Berns Custom Homes, Inc. v. Johnson

2014 Ohio 3918
CourtOhio Court of Appeals
DecidedSeptember 11, 2014
Docket100837, 101014
StatusPublished
Cited by5 cases

This text of 2014 Ohio 3918 (Berns Custom Homes, Inc. v. Johnson) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Berns Custom Homes, Inc. v. Johnson, 2014 Ohio 3918 (Ohio Ct. App. 2014).

Opinion

[Cite as Berns Custom Homes, Inc. v. Johnson, 2014-Ohio-3918.]

Court of Appeals of Ohio EIGHTH APPELLATE DISTRICT COUNTY OF CUYAHOGA

JOURNAL ENTRY AND OPINION Nos. 100837 and 101014

BERNS CUSTOM HOMES, INC. PLAINTIFF-APPELLEE

vs.

RICHARD G. JOHNSON

DEFENDANT-APPELLANT

JUDGMENT: AFFIRMED

Civil Appeal from the Cuyahoga County Court of Common Pleas Case No. CV-12-791858

BEFORE: E.A. Gallagher, J., Boyle, A.J., and Jones, J.

RELEASED AND JOURNALIZED: September 11, 2014 ATTORNEY FOR APPELLANT

Robert D. Kehoe Kehoe & Associates, L.L.C. 900 Baker Building 1940 East Sixth Street Cleveland, Ohio 44114

ATTORNEYS FOR APPELLEE

Jordan Berns Paul M. Greenberger Berns, Ockner & Greenberger, L.L.C. 3733 Park East Drive, Suite 200 Beachwood, Ohio 44122 EILEEN A. GALLAGHER, J.:

{¶1} Appellant Richard G. Johnson appeals the decision of the trial court, which

confirmed an arbitration award rendered in favor of Berns Custom Homes Incorporated

(“Berns”). Johnson argues the trial court erred in confirming the award because the

arbitrator exceeded his authority and powers, his decision directly contradicts the terms

of the agreement between the parties and the arbitrator’s decision could not be rationally

derived from the terms of the agreement. Finding no merit to the instant appeal, we

affirm the decision of the trial court.

{¶2} Richard Johnson contracted with Berns to renovate his home in Bentleyville,

Ohio. The parties entered into a contract and each party was represented by counsel.

The contract itself was detailed and specifically tailored to this home renovation. In

particular, the work was supposed to be done in two phases: phase one to remodel the

main level of the house was to begin on June 14, 2010 and was scheduled to take 80

days; thereafter, phase two on the lower level was to take 57 days. The parties’ contract

stated that “[n]o amendment to this [c]ontract shall be effective unless in an instrument

signed by all parties.” The parties further agreed that with respect to work not

described in the plans and specifications — whether new items requested by Johnson or

extra work necessitated because of unexpected conditions — there must be joint consent

in a written change order, otherwise Berns would not be obligated to do the additional

work.

{¶3} Disagreements arose as the work progressed and, by October 6, 2010, Johnson barred the workers from his home and emailed Justin Berns, president of Berns,

advising that Berns was “in material breach of our contract since September 20th for

failing to complete” the main level. Then, on October 15, 2010, Johnson notified

Berns, pursuant to paragraph five of the contract, that the agreement was terminated.

{¶4} Paragraph 16 of the contract requires “any dispute” under the contract be

submitted to binding arbitration before a single arbitrator. Berns initiated arbitration

with the American Arbitration Association (“AAA”) claiming that Johnson breached

the contract and Johnson counterclaimed. A nine-day arbitration hearing was held and

the arbitrator awarded Berns $160,162.27 in damages plus $6,388.58 for AAA’s

administrative fees and expenses.

{¶5} The arbitrator found that “Johnson breached his agreement with [Berns] by

failing to pay for certain base contract and extra work.” The arbitrator also concluded

that Johnson prevented Berns’ performance under the contract by “removing [Berns] and

its subcontractors” from the job site and “by terminating [Berns].” At the same time, he

rejected Berns’ claims for liquidated damages and attorney fees so that the combined

total award was less than Berns sought.

{¶6} Berns filed a lawsuit in the common pleas court to reduce the arbitrator’s

award to judgment under R.C. 2711.09, which allows a party who prevailed at an

arbitration to apply to the common pleas court for such an order. Johnson opposed and

moved the trial court to vacate the arbitrator’s award under R.C. 2711.10(D). The trial

court entered a journal entry denying Johnson’s motion to vacate the arbitration award and granted Berns’ application to reduce the award to judgment. In its entry, the trial

court concluded that the arbitrator’s award was rationally related to the contract and that

because the award “draws its essence from the renovation contract, the defendant’s

motion to vacate the award must be denied.”

{¶7} Johnson initially appealed but then on the same day, filed a motion with this

court to stay the appeal and remand and also filed a motion to reconsider and motion to

vacate the judgment with the trial court. This court granted Johnson’s motion to stay

the appeal and to remand.

{¶8} The basis for Johnson’s reconsideration was the First District’s decision in

H.C. Nutting Co. v. Midland Atlantic Dev. Co., L.L.C., 1st Dist. Hamilton No.

C-1300132, 2013-Ohio-5511. In its decision, the First District affirmed the vacation of

an arbitration award finding that the arbitrator exceeded its authority under the parties’

contract by including consequential damages that were expressly excluded by the parties’

agreement. Johnson argued that the damages awarded by the arbitrator were not

recoverable because there never were written change orders for the work done by Berns

and not paid for by Johnson.

{¶9} The trial court distinguished Nutting from the instant case concluding that

“there is legal precedent for the position that a party, by his conduct, can waive the

contract requirement for written, signed change orders, and evidence was offered at

arbitration that this is exactly what happened.” 1 The trial court denied Johnson’s

1 The parties’ emails attached as exhibits to their trial court briefs reference both running motion to reconsider and motion to vacate.

{¶10} Johnson appealed the trial court’s order and this court consolidated his two

appeals for record, briefing, hearing and disposition. In his appeal, Johnson raises the

following assigned errors:

I. The trial court erred in affirming the arbitration award because the arbitrator exceeded his authority and powers where his decision directly contradicts the express terms of the agreement between the parties, and could not be rationally derived from the terms of the agreement.

II. The trial court erred in affirming the arbitration award which is defective because the arbitration award does not draw its essence from the agreement and is unlawful, arbitrary, or capricious where the agreement expressly required any changes in work to be approved in writing, and the damages awarded were for work that was not approved in writing.

III. The trial court erred in affirming the arbitration award which is defective because the arbitration award does not draw its essence from the agreement where it disregarded express terms in the agreement that state time is of the essence and set forth a schedule for work that established Plaintiff’s breach for not completing work in the time agreed upon for performance.

{¶11} Although Johnson puts forth three assigned errors for our review each

involves an analysis of the same standard of review and legal issues and, as such, we

shall address them together.

{¶12} Judicial review of an arbitrator’s decision is narrow. BIGResearch,

L.L.C., v. PENN L.L.C., 10th Dist. Franklin Nos. 11-AP-855 and 11AP-856,

2012-Ohio-2992.

{¶13} As stated by the Eleventh District Court of Appeals:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Berns Custom Homes, Inc. v. Johnson
2021 Ohio 3033 (Ohio Court of Appeals, 2021)
Johnson v. U.S. Title Agency, Inc.
2020 Ohio 4056 (Ohio Court of Appeals, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
2014 Ohio 3918, Counsel Stack Legal Research, https://law.counselstack.com/opinion/berns-custom-homes-inc-v-johnson-ohioctapp-2014.