Berninger v. Sunbury, Hazleton & Wilkes-Barre Railway Co.

53 A. 361, 203 Pa. 516, 1902 Pa. LEXIS 753
Supreme Court of Pennsylvania·Decided October 13, 1902·No. Appeal, No. 33·Published·Cited by 10 cases

Opinion

Opinion by

Mr. Justice Dean,

This is an action of trespass brought by the plaintiff against defendant to recover damages occasioned by backwater on his mill property situate on Catawissa creek in Columbia county. Plaintiff’s property was 2,000 feet up stream from where defendant’s railway bridge crossed the same stream. In March, 1893, an ice gorge lodged against the piers of the bridge, which had the effect of damming back the water to plaintiff’s mill dam and partially destroying it; he alleged the bridge was unskillfully and negligently constructed, in that the piers were not properly set to meet the current of the stream in time of spring floods, and further, that they were not far enough apart to afford passage to floating ice at break-ups in spring freshets. The defendant alleged that the bridge was constructed according to the best engineering skill, to meet any ordinary or probable demand upon it, in view of the size of the stream and the watershed contributory to it. That this was the whole duty demanded of it, and having performed this, it was guilty of no negligence which would support plaintiff’s action.

At the close of plaintiff’s evidence, the learned judge of the court below, being of opinion, that plaintiff had failed to make out a case warranting a verdict, directed a nonsuit. This he afterwards, on motion, refused to take off, and we have this appeal by plaintiff. The reason given by the court for directing a nonsuit is that the bridge, whether negligently or skillfully constructed, was the act of an independent contractor, and that for his act under the authority of Painter v. Pittsburg, 46 Pa. 221, he alone was answerable to third parties. This ruling may have been correct; in our examination of the evidence it does not appear clearly to be so. But however this may be, if for any other reason the evidence failed to show negligence on the part of defendant, plaintiff’s case must fail, and the decree should be affirmed. The bridge is 182 feet between the abutments; it has three piers with cutwater points; the stream at the bridge and for some distance above it is about fifty feet wide; deduct[518] ing the area covered by the foundations of the piers, there is over 100 feet of waterway between the abutments; the usual depth of the water is two to three feet; the fall from plaintiff’s property to the bridge is about fifteen feet; between the bridge and plaintiff’s mill are a country bridge and pipe-line, both crossing the stream; there is also a paper-mill dam between.

What was the defendant’s duty in the design and construction of this bridge ? The fact that the ice gorged at the bridge and backed the water on plaintiff’s property, does not of itself fix upon defendant the charge of negligence; plaintiff must go further, and show, that defendant did not construct the bridge with proper care and skill, having regard to the landowners above and below. The case of Pittsburg, etc., Railway Co. v. Gilleland, 56 Pa. 445, a case of alleged negligence in the construction of a culvert, lays down a rule which satisfies both law and reason; we said in that case:

“If the culvert was so unskillfully and negligently constructed as to be insufficient to vent the ordinary high water of the stream, the railroad company building it would have been liable for the injury thereby caused. The apparent facts indicated the duty. The stream, though small, must find a vent or overflow the adjacent land and undermine the railroad. The size, the character of its channel, and the declivity of the circumadjacent territory which forms the watershed, indicated the probable quantity of water to pass through. Proper engineering skill should observe these circumstances and supply the means of avoiding the injury which would result from locking up the natural flow, or obstructing its passage so as to cause a reflux in times of ordinary high water. Beyond this, prudent circumspection cannot be expected to look, and there is, therefore, no liability for extraordinary floods.” This rule was followed in Baltimore & Ohio Railroad Co. v. Sulphur Spring Independent School District, 96 Pa. 65, and Brown v. Pine Creek Railway Co., 183 Pa. 38.

Free access — add to your briefcase to read the full text and ask questions with AI

Berninger v. Sunbury, Hazleton & Wilkes-Barre Railway Co., 53 A. 361, 203 Pa. 516, 1902 Pa. LEXIS 753 (Pa. 1902).

53 A. 361 (Berninger v. Sunbury, Hazleton & Wilkes-Barre Railway Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Sturgeon v. Borough of Oakdale
77 Pa. Super. 448 (Superior Court of Pennsylvania, 1921)
Sebree v. Huntingdon Water Supply Co.
110 A. 142 (Supreme Court of Pennsylvania, 1920)
Reichert v. Northern Pacific Railway Co.
167 N.W. 127 (North Dakota Supreme Court, 1917)
White v. Philadelphia & Reading Railway Co.
46 Pa. Super. 372 (Superior Court of Pennsylvania, 1911)
Metzgar v. Lycoming Township
39 Pa. Super. 602 (Superior Court of Pennsylvania, 1909)
Matteson v. New York Central & Hudson River Railroad
40 Pa. Super. 234 (Superior Court of Pennsylvania, 1909)
Braine v. Northern Central Railway Co.
66 A. 985 (Supreme Court of Pennsylvania, 1907)
Dutton v. Philadelphia, Baltimore & Washington Railroad
32 Pa. Super. 630 (Superior Court of Pennsylvania, 1907)
Taylor v. Canton Township
30 Pa. Super. 305 (Superior Court of Pennsylvania, 1906)
Miller v. Buffalo & Susquehanna Railroad
29 Pa. Super. 515 (Superior Court of Pennsylvania, 1905)