Berman Construction & Development, Inc. v. Carnaval Home, LLC

CourtDistrict Court of Appeal of Florida
DecidedApril 22, 2026
Docket4D2024-2174
StatusPublished

This text of Berman Construction & Development, Inc. v. Carnaval Home, LLC (Berman Construction & Development, Inc. v. Carnaval Home, LLC) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Berman Construction & Development, Inc. v. Carnaval Home, LLC, (Fla. Ct. App. 2026).

Opinion

DISTRICT COURT OF APPEAL OF THE STATE OF FLORIDA FOURTH DISTRICT

BERMAN CONSTRUCTION & DEVELOPMENT, INC., Appellant,

v.

CARNAVAL HOME, LLC, et al., Appellees.

No. 4D2024-2174

[April 22, 2026]

Appeal from the Circuit Court for the Seventeenth Judicial Circuit, Broward County; Keathan Briscoe Frink, Judge; L.T. Case No. 062020CA002555AXXXCE.

Michael A. Rosenberg, George Richard Truitt, Jr., and Mitchell Irving Rozen of Cole, Scott & Kissane, P.A., Plantation, and Mark Boyle and Thomas Evan Shepard of Boyle Leonard Anderson, P.A., Fort Myers, for appellant.

Jesús E. Cuza, Christopher Noel Bellows, and Annelise Del Rivero of Holland & Knight LLP, Miami, for appellee.

SHERMAN, JAMES, Associate Judge.

This case arises from a contract to perform renovations on residential property. The property was destroyed by a fire of unknown origin while the renovations were still in progress. The owner sued the contractor and several subcontractors for damages caused by the fire, resulting in a judgment for the owner. We are required to decide whether the trial court erred in denying the contractor’s request to include an interrogatory question on the verdict form asking whether the contractor should have been excused from performance under the contract’s risk of loss provision as alleged in an affirmative defense. For the reasons set forth below, we find the trial court erred in denying the requested interrogatory question and thus reverse the final judgment and remand for a new trial. BACKGROUND

Carnaval Home, LLC (“the owner”) hired Berman Construction (“the contractor”) to renovate an existing, company-owned home. The contract between the parties set a substantial completion deadline of September 4, 2019.

The contract contained a risk of loss provision placing risk predominantly on the owner:

§ 15.9 Owner shall bear the risk of increased labor and materials costs and material and labor shortages. Owner shall bear the risk of loss, costs and damage to the Work caused by natural disasters, vandalism, arson, insect infestation and perils beyond Contractor’s reasonable control.

The contractor then hired several subcontractors to carry out various aspects of the renovation, including an electrician and project supervisor. On July 29, 2019, with the renovation ninety-percent complete, a fire destroyed the house.

The owner sued the contractor for breach of contract, negligence, and violation of the Florida Building Code. The owner pursued its breach of contract claim primarily under the theory that the contractor had failed to deliver the renovated property by the substantial completion deadline, though additional breaches were raised.

At trial, the parties hotly contested the fire’s cause. The owner presented evidence supporting its theory that faulty wiring in the attic ignited the fire, which spread quickly and engulfed the rest of the home. The contractor, in contrast, contended the fire was caused by arson or another cause beyond its control.

During the charge conference, the contractor requested an interrogatory question on the verdict form regarding the risk of loss provision as well as its other defenses of impossibility of performance and frustration of purpose. After extensive discussion, the trial court granted a directed verdict on the impossibility of performance and frustration of purpose defenses, finding that the express risk of loss provision foreclosed the availability of those equitable defenses. The trial court also denied the contractor’s request to include a risk of loss question on the verdict form.

2 The verdict form submitted to the jury contained questions related to the claims for breach of contract, negligence, and building code violations, respectively. As to the breach of contract claim, the standard form used by the court asked:

1.a. Did [the owner] do all, or substantially all, of the essential things which the contract required it to do?

1.b. Was [the owner] excused from having to do all, or substantially all, of the essential things which the contract required it to do?

2. Did [the contractor] fail to do something essential which the contract required it to do?

3. Was [the owner] damaged by that failure?

The jury found the contractor was not negligent but had violated the building code. However, the jury also found the contractor’s violations did not cause the owner’s damages. Finally, the jury found that the contractor breached the contract and awarded the owner $928,850.00.

The trial court denied the contractor’s post-trial motions and granted the owner’s motion for attorneys’ fees, finding the owner had prevailed on the significant issues.

ANALYSIS

The trial court correctly denied the contractor’s post-trial motion for directed verdict on the breach of contract claim.

We review the denial of a motion for directed verdict de novo. See Wheeler v. City of Fort Lauderdale, 367 So. 3d 525, 527 (Fla. 4th DCA 2023). Absent legal error, the trial court’s denial of a motion for directed verdict must be upheld if competent, substantial evidence supports the verdict for the non-movant. See State Dep’t of Child. & Fam. Servs. v. Amora, 944 So. 2d 431, 435 (Fla. 4th DCA 2006).

The contractor contends a directed verdict was warranted because the owner did not present any evidence establishing the contractor was directly responsible for the fire. Without detailing all the evidence, this claim is undermined by a brief review of the record below.

3 At trial, the owner presented testimony showing that the fire occurred on the day when the electrical work was completed and power was restored to the interior of the house for the first time since construction began approximately ten months earlier. Throughout that time, the home was in the exclusive control of the contractor and its subcontractors. The owner also presented testimony from the carpenter, who was on the project that day, that the lights in the kitchen and family room went out while he was at the property between 5:00 p.m. and 8:00 p.m. This was corroborated by the owner’s principal, Luis Ormo, who testified that when he arrived at the home at 9:00 p.m. that evening, the kitchen and family room lights were off. Ormo further testified that he attempted to turn on all of the lights, but some of them did not work. Finally, the owner presented expert testimony that the fire likely originated in the attic and was not the result of arson.

The contractor disputed the above evidence and offered its own evidence to the contrary. The contractor also advanced its theory that the fire was the result of arson. This included testimony that traces of gasoline were detected after the fire, evidence of unusual burn patterns on the first floor consistent with the presence of an accelerant, heat deformation on the bottom of the door frames, and expert opinion that the fire had multiple points of origin. The contractor also established the fire had engulfed the house and was emanating from the roof just twenty minutes after the owner had left the property. The contractor attempted to persuade the jury that the fire, absent arson, could not have so fully permeated the structure within that short period of time. The contractor also argued to the jury that the electrician and Ormo had dealings apart from and in violation of the contract, suggesting that some of the electrician’s conduct was beyond the contractor’s control.

The contractor directs our attention to what it contends are contradictory findings among the three causes of action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gibson v. Matthews
926 F.2d 532 (Sixth Circuit, 1991)
Crawford v. DiMicco
216 So. 2d 769 (District Court of Appeal of Florida, 1968)
DCF v. Amora
944 So. 2d 431 (District Court of Appeal of Florida, 2006)
PD v. Department of Children and Families
866 So. 2d 100 (District Court of Appeal of Florida, 2004)
FIRST NAT. BANK OF LAKE PARK v. Gay
694 So. 2d 784 (District Court of Appeal of Florida, 1997)
Diana Coba, etc. v. Tricam Industries, Inc.
164 So. 3d 637 (Supreme Court of Florida, 2015)
WESLEY BROWN v. STATE OF FLORIDA
263 So. 3d 48 (District Court of Appeal of Florida, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Berman Construction & Development, Inc. v. Carnaval Home, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/berman-construction-development-inc-v-carnaval-home-llc-fladistctapp-2026.