Berger Engineering Co. v. Hopkins

340 P.2d 777, 54 Wash. 2d 300, 1959 Wash. LEXIS 397
CourtWashington Supreme Court
DecidedJune 11, 1959
Docket34762
StatusPublished
Cited by12 cases

This text of 340 P.2d 777 (Berger Engineering Co. v. Hopkins) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Berger Engineering Co. v. Hopkins, 340 P.2d 777, 54 Wash. 2d 300, 1959 Wash. LEXIS 397 (Wash. 1959).

Opinion

Ott, J.

June 1, 1955, the 143rd & Greenwood Corporation and E & M Incorporated, hereinafter referred to as E & M, entered into an agreement with Charles W. Hopkins, a building contractor, doing business as C. Hopkins & Associates, hereinafter referred to as Hopkins, for the construction of a four-unit doctors’ clinic. The contract provided for a curtain wall fabricated of aluminum bars, designed to hold the aluminum window frames in place, together with aluminum exterior panels which were to be bonded with glue to a backing of eleven-sixteenths inch insulating Cemesto board.

June 3rd, Hopkins subcontracted the aluminum panels and window frame installation to Berger Engineering Company and Seattle Bronze, Inc., doing business as Tecler Aluminum. The joint subcontractors will hereinafter be referred to as Tecler. Tecler’s shop drawings of the proposed aluminum installation were approved by Kenneth S. Ripley, architect for E & M. Ripley will be hereinafter referred to as the architect. Both contracts provided for the architect’s approval of the completed work before final payment.

Tecler performed its portion of the contract and, on September 22nd, requested payment from Hopkins. September 30th, Tecler’s attorney made a second demand for pay *304 ment from Hopkins and stated that, if payment was not made within five days, a lien would be filed. October 6th, Tecler filed its claim of lien for the full contract price of $5,498. October 7th, Hopkins furnished Tecler with an “acceptance slip” to be signed by the architect, as required by the contract. October 18th, Tecler forwarded the “acceptance slip” to the architect for his signature. October 26th, the architect specified in writing seven items of imperfections in the aluminum work, which he requested be corrected prior to acceptance. •

Tecler attempted to overcome six of the architect’s objections. With reference to the remaining objection, which related to several of the aluminum panels that had bulged or blistered, Tecler, in a letter to the architect dated November 21, 1955, stated as follows:

“This leaves number 6 — we have examined the panels and can state that they were fabricated with the best shop practice and materials. In this connection, we had the advice of the people who manufacture the adhesive material, and followed their suggested procedures. We can think of nothing that will improve these panels, and believe that they are manufactured to the proper standards.”

Tecler received no answer from the architect and, on December 8th, wrote him as follows:

“At your convenience will you please examine the E and M Clinic Building and let us have your certification of acceptance on the form we have previously sent you.”

The architect did not answer the letters, and refused to negotiate further with Tecler, but continued to correspond with Hopkins, as provided by the contract.

January 13, 1956, E & M and Hopkins settled and compromised, by written agreement, the extras and remaining balance due on the Hopkins contract, except for the alleged damages E & M claimed from Hopkins for improper workmanship, for its failure to complete the building within the time limit, and for Tecler’s defective aluminum work. With reference to the Tecler item,'the settlement'agreement provided: .

“It is understood and agreed that the owner [E & M] is *305 retaining and is authorized to retain the sum of $5498.00 as security for its damages and to secure and indemnify the owner against any costs, expenses or loss on account of the lien heretofore filed by Tecler Aluminum Co., the contractor [Hopkins] having expressly contested the amount and validity of the said lien.”

March 16, 1956, Tecler filed its complaint, asking for judgment against Hopkins, on its first cause of action, for the full amount due on its subcontract, and, on its second cause of action, for foreclosure of its lien upon the E & M property and for attorneys’ fees.

Thereafter, the attorneys representing the various parties corresponded relative to the defective aluminum work. The attorneys for E & M demanded of Hopkins that the defects be corrected. The demands were forwarded to the attorneys for Tecler.

April 16, 1956, Hopkins answered the complaint of Tecler, in accordance with its contract and compromise agreement with E & M, and denied that any payment was due Tecler from Hopkins or E & M.

April 17, 1956, E & M answered Tecler’s complaint, denied liability and alleged, as an affirmative defense, defective workmanship and lack of the architect’s approval. E & M cross-complained against Hopkins alleging (1) $3,500 in damages for the repair of Tecler’s defective aluminum work, (2) $7,200 in damages for loss of rent due to the delay in completion of the building, and (3) $4,500 in damages for decrease in the market value of the building due to irreparable defects in workmanship.

April 25th, the attorneys for E & M wrote to Hopkins’ attorney as follows:

“We have received no response to our letters of April 10 and April 17, requesting that action be taken to correct the defective aluminum work at the above premises. Please be advised that the owner will take such steps as are possible to remedy these defects, with the purpose of rendering the building tenantable, if possible, and minimizing damages, and will hold you for the costs as well as for damages for those defects in construction which cannot be remedied.”

*306 April 26th, the attorney .for Hopkins wrote the following letter to Tecler’s attorney:

“On April 12th and April 20th I advised you of the demands made by 143rd and Greenwood Clinic for remedying the aluminum defects on their building. Today I have received another demand for remedying such defects, coupled with a notice that the 143rd and Greenwood clinic will proceed to remedy these defects as are possible so as to make the building tenantable. Copy of their letter is enclosed herewith.
“I would appreciate being advised if your client, Tecler Aluminum, intends to do anything on these requests. If they do not, then either my client or the owners would be within their rights in remedying these defects and doing so without waiving any rights or claims against Tecler.
“If your client is, however, intending to take some action on these requests, we believe he should advise us immediately of what he intends to do and when. In the absence of any notice from you by April 30th, we will interpret that to mean that Tecler will not comply with our previous request and the one herein to remedy the defects and minimize the damage.”

May 8th, the attorney for Tecler replied to this letter as follows:

"... We are prepared, in any event, to show substantial compliance with all of the specifications and drawings rendered by Mr. Ripley or approved by Mr. Ripley for use in the building.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Of Washington, V James John O'hagan
Court of Appeals of Washington, 2019
In re the Marriage of Tobias M. Lynn & Amanda S. Lynn
Court of Appeals of Washington, 2013
Clallam County v. Dry Creek Coalition
161 Wash. App. 366 (Court of Appeals of Washington, 2011)
J.L. Storedahl & Sons, Inc. v. Cowlitz County
103 P.3d 802 (Court of Appeals of Washington, 2004)
State Ex Rel. Lige & Wm. B. Dickson Co. v. County of Pierce
829 P.2d 217 (Court of Appeals of Washington, 1992)
In Re the Adoption of Reinius
346 P.2d 672 (Washington Supreme Court, 1959)
Choate v. Swanson
344 P.2d 502 (Washington Supreme Court, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
340 P.2d 777, 54 Wash. 2d 300, 1959 Wash. LEXIS 397, Counsel Stack Legal Research, https://law.counselstack.com/opinion/berger-engineering-co-v-hopkins-wash-1959.