Berwind-White Coal Mining Co. v. Metropolitan S. S. Co.

173 F. 806, 1909 U.S. App. LEXIS 5914
U.S. Circuit Court for the District of Maine·Decided September 18, 1909·No. No. 625·Published·Cited by 1 cases

Opinion

PUTNAM, Circuit Judge.

This petition was heard on April 9, 1909. At that time the court found nothing in the record which impressed it with any conviction that, so far as the larger portion of the claim was. concerned, the result would be in any way different .on this petition from what it was with .the Fletcher petition, decided on December 26, 1908 (166 Fed. 782), and affirmed by the Circuit Court of Appeals on August 18, 1909, reported in 173-Fed. 471, as modified by [807]*807force of some circumstances in the opinion passed down on the Wanamaker petition, March 10, 1909 (169 Fed. 491). In the Fletcher Case, everything furnished was furnished within the state of New Jersey. In the Wanamaker Case, the contract for all that was furnished was made in the state of New York, but the delivery of the major portion thereof was made in the state of New Jersey. A portion was delivered in the state of New York, where they were contracted for, and as to that we held that there was not enough to bring the case within the statutes of that state. In the present case, the contract was made by correspondence carried on on the part of the petitioner in New York state, and on the part of the Metropolitan Steamship Company at Boston, in the state of Massachusetts. A portion of the work was put aboard the vessels at Chester, in the state of Pennsylvania, where the hulls were constructed. The entire preliminary work was done at the shops of the petitioner at Greenpoint, in the state of New York. Some portion may have been installed while the vessels were in the state of New York, but the great bulk was installed at Hoboken, in New Jersey, where the vessels were being completed, as explained in the Fletcher Case. As the record here fails in the same particular in which the record failed in the Wanamaker Case, with reference to what was installed within the state of New York, the judgment in this case will relate only to what was installed at Hoboken, and, on the principle stated with reference to the Wanamaker petition, it will cover whatever was installed there, wherever else the preliminary work or any part of the work was done. It will be understood, therefore, that the reference to the master, whatever its general terms, will be limited to what was thus installed at Hoboken.

At the hearing in April, the original complainant, namely, the Berwind-White Coal Mining Company, an unsecured creditor, asked leave to file a brief on the question of waiver. All questions of this character were disposed of quite fully both by us and by the Circuit Court of Appeate with reference to the Fletcher petition; but it is now urged that we stated in our opinion in that case that there is no legal evidence that Fletcher knew of the prior'mortgage, and that the present record shows that Fnglis not only knew of the prior mortgage described in our opinion on tlie Fletcher petition, but also knew that there were to be supplemental mortgages covering the Flarvard and Yale specifically, and also that his knowledge did precede his liens. The brief proceeds with much vigor and care to develop this alleged fact of knowledge on the part of Englis, and to press upon the court the essential difference between the two petitions on that account. On-the whole, we think we had better review the present propositions carefully, although we think there is an expression in the opinion of the Circuit Court of Appeals which renders the attempt to discriminate of no effect.

We wish, first, to state that no inference is to be drawn, from what we decided with reference to the Elelcher petition, that any amount of knowledge would have affected the conclusion which we then reached. We decided that case on the then existing- facts, leaving any case involving- different facts to take care of itself. We also observed at the [808]*808outset that all the propositions we have received from counsel with reference to either of the petitions before us in regard to the question of waiver, or any cognate question, entirely overlooked the fact that the conclusions of this court, as well as of the Circuit Court of Appeals, rest on the proposition that the lien given by the statutes of New Jersey is akin to the maritime lien, and has the same characteristics, except it cannot be enforced in admiralty. In this respect it is widely distinguished from the ordinary lien given by the common law or by statutes. The pith of the distinction, and.the reason therefor, is found in the following expression appearing in the opinion of the Circuit Court of Appeals with reference to the Fletcher petition, namely:

“By the maritime law, on the other hand, a lien existed for the supply and repair of a vessel having an application more extended. It was not possessory. Indeed, the maritime lien was deemed to be given in order that the vessel might go on its way unembarrassed by the lienor’s attempt to obtain immediate payment.”

Therefore it is that, with reference to expedition in enforcing the lien, there is a wide difference in favor of the maritime lien, and, consequently, pf the liens set out by the petitions for the interveners, which it is now decided, so far as we are concerned, are akin to maritime liens, as we have said. Consequently it was that we decided on the Fletcher petition, as pointed out on pages 791 and 792 of 166 Fed., where we fully stated the facts, that there was ne basis for a claim of laches with regard thereto. So far as mere laches is concerned, what we have said there applies to the case here. For any one who wishes to read examples of the extent to which the doctrine of laches fails to apply as against maritime liens, we refer them to 2 Parsons on Shipping and Admiralty (1869) 361 et seq.

Another proposition must be considered with reference to the distinguishing features of maritime liens, and, therefore, the liens in this case; and that is that they are not prejudiced by existing incumbrances, although the incumbrances are known to the lienor, unless in an extreme case like that of a tort-feasor. This is on the broad principle that whoever voluntarily takes a lien on a vessel gives the owner of the vessel implied authority to incumber her for supplies and repairs, so far as the maritime law is concerned. At any rate, so far as that law is concerned, the lien cuts through all incumbrances in the way of mortgages, even though known to the lienor. For the reasons stated, the same rule applies here.

For the reasons we have given in our opinion with reference to the Fletcher petition, it is useless to maintain that the original mortgage of 1905, before the steamers Yale and Harvard were constructed, or their construction commenced, raised any equity as against the interveners. That was fully disposed of in that opinion, and no claim of that nature is made now. Therefore the issue, if at all, is between the lienors and the mortgages on the Yale and the Harvard, one of which was made May 25, 1907, and the other one August 14, 1907. In the present case, one contract was made with the petitioner with reference to the construction work for both vessels. This was made in August, 1905, a complete, binding contract, though in the form 'of letters. The record does not show when the work of preparation was [809]*809commenced by the petitioner, but a very considerable installation on both

Free access — add to your briefcase to read the full text and ask questions with AI

Berwind-White Coal Mining Co. v. Metropolitan S. S. Co., 173 F. 806, 1909 U.S. App. LEXIS 5914 (circtdme 1909).

173 F. 806 (Berwind-White Coal Mining Co. v. Metropolitan S. S. Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

The Solhaug
2 F. Supp. 294 (S.D. New York, 1931)