Berns Custom Homes, Inc. v. Johnson
Opinion
Court of Appeals of Ohio
EIGHTH APPELLATE DISTRICT COUNTY OF CUYAHOGA
JOURNAL ENTRY AND OPINION Nos. 100837 and 101014
BERNS CUSTOM HOMES, INC.
PLAINTIFF-APPELLEE
vs.
RICHARD G. JOHNSON
DEFENDANT-APPELLANT
JUDGMENT:
AFFIRMED
Civil Appeal from the
Cuyahoga County Court of Common Pleas Case No. CV-12-791858
BEFORE: E.A. Gallagher, J., Boyle, A.J., and Jones, J.
RELEASED AND JOURNALIZED: September 11, 2014
ATTORNEY FOR APPELLANT
Robert D. Kehoe Kehoe & Associates, L.L.C. 900 Baker Building 1940 East Sixth Street Cleveland, Ohio 44114
ATTORNEYS FOR APPELLEE
Jordan Berns Paul M. Greenberger Berns, Ockner & Greenberger, L.L.C. 3733 Park East Drive, Suite 200 Beachwood, Ohio 44122
EILEEN A. GALLAGHER, J.:
{¶1} Appellant Richard G. Johnson appeals the decision of the trial court, which confirmed an arbitration award rendered in favor of Berns Custom Homes Incorporated (“Berns”). Johnson argues the trial court erred in confirming the award because the arbitrator exceeded his authority and powers, his decision directly contradicts the terms of the agreement between the parties and the arbitrator’s decision could not be rationally derived from the terms of the agreement. Finding no merit to the instant appeal, we affirm the decision of the trial court.
{¶2} Richard Johnson contracted with Berns to renovate his home in Bentleyville, Ohio. The parties entered into a contract and each party was represented by counsel. The contract itself was detailed and specifically tailored to this home renovation. In particular, the work was supposed to be done in two phases: phase one to remodel the main level of the house was to begin on June 14, 2010 and was scheduled to take 80 days; thereafter, phase two on the lower level was to take 57 days. The parties’ contract stated that “[n]o amendment to this [c]ontract shall be effective unless in an instrument signed by all parties.” The parties further agreed that with respect to work not described in the plans and specifications — whether new items requested by Johnson or extra work necessitated because of unexpected conditions — there must be joint consent in a written change order, otherwise Berns would not be obligated to do the additional work.
{¶3} Disagreements arose as the work progressed and, by October 6, 2010,
Johnson barred the workers from his home and emailed Justin Berns, president of Berns, advising that Berns was “in material breach of our contract since September 20th for failing to complete” the main level. Then, on October 15, 2010, Johnson notified Berns, pursuant to paragraph five of the contract, that the agreement was terminated.
{¶4} Paragraph 16 of the contract requires “any dispute” under the contract be submitted to binding arbitration before a single arbitrator. Berns initiated arbitration with the American Arbitration Association (“AAA”) claiming that Johnson breached the contract and Johnson counterclaimed. A nine-day arbitration hearing was held and the arbitrator awarded Berns $160,162.27 in damages plus $6,388.58 for AAA’s administrative fees and expenses.
{¶5} The arbitrator found that “Johnson breached his agreement with [Berns] by failing to pay for certain base contract and extra work.” The arbitrator also concluded that Johnson prevented Berns’ performance under the contract by “removing [Berns] and its subcontractors” from the job site and “by terminating [Berns].” At the same time, he rejected Berns’ claims for liquidated damages and attorney fees so that the combined total award was less than Berns sought.
{¶6} Berns filed a lawsuit in the common pleas court to reduce the arbitrator’s award to judgment under R.C. 2711.09, which allows a party who prevailed at an arbitration to apply to the common pleas court for such an order. Johnson opposed and moved the trial court to vacate the arbitrator’s award under R.C. 2711.10(D). The trial court entered a journal entry denying Johnson’s motion to vacate the arbitration award and granted Berns’ application to reduce the award to judgment. In its entry, the trial court concluded that the arbitrator’s award was rationally related to the contract and that because the award “draws its essence from the renovation contract, the defendant’s motion to vacate the award must be denied.”
{¶7} Johnson initially appealed but then on the same day, filed a motion with this court to stay the appeal and remand and also filed a motion to reconsider and motion to vacate the judgment with the trial court. This court granted Johnson’s motion to stay the appeal and to remand.
{¶8} The basis for Johnson’s reconsideration was the First District’s decision in H.C. Nutting Co. v. Midland Atlantic Dev. Co., L.L.C., 1st Dist. Hamilton No. C-1300132, 2013-Ohio-5511. In its decision, the First District affirmed the vacation of an arbitration award finding that the arbitrator exceeded its authority under the parties’ contract by including consequential damages that were expressly excluded by the parties’ agreement. Johnson argued that the damages awarded by the arbitrator were not recoverable because there never were written change orders for the work done by Berns and not paid for by Johnson.
{¶9} The trial court distinguished Nutting from the instant case concluding that “there is legal precedent for the position that a party, by his conduct, can waive the contract requirement for written, signed change orders, and evidence was offered at arbitration that this is exactly what happened.” 1 The trial court denied Johnson’s
1 The parties’ emails attached as exhibits to their trial court briefs reference both running motion to reconsider and motion to vacate.
{¶10} Johnson appealed the trial court’s order and this court consolidated his two appeals for record, briefing, hearing and disposition. In his appeal, Johnson raises the following assigned errors:
I. The trial court erred in affirming the arbitration award because the arbitrator exceeded his authority and powers where his decision directly contradicts the express terms of the agreement between the parties, and could not be rationally derived from the terms of the agreement.
II. The trial court erred in affirming the arbitration award which is defective because the arbitration award does not draw its essence from the agreement and is unlawful, arbitrary, or capricious where the agreement expressly required any changes in work to be approved in writing, and the damages awarded were for work that was not approved in writing.
III. The trial court erred in affirming the arbitration award which is defective because the arbitration award does not draw its essence from the agreement where it disregarded express terms in the agreement that state time is of the essence and set forth a schedule for work that established Plaintiff’s breach for not completing work in the time agreed upon for performance.
{¶11} Although Johnson puts forth three assigned errors for our review each involves an analysis of the same standard of review and legal issues and, as such, we shall address them together.
{¶12} Judicial review of an arbitrator’s decision is narrow. BIGResearch, L.L.C., v. PENN L.L.C., 10th Dist. Franklin Nos. 11-AP-855 and 11AP-856, 2012-Ohio-2992.
{¶13} As stated by the Eleventh District Court of Appeals:
change order lists as well as admissions that changes were made orally during the home renovation.
Before embarking on an analysis of the merits, we first point out that a court has a very limited role in reviewing a binding arbitration award.
The arbitrator is the final judge of both law and facts and we may not substitute our judgment for that of the arbitrator. An arbitrator’s decision is presumed valid and thus enjoys great deference. (Internal citation omitted).
Free access — add to your briefcase to read the full text and ask questions with AI
2014 Ohio 3918 (Berns Custom Homes, Inc. v. Johnson) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.