Bergeron v. Parish Lumber Home Improvements, Inc.

255 So. 2d 163, 1971 La. App. LEXIS 5515
CourtLouisiana Court of Appeal
DecidedNovember 10, 1971
DocketNo. 8582
StatusPublished
Cited by3 cases

This text of 255 So. 2d 163 (Bergeron v. Parish Lumber Home Improvements, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bergeron v. Parish Lumber Home Improvements, Inc., 255 So. 2d 163, 1971 La. App. LEXIS 5515 (La. Ct. App. 1971).

Opinion

BLANCHE, Judge.

This appeal arises out of a suit instituted by plaintiff against defendant to recover damages allegedly sustained by plaintiff as a result of the improper performance by defendant of home improvements and [165]*165remodeling.1 Judgment was rendered in favor of plaintiff and against defendant in the principal sum of $1,700. From this judgment defendant suspensively appealed, assigning several specifications of error. Plaintiff timely answered the appeal, seeking an increase in the award of damages.

The trial judge handed down Written Reasons for Judgment summarizing his findings of fact and conclusions drawn therefrom as follows:

“Plaintiff has brought a suit for damages against Parish Lumber Home Improvement, Inc. contending that the defendant constructed certain additions and improvements to the plaintiff’s residence in an unworkmanlike manner resulting in serious defects and thereby breaching their contractual agreement. It is admitted by the defendant that it entered into a contract with the plaintiff on January 29, 1969 to construct certain additions to plaintiff’s home at 6873 LaSalle Avenue for the sum of $7,000.00. The defendant, however, avers that the additions were constructed in a good and workmanlike manner free from any vices or defects and in accordance with the terms of the contract. A determination of the issues presented by the law suit require an inquiry into the contract entered into between the parties. It stipulates, inter alia:

‘Build additions as per plan and following specifications. Build addition to kitchen, 12x18. Porch, 15x22, and addition to bedroom, 8 x 15. Kitchen and bath additions to match house in foundation and framing and exterior finish. Porch to have concrete floor with polyethylene vapor barrier. Framed for screen with heart redwood. Brick on house and addition sides to height of 4 feet in porch area. All additions unfinished on inside but complete on outside with exception of paint. Plumbing to be roughed in only and a sewer run two feet in cast iron from under the house. Install two new windows in the front and frame for a hall and a closet in the present living room. No electric, plumbing finish or painting included. Level rear section of den floor. $7,000.00; $2,000.00 cash, $5,000.00 FHA Title One Loan.’

“The plaintiff has enumerated four specific complaints in his petition, these being:

“(a) The additions to the rear of the kitchen are not level with the adjoining portions of the house.
“(b) The concrete slab floor of the rear porch is not level.
“(c) The roof line on the outside of the kitchen and dining room walls are uneven and do not match; and,
“(d) The rear section of the den floor is not level.

“In addition to these specific complaints, the plaintiff and his wife related their disapproval concerning other features of defendant’s work. Principal among these were: the ceiling in the den was not level with the remainder of the house; the brick wall between the den and the porch is pitted and improperly finished; weak spot in flooring in doorway between den and kitchen; a dip in corner of porch slab which collects water; and tar dripping from the roof of the porch to the slab below.

“During the trial the court went out and personally inspected the plaintiff’s residence and observed those areas about which there is controversy. It is the [166]*166court’s opinion that most of the plaintiff’s complaints are not of any major consequence, but stem from their dissatisfaction with the defendant’s failure to remedy the outstanding faults in the floor of the den and kitchen in plaintiff’s house.

“The defendant acknowledges that there is a ‘hump’ in the den floor but contends that this was not its responsibility under the contract and that it was only obligated to see that the floor of the new addition was level. Its position is similar in this respect regarding the situation in the kitchen floor. As evidenced by the contract which was signed by both Mr. and Mrs. Berge-ron, Parish was only obligated to ‘level rear section of den floor’ and, if strictly interpreted, their responsibility was limited. Parish certainly was not required to level the floors of the entire house about which it appears there was considerable irregularity. Nonetheless, it is this court’s opinion that based upon the testimony of the craftsman and upon its own inspection that Parish should have done a better job in joining the old section and new sections together so that the difference in levels would be less noticeable. Parish must have considered that they had some professional obligation in this regard, because a limited effort was made to rectify the problem.

“In the opinion of the court the same situation prevails in the kitchen, but to a lesser degree. There is an obvious slope that prevails in the new section of the kitchen. Plaintiff’s witnesses stated that this was merely an optical illusion and that their surveys show that the new section is perfectly level. Nonetheless, the court believes that corrective measures are required to correct this defect. The defendant’s own expert admitted that the ‘weak spot’ in the kitchen was due to poor workmanship and should be corrected.

“The only other defect observed by the court which was of any significance and which was due to poor workmanship is a dip in the concrete surface of the porch. This was obviously collecting water and a pool of water was noted to be standing at this point when the inspection was made. It is true that there is a small irregularity at a point where the old and new roof lines were joined together, but the testimony indicates no attendant structural weakness and there is no obvious deformity requiring corrective measures. Plaintiff’s complaints about the character of the brick work on the porch is not warranted in the court’s opinion. Neither is there any substantial justification for his complaint about the tar drip on the porch. It must be noted that no ceiling has been erected on the porch and if this were done the problem would no doubt disappear.

“In general the plaintiff received what he bargained for under his contract, but he does have cause for complaint against the contractor in some areas in which the contractor had basic responsibility. It would be impossible for the court to itemize the cost of remedying those defects for which the contractor is liable; however, using the testimony of Fred Griggs, general contractor, as a yardstick, it appears that the sum of $1,700.00 would be adequate to compensate the plaintiff as damages for the defendant’s failure to complete the job in a good workmanlike manner.” (Written Reasons for Judgment, Record, pp. 21-24)

Defendant assigns as its first specification of error the awarding by the trial court of damages to plaintiff for alleged items of construction which defendant was not obligated to perform according to the contract between plaintiff and defendant, such as leveling old sections of the house so that the difference between the old unleveled sections and the level new sections would be less noticeable or constructing the new section unlevel so as to more closely match the unlevel old section. This specification of error is without merit. There is ample evidence in the record to support the trial judge’s finding and holding that defendant “should have done a better job in joining the old section and new sections together so that the dif[167]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Merrydale Glass Works, Inc. v. Merriam
349 So. 2d 1315 (Louisiana Court of Appeal, 1977)
Sledge v. Aluminum Specialties Mftg., Inc.
351 So. 2d 835 (Louisiana Court of Appeal, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
255 So. 2d 163, 1971 La. App. LEXIS 5515, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bergeron-v-parish-lumber-home-improvements-inc-lactapp-1971.