Berger Mfg. Co. v. Huggins

242 F. 853, 155 C.C.A. 411, 1917 U.S. App. LEXIS 1948
CourtCourt of Appeals for the Eighth Circuit
DecidedMay 7, 1917
DocketNo. 4759
StatusPublished
Cited by2 cases

This text of 242 F. 853 (Berger Mfg. Co. v. Huggins) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Berger Mfg. Co. v. Huggins, 242 F. 853, 155 C.C.A. 411, 1917 U.S. App. LEXIS 1948 (8th Cir. 1917).

Opinion

MUNGER, District Judge.

Appellant, the Berger Manufacturing Company, brought suit in the court below against George W. Huggins and the trustees of William Jewell College, seeking to establish and foreclose a mechanic’s lien. Mr. Huggins was a contractor, and had made a successful bid to the trustees for the erection of a dormitory building according to plans and specifications that had been prepared by Felt & Co., architects, for a building not of fireproof material. The Berger Company induced the college trustees to adopt its system of fireproof construction, and the contract as finally entered into between Huggins and the college trustees required the contractor to use the Berger system. Huggins made a written contract with the Berger Company for the installation of its materials and out of the construction of that contract have grown the controversies involved in this suit.

In general, the contract bound the Berger Company to furnish the materials and to put in place the structural steel and iron work, iron stairs, and the metal fireproofing, according to the plans and specifications of the architects and within a time limited. An addendum to these plans and specifications attempted to cover the changes made necessary by the substitution of metal for lumber. The Berger Company was unable to reach a satisfactory settlement for the service and materials it supplied, and filed a lien for the balance it claimed to [855]*855be due. The college trustees have acknowledged owing a balance either to Huggins or the Berger Company, and averred a readiness to pay it to the one to whom it may belong. Huggins has contested the claim of lien of the Berger Company, and has presented a counterclaim. The case was referred to a master, whose findings and report stated an account between Huggins and the Berger Company, found a balance due to Huggins, and disallowed the lien.

The trial court, after argument on exceptions to the report, entered a decree canceling the lien, and awarding a balance to Huggins. The court disallowed some items found to be due by the master and allowed some items the master had rejected. The briefs cover a wide field in argument, but the real issues of the case are found in smaller area. One of the master’s findings, approved by the court, allowed the sum of $1,500 to Huggins because the Berger Company delayed in the performance of the work. The contract required the work to be begun at once, to be done within three months, and to 'be so performed as not to cause any delay or inconvenience in other construction work. Appellant contends that it caused no delays that-injured Huggins, but was itself delayed by him. A number of claimed delays are in issue. The evidence has been examined relating to them, and no useful purpose would be served by detailing it, as questions of fact only are involved. It is sufficient to sustain the findings of the master, approved by the court, that the delays were the fault of the Berger Company, and that the contractor complied with the requirements of his contract. The decree allowed this amount as the difference between the cost of construction paid by Huggins and the amount it would have cost Huggins to perform this work, if the Berger Company had not delayed and disorganized it. The only evidence offered on the 'amount of these damages was given on behalf of Huggins, and would have supported a much larger credit allowance to him. The appellant invokes the rule that damages will not be apportioned between parties in mutual fault, but the finding that there was no delay by Huggins renders the rule inapplicable.

[1,2] The master and the trial court allowed two items of, damages against the Berger Company for the expense of reconstructing floors, the roof, and other portions of the building, which the Berger Company had undertaken to construct. The joists of these floors were spaced at a distance between centers that the Berger Company claimed was in compliance with plans which it had submitted to the architect and he had approved before the work was begun. After the joists were placed the contractor had a test made, and found a deflection that he reported to the architect. The architect disapproved of the proposed construction and required a reinforcement of the joists. The Berger Company was notified of this decision, but failed to supply the additional members, and the contractor, following the architect’s direction, incurred the expense mentioned. There were a number of provisions in the contract of the Berger Company subjecting the work to the approval of the architects. Among them was the following:

‘•In case any oí said work done or materials provided by tlio said party of the second part shall be unsatisfactory to the architects, then the said party [856]*856of the second part will, on being notified thereof by the architects, or general contractor, immediately remove such unsatisfactory work or materials, and supply the place thereof with other work and materials satisfactory to the architects or general contractor.”
“If any question should arise during the progress of the work or in the settlement of accounts, it is to be referred to the architects, whose decision shall be binding upon both parties; but there is reserved the right of final decision in all such questions by two disinterested parties, one chosen by each party to this agreement, at his own' expense, and in the event of the parties so chosen failing to agree, they are to have the power to choose a third at the joint expense of both parties hereto; and the decision of two of the referees so chosen shall be binding on both parties.”

In the original specifications there was a certain test provided for the concrete floors then contemplated, to be made after the floors had been in place for 45 days, and the Berger Company contends that this test was the limit of the architect’s authority. The provisions quoted from the contract refute this contention. The preliminary approval of the Berger Company plans was not the only permissible use of the architect’s discretion, for the contract allowed the condemnation of “work done or materials provided.” _ Neither was the judgment of the architect required to be based on any particular tests. The amount of deflection of tire floor joists when the test load was applied to them, and the probable effect of that deflection upon the terazzo floors ft} be laid upon them, when such floors should be put to the strain of use, justified the architect in condemning them and in avoiding the delay that would ensue if the floors were finished before a test was made. Some criticism is made of the method employed in making a test of the roof material, but the architect’s decision does not depend upon the results of this test. As the parties committed their work to the satisfaction of an arbiter, his judgment, when reached in the exercise of good faith is conclusive. Kihlberg v. United States, 97 U. S. 398, 24 L. Ed. 1106; Martinsburg & Potomac R. R. Co. v. March, 114 U. S. 549, 5 Sup. Ct. 1035, 29 L. Ed. 255; United States v. Hurley, 182 Fed. 776, 105 C. C. A. 208; Frisco Lumber Co. v. Hodge, 218 Fed. 778, 134 C. C. A. 456. The amount allowed because of these deficiencies was not the subject of an exception by the Berger Company.

[3] The court affirmed an allowance of a credit to Huggins for the failure of the Berger Company to furnish some gas pipe railings and thresholds.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
242 F. 853, 155 C.C.A. 411, 1917 U.S. App. LEXIS 1948, Counsel Stack Legal Research, https://law.counselstack.com/opinion/berger-mfg-co-v-huggins-ca8-1917.