that the prices of the contemplated houses were in the range of $10,000 to $13,000. The two lots sold on contract were for specialty use by professional men.

[123]*123There were altogether 10 takings on the subject property. These occurred during the years 1954 and 1955, but the parties agree that the taking date should be as of December, 1955. The present Claim No. 34212, is an amendment of and supplemental to Claim No. 32701. In this present claim the claimant asks damages as follows:

Lots in whole or in part appropriated.............. $200,000
50' road beds appropriated and road system
destroyed..................................... 35,000
Remaining land damaged......................... 250,000
Other damages ................................. 1,000,000
Total damages .............................. $1,485,000

His proof, however, has been based on the quite different theory of original investment plus all costs allegedly involved in the development, plus loss of profits.

The trial moved slowly for the reason that there were too many theories advanced and too many tentative approaches made to the end desired. The court found it impossible to bring about any agreement between the parties whereby proof could be adduced along definite lines of approach without interminable discussions of many collateral issues. Nevertheless, in spite of all these unnecessary excursions into theory, hope and speculation, the fact is that the claimant did sustain damages for which he must be fairly compensated.

Claimant stated that he had bought 36 acres of raw land. He had a development map drawn by the engineer he engaged, from which resulted 91 lots to be built upon. He did build two sample houses on Monsey Heights Road and he retained nine lots on Route 59 for stores or a shopping center. Fifty-eight lots were finally approved on June 2, 1952 and 33 lots were unapproved by the State Department of Health for building thereon at that time. A part of the development was reserved for a proposed park and pond into which surface drainage water from the development would flow.

In arriving at values herein, the court considers that since June, 1952, when claimant was compelled to stop work on his development, until December, 1955, the agreed date of the takings, values of real estate increased in the Town of Ramapo. The claimant asserts that the increase was by 50%; the State says it was by 10%. The court feels that a fair increase was between 20% to 25%, which increase will be taken into consideration in the court’s evaluation.

[124]*124The Thruway took nine acres right through the development, which involved a number of lots, some of which were partly damaged. These will be itemized in a later part of this decision for the purpose of clarity. State’s Exhibit “ A ” presents an excellent and comprehensive tableau of the entire development with the various takings clearly indicated in colors.

The claimant is entitled to direct as well as consequential damages. The State originally contended that because only two houses (model homes) were built, the damage should be based on acreage and not on lots, as said lots are indicated in State’s Exhibit ‘1 A ” (which is actually claimant’s final development map, indicating the conditions upon which it could or could not be built upon certification thereof by the State Department of Health, and which also reflects the various takings as above stated). The State’s experts later found that claimant’s efforts justified approval on a lot basis rather than raw acreage, and so valued the property.

The testimony has made it abundantly clear that the claimant, before the Thruway taking, had filed said map and had submitted it several times and that in fact the map had been partially approved for building houses; that he had done enough work therein, such as rough grading of the roadways, staking out of lots, laying some subsoil drainage pipes and other work as to change the character of that acreage to lots. Therefore, the damage to the claimant may be based only upon the lots taken and consequential damages to the remaining lots in the development. What the value of each lot was, however, is something else to consider. On this basis I do not accept claimant’s proof of analysis of costs and disbursements allegedly incurred in achieving the transformation from acreage to lots, nor the claim for loss of profits which never existed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Glazer v. Quittman
84 Misc. 2d 561 (New York Town and Village Courts, 1975)
Commonwealth, Department of Highways v. Fister
373 S.W.2d 720 (Court of Appeals of Kentucky (pre-1976), 1963)

Cite This Page — Counsel Stack

Bluebook (online)
17 Misc. 2d 119, 185 N.Y.S.2d 495, 1959 N.Y. Misc. LEXIS 3915, Counsel Stack Legal Research, https://law.counselstack.com/opinion/besen-v-state-nyclaimsct-1959.