Bernos Coal Co. v. Lujan

739 F. Supp. 1133, 1989 WL 222583
CourtDistrict Court, E.D. Tennessee
DecidedJune 6, 1989
DocketCiv. No. 3-87-437
StatusPublished
Cited by2 cases

This text of 739 F. Supp. 1133 (Bernos Coal Co. v. Lujan) is published on Counsel Stack Legal Research, covering District Court, E.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bernos Coal Co. v. Lujan, 739 F. Supp. 1133, 1989 WL 222583 (E.D. Tenn. 1989).

Opinion

ORDER

HULL, Chief Judge.

This is an appeal from a decision issued May 18, 1987, by the United States Department of Interior Board of Land Appeals. 30 U.S.C. § 1276(a)(2). In addition, the plaintiffs seek permanent injunctive relief against the defendants.

In 1978, the State of Tennessee issued Bernos Coal Company (Bernos) a surface mining permit, No. 78-148, to conduct mining in a previously mined area in Bledsoe County, Tennessee. Excello Land and Mineral Corporation (Excello) succeeded to the interests of Bernos under the permit and obligated itself contractually to follow its reclamation requirements. In late 1978 and early 1979, Excello conducted limited coal extraction activities in the permit area. It soon discovered that the hoped for coal reserves did not exist. It backgraded and at least partially reclaimed the disturbed area. It also did some grading in areas disturbed by previous operations. Excello removed its equipment from the permit area in the fall of 1979. On December 6, 1979, the area was inspected by the Office of Surface Mining (OSM) inspector Walker and was found to have been returned to its approximate original contour.

Mr. Walker inspected the mining site five times in 1980, without citing it for any violations.

On January 19, 1981, the site was visited by another OSM inspector, Douglas Gode-sky, who wrote up a Notice of Violation (NOV) citing Bernos, in pertinent part, for failing to establish final graded slopes which did not exceed the approximate pre-mining slopes and failing to backfill and grade to the most moderate slope possible. This NOV was amended on March 16, 1981, to include Excello as the operator. After an informal hearing on April 7, 1981, the NOV was modified to extend the abatement period. On June 16, 1981, Cessation Order (CO) 81-2-75-22 was issued to Ber-nos and Excello for failing to correct the slope violation previously cited. On June 17, 1981, Bernos and Excello filed for review of this CO. On December 11, 1981 (six months rather than thirty days after the CO), the OSM issued its notice of proposed penalty assessment of $22,500.00 and Bernos and Excello requested a conference. Unfortunately, before the conference could be held, on February 24, 1982, Excello suffered a fire and lost its maps, photos, and other records of its reclamation efforts. The OSM’s conference report affirmed the assessment. Bernos and Excello paid the assessment into escrow, petitioned for its review, and moved to dismiss it as untimely. The appeal on CO-81-2-75-22 was not heard until November 19, 1984.

In the meantime, on August 10, 1982, the State of Tennessee became the primary regulatory authority for mining in the state under the Surface Mining Control and Reclamation Act subject only to oversight by the Department of the Interior through the OSM. 30 U.S.C. § 1253 (1983). In October and November of 1983, state OSM inspectors issued NOVs to Bernos and Excello for “rill and gully” violations. The plaintiffs vigorously contested these before the Tennessee Board of Reclamation Review (Tennessee Board), the body now sanctioned by the OSM to decide such cases. On April 19, 1984, the Tennessee Board vacated the rill and gully violations but ordered specific corrective measures to be [1135]*1135performed on the permit site. On April 25, 1984, the Tennessee Board found the measures to have been taken, ruled that the mine site had been reclaimed, and ordered the reclamation bond released.

Less than a week later, on May 1, 1984, the OSM suspended the authority of Tennessee’s Department of Surface Mining on a finding that the state was not adequately implementing and enforcing its regulations. The OSM resumed direct enforcement efforts.

On July 20, 1984, OSM Inspector Morgan visited the Excello mining cite and issued the same rill and gully notice of violation just litigated before the state board. Ber-nos and Excello appealed and also applied for temporary relief pending a final ruling on the merits of the NOV. On October 22, 1984, an administrative law judge (AU) denied their application for temporary relief finding that Bernos and Excello had failed to show that there was a substantial likelihood that they would eventually prevail on the merits. In his ruling, the AU specifically rejected the plaintiffs’ contention that the state agency’s release of the bond rendered the mine site immune from further regulation and that its ruling on the rill and gully violation was binding on the OSM. Bernos and Excello appealed from the denial of temporary injunctive relief to federal court. The parties consented to a hearing before United States Magistrate Robert P. Murrian.

On December 28, 1984, in Excello v. Clark, CIV-3-84-902, Magistrate Murrian reversed the AU’s denial of temporary relief. In a carefully reasoned opinion, he ruled that the same operative facts (rill and gully violations) gave rise to the two (state and federal) enforcement proceedings; that the issues were actually and finally litigated in the state proceedings; that the DSM (state) and OSM (federal) were privies because both agencies were participating in the same federal program, enforcing the same guidelines, and because the DSM was the OSM’s actual representative; and that, therefore, the state ruling had collateral estoppel or res judicata effect on the subsequent federal proceedings. Magistrate Murrian’s ruling was never appealed.

Back before the AU, Bernos and Excello moved for a summary decision, relying on the Magistrate’s ruling that the OSM was collaterally estopped from relitigating the rill and gully violations. The motion was unopposed. On April 20, 1985, AU David Torbett granted the uncontested motion and vacated the NOV.

A few months later, AU Torbett finally ruled on the appeal of CO-81-2-75-22, the slope violations issued back in 1981 by OSM Inspector Godesky before the state became the regulatory authority. In an order dated July 26, 1985, Judge Torbett held that both the CO itself and the penalty assessment were proper. He also declined the invitation to find the federal enforcement precluded by the Tennessee Board’s prior ruling that the mine site had been reclaimed reasoning that the slope violation (unlike the rill and gully question) had not been actually litigated before the Tennessee Board.

Bernos and Excello appealed from this decision to the United States Department of Interior Board of Land Appeals (IBLA). The grounds raised on appeal were: (1) that the NOV and CO were invalid because their mining activity had had no adverse impact on the permit site, (2) that even if the NOV and CO were valid, the doctrines of res judicata and collateral estoppel barred the OSM from further enforcement because the state had already determined that the site was fully reclaimed; and (3) that the CO should have been dismissed anyway because the penalty assessment was untimely and the delay had caused them actual prejudice (the fire loss of their reclamation records).

On May 18, 1987, AU Bruce Harris of IBLA found that the NOV and CO had been properly issued; that Bernos and Ex-cello had not been prejudiced by the delay in the penalty assessment; and, more importantly, that the Tennessee Board’s ruling that the mine site had been reclaimed had no preclusive effect on federal enforcement attempts. Judge Harris specifically addressed Magistrate Murrian’s ruling on [1136]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Catron v. Babbitt
955 F. Supp. 627 (W.D. Virginia, 1997)
Horizon Coal Corp. v. United States
876 F. Supp. 1512 (N.D. Ohio, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
739 F. Supp. 1133, 1989 WL 222583, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bernos-coal-co-v-lujan-tned-1989.