Bergeron v. Con-Plex, Inc.

255 So. 2d 397, 1971 La. App. LEXIS 5517
CourtLouisiana Court of Appeal
DecidedNovember 10, 1971
DocketNo. 8377
StatusPublished
Cited by8 cases

This text of 255 So. 2d 397 (Bergeron v. Con-Plex, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bergeron v. Con-Plex, Inc., 255 So. 2d 397, 1971 La. App. LEXIS 5517 (La. Ct. App. 1971).

Opinion

LANDRY, Judge.

Plaintiff brings this action in tort and trespass to recover damages from defendants, The State of Louisiana, Through the Department of Highways (Department) and Con-Plex, Inc. (Contractor), for alleged damages occasioned plaintiff’s turtle farm in the construction of a highway overpass by Contractor pursuant to a contract with the Department. Both defendants third partied each other. The trial court rendered judgment in favor of plaintiff against Contractor only in the sum of $26,609.00; its decree was silent as to the third party demands of defendants. Contractor has appealed praying that the judgment against it be set aside and, alternatively, praying for judgment on its third party demand. Plaintiff has appealed dismissal of its demand against the Department and is also asking for an increase in damages to the sum of $85,000.00. We affirm the judgment holding Contractor liable. We reverse the judgment releasing the Department from liability, and render judgment in favor of plaintiff in reduced amount, and against the Department and Contractor in solido. We also render judgment in favor of the Department against the Contractor on the Department’s third party demand.

Commencing in approximately 1953, plaintiff began operation of a turtle farm near Shreiver, Terrebonne Parish, Louisiana, in a 27 acre borrow pit verbally leased from Southern Pacific Railroad Company. Plaintiff’s turtle farm is situated at the northeast corner of the intersection of the railroad right of way and Louisiana Highway 20. Contractor, subject to the Department’s supervision, constructed the overpass in part upon a 116 foot right of way obtained by the Department from the railroad. The right of way traverses the turtle pond. Numerous pilings which support the overpass are located within the right of way, both within and outside the pond.

Plaintiff constructed his farm by surrounding the borrow pit and adjacent banks with a galvanized iron fence to contain his turtles. Protection of the turtles from marauding raccoons, opossums and other similar predators was accomplished by means of a single strand of energized electric wire which encompassed the fence perimeter. Two strings of electric lights were strung across the pond and burned at night to attract bugs and insects as supplemental turtle feed. Plaintiff placed several hundred cross-ties in the pond for the convenience and accommodation of the turtles. During the years 1953, 1954 and [400]*4001955, plaintiff stocked the pond with 55,000 turtles of the species Pseudemys Scripta Elegans, commonly known as “red eared” or “elegant slider” turtles. During subsequent years some restocking was done by plaintiff, the amount thereof being in dispute.

It is undisputed that the turtles in question spend most of their time in the water, and rarely go on land for any purpose other than egg laying. The laying season extends from March to July each year. Laying usually occurs at dusk or early morning. The females of the species proceed onto dry land for egg laying. They prefer a dry sandy, grassy bank for such purposes. In laying her eggs, the female digs a hole four to ten inches in depth, deposits her eggs therein and covers them with earth. The process takes approximately two to four hours. The species are naturally skittish and therefore easily excitable. Should the female be disturbed by noise or human activity during the laying process, she returns immediately to the water. Actual laying consumes only five per cent of the time required for the nesting process. The remainder of the time is spent in building the nest. A female actually laying eggs will not, if disturbed, return to the water. Females continually prevented by noise or human activity from laying eggs either reabsorb their eggs into their ovaries or abort the eggs into the water where they will not hatch. The most advantageous egg laying area around the pond is situated within 100 to 125 feet of the overpass.

Plaintiff gathered the eggs daily during the laying season. Incubation was achieved by placing the eggs in specially contrived containers and covering them with earth or sand until hatching occurred. Plaintiff engaged a Mr. Fonseca to incubate the eggs for a share of the live turtles produced. Plaintiff also purchased turtles from other producers. Plaintiff sold turtles to pet shops, chain stores and other similar outlets.

During the period 1960 to 1969, plaintiff obtained the following egg production:

Year No. of Eggs Laid No. of Turtles Hatched

1960 121,000 79,854

1961 170,750

1962 126,450 59,916

1963 264,775 158,064

1964 211,698 125,750

1965 262,403 142,288

1966 102,791 57,493

1967 86,435 29,248

1968 5,260 512

1969 As of June 1, duced but hatched. 300 eggs were pro-none as yet have

In 1967, plaintiff sold 84,450 turtles for $20,714.67 or 24.5 cents each. In 1968, 45,548 turtles were sold for a total of $14,916.28, or 32.7 cents apiece.

The construction contract was awarded Contractor on April 19, 1967. Work thereon commenced on or about July 5, 1967. During the fall and winter of 1966, the Department conducted surveying operations in the pond preparatory to advertising for construction bids. In the process of surveying, employees of the Department operated a paddle boat in the pond within and outside the right of way. Contractor and the Department were both aware that plaintiff conducted a turtle farm in the pond in question.

Test pilings were driven by Contractor in October, 1967, two such pilings being located in the pond itself. Pilings were driven by means of a crane and pile driver mounted on barges floated on the pond. The barges were brought to the pond on trailers. To mount a crane and other equipment on the barges, a channel approximately sixty-five feet wide and five feet deep was cut into the pond bank outside the right of way. This excavation was never refilled. Large concrete pilings were stacked on the bank of the pond outside the right of way. Barges were operated by Contractor in the pond both within and without the right of way. A motorboat operated by Contractor in the pond resulted in the death of thirty to forty tur[401]*401ties who were killed by the boat’s propeller. While the bank excavation was open, an unusually heavy rain caused adjacent Bayou Terrebonne to overflow with the result that a large number of turtles escaped from the pond. After the pilings were driven by Contractor, it was necessary to break approximately fifteen inches from the top of each piling. This was done with air hammers. Large chunks of concrete thusly broken off fell into the pond. Plywood forms used in the construction process were allowed to float across virtually the entire surface of the pond. The bank of the pond was removed for a distance of approximately 30 feet within the right of way. Construction activities resulted in destruction of the lighting system and the electric protection wire. The fence in the excavation area was destroyed.

In essence plaintiff testified he rented the pit pursuant to an oral lease, and began his operation approximately 8 to 12 years prior to commencement of construction. He maintained that activities in the pond by the Department and Contractor were detrimental to his endeavor. Despite his protests, no steps were taken to protect the turtles or minimize the disturbance resulting from construction activities. He first noted a decline in egg production in 1966 when the Department’s survey crew operated a boat in the pond.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Riddle v. Fortis Ins. Co.
945 So. 2d 251 (Louisiana Court of Appeal, 2006)
Oswalt v. Irby Const. Co.
424 So. 2d 348 (Louisiana Court of Appeal, 1982)
Jardell v. Sabine Irrigation Co., Inc.
346 So. 2d 1365 (Louisiana Court of Appeal, 1977)
Sick v. Bendix-United Geophysical Corp.
341 So. 2d 1308 (Louisiana Court of Appeal, 1976)
Cane River Needle Art v. Reon, Inc.
335 So. 2d 751 (Louisiana Court of Appeal, 1976)
Lou-Con, Inc. v. Gulf Building Services, Inc.
287 So. 2d 192 (Louisiana Court of Appeal, 1974)
New Orleans Shrimp Co., Inc. v. DUPLANTIS TRUCK L., INC.
283 So. 2d 521 (Louisiana Court of Appeal, 1973)
McKinnon v. Caddo Parish Police Jury
262 So. 2d 834 (Louisiana Court of Appeal, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
255 So. 2d 397, 1971 La. App. LEXIS 5517, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bergeron-v-con-plex-inc-lactapp-1971.