Bergholtz v. City of Oregon City.

240 P. 225, 116 Or. 18, 1925 Ore. LEXIS 115
CourtOregon Supreme Court
DecidedOctober 1, 1925
StatusPublished
Cited by6 cases

This text of 240 P. 225 (Bergholtz v. City of Oregon City.) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bergholtz v. City of Oregon City., 240 P. 225, 116 Or. 18, 1925 Ore. LEXIS 115 (Or. 1925).

Opinion

BBOWN, J.

The plaintiff is an architect. The defendant is a municipal corporation. By the vote of the people of Oregon City, its charter was amended to provide bonds in the sum of $35,000 for the erection and construction of a city hall. The city council agreed upon a site for the building, and, upon their invitation, the plaintiff, as well as other architects, submitted plans and specifications for the construction of the structure. The plaintiff’s plans and specifications were selected hy the council as suited for the erection of a city hall upon the site chosen, and were adopted upon the condition that the cost of the construction of the proposed building would not exceed the sum of $35,000, the amount authorized. The council enacted an ordinance empowering the mayor and city recorder to execute a contract with plaintiff employing plaintiff, as archi *20 tect, to furnish, plans, specifications and detailed drawings, and to superintend the construction of the building*. The written contract was duly executed and on its execution the defendant paid plaintiff the sum of $300 thereunder.

When this action was instituted, the contract was made a part of the pleadings, and, on the trial of the case, was offered and received in evidence. In explaining to the jury the issue made by the averments of the pleadings, the court said, among other things:

“The said agreement further provides that, in case the work is abandoned before the completion of the same, the plaintiff was to receive for preliminary studies, general drawings, specifications and details, three per cent of the estimated cost of said building; that in pursuance to said agreement the plaintiff did prepare complete plans, working drawings, together with specifications and all necessary details promptly, and submitted the same to the defendant and the same were duly accepted and approved by the said defendant, and the contract for the construction of said building has been let * * .
“The defendant comes in and sets up a copy of the contract actually entered into * * , and, in addition to that, alleges, in effect, that the plaintiff agreed to furnish plans and specifications of a building that could be erected for $35,000, and that the building that would be erected from plans and specifications he furnished would cost much more than that; and consequently that the plans were worthless. * *
“It is agreed that in case the work is abandoned before completion, and I instruct you as a matter of law that the work, meant is the work of the plans and specifications, and superintending of the building, if that work was abandoned, the architect is to be reimbursed as follows: * #
*21 ‘For preliminary studies, general drawings, specifications and details, three per cent, as payment in full for all drawings furnished to date of estimated cost. ’
“I instruct you as a matter of law that that would mean three per cent of the estimated cost of the part of the building for which he had furnished preliminary studies, general drawings, specifications and details. ’
To the construction placed upon the contract by the court in the foregoing instructions, neither the plaintiff nor the defendant objected.

The testimony shows that, at the direction of the city council, the plaintiff advertised for bids for the construction of a city hall, all of which were rejected because they were above the sum of $35,000. Following the receipt of the bids, the plaintiff, at the request of the city council, made changes in his plans and specifications that would have reduced the cost of construction of the building, and there is testimony tending to show that under the revised plans and specifications the city council could have constructed the building for $35,000. The record further shows that the city council notified the architect that he had seven days in which to procure a contractor for the construction of the city hall, but that thereafter it met and rejected the revised plans and specifications for the building and the proposed contract for its construction, thereby paving the way for the selection of a new building site, and decided to submit the question to the legal voters of Oregon City. The subsequent selection of the new site necessitated different plans and specifications for the construction of a suitable building thereon.

The defendant assigns as error the overruling of its motions for nonsuit and directed verdict. It is *22 a rule o.f law that, when a- motion for a nonsuit or a directed verdict is made, the grounds therefor must he precisely and specifically stated in the motion. In the case at bar, the motion was made orally and the grounds for such motion are somewhat involved with the argument in support thereof. A proper case for a directed verdict or a nonsuit is presented whenever the plaintiff has failed to establish by his evidence a prima facie case. Such action, however, is not proper when there are disputed facts to be settled by conflicting evidence. This court has often said that a motion to direct a verdict or grant a nonsuit is in the nature of a demurrer to the evidence and is governed by practically the same rulés. Such a motion concedes as true the evidence adduced in behalf of the plaintiff, with all fair and reasonable intendments to be deduced therefrom. Again, a verdict should not be directed by the court except in cases where the evidence is so plain that reasonable minds could not differ as to the conclusion to be reached: Peabody v. Oregon R. & N. Co., 21 Or. 121 (26 Pac. 1053, 12 L. R. A. 823); Herrick v. Barzee, 96 Or. 357 (190 Pac. 141); Saylor v. Enterprise Elec. Co., 110 Or. 231 (222 Pac. 304, 223 Pac. 725).

“Doubts should in all cases be resolved in favor of the submission of the case to the jury.” 38 Cyc. 1567.

~We cannot say, as a matter of law, that there is an absence of competent evidence to establish the material allegations in the plaintiff’s complaint. The court submitted the ease to the jury with instructions as favorable to the defendant as could have been asked, and the issue was decided against the city. The question involved was prop *23 erly submitted, and we have no legal ground upon which to set the verdict aside. Where an architect submits estimates of the probable cost of a building, it is ordinarily for the jury to say whether his estimate is reasonably near the actual cost: Nelson v. Spooner, 2 F. & F. (Eng.) 613; Williar v. Nagle, 109 Md. 75 (71 Atl. 427, 16 Ann. Cas. 985).

“And where plans are required for a building not to cost more than a certain sum, or are accepted on condition that it can be constructed for a given amount, there can be no recovery by the architect unless the structure can be erected for the sum named, or for an amount reasonably near thereto.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vander Veer v. Toyota Motor Distributors
577 P.2d 1343 (Oregon Supreme Court, 1978)
Remington v. Landolt
541 P.2d 472 (Oregon Supreme Court, 1975)
Western Feed Co. v. Heidloff
370 P.2d 612 (Oregon Supreme Court, 1962)
Laing v. School District No. 10
224 P.2d 923 (Oregon Supreme Court, 1950)
Egli v. Hutton
294 P. 347 (Oregon Supreme Court, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
240 P. 225, 116 Or. 18, 1925 Ore. LEXIS 115, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bergholtz-v-city-of-oregon-city-or-1925.